18-General Notices, Notes and Information.pdf

PDF 3 MB Posted

Attached to
ITB - Roadway Improvements on Avenue G from Texas Avenue to Allen Genoa Road in South Houston (2024) for Harris County Precinct 2
Solicitation number
26/0026
Issued by
Harris County, Texas

About this file

This is a General Notices, Notes and Information document prepared by Harris County Precinct 2 Engineering Department for a roadway improvement project in South Houston. The project involves converting Avenue G from Texas Avenue to Allen Genoa Road (approximately 1 mile in length) from a two-way, two-lane asphalt road to a one-way, one-lane asphalt road with the addition of 5-foot-wide concrete sidewalks with pedestrian lighting on both sides. The scope of work includes construction of approximately 22,255 square yards of new asphalt pavement, approximately 2.5 miles of sidewalk installation, drainage improvements, utility coordination and relocation as needed, traffic control implementation, site stabilization, and final site cleanup. The project is classified as UPIN 240102MF3HS01 and is located within the City of South Houston. The contract time for completion is 180 working days (consecutive calendar days), and the contractor must use BEYOND SOLAR solar-powered pedestrian bollards or engineer-approved equivalents for the project lighting.

The project requires compliance with Harris County 2023 Standard Specifications, Harris County Flood Control District 2020 Standard Specifications, TxDOT 2014 Standard Specifications, and City of Houston Standard Specifications as applicable. A minimum of 25% of the work must be performed by the bidder, and contract price increases are limited to 25% of the original bid amount, with decreases requiring contractor consent if 18% or greater. The contractor is responsible for damages to existing utilities including CenterPoint, AT&T, and City of South Houston utility lines. Environmental compliance is mandatory, including storm water pollution prevention planning based on project disturbance acreage, compliance with cultural resource and hazardous materials requirements, and coordination with the City of South Houston and nearby schools regarding construction scheduling. The contractor must maintain records using Harris County's e-Builder construction program management software and provide a pre-construction list of all suppliers and subcontractors with contact information.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Preparer’s Certification for

Specifications, Special Specifications, Special

Provisions, Estimate and Specification Data

Special Note:

The following items developed per the published Construction Drawings have been verified and included in the Purchasing Department’s Bid

Specification Package, which can be found on Bonfire.

The items include:

• Pricing/Delivery Information

• Scope of Work

• Special Provision to Standard Specifications

• Special Specifications

• Supplement to General Requirements

• Contract Time

Firm Registration No. F-1386

11821 E. FWY Suite 360 Houston, TX 77029

FOR:

Roadway Improvements –

South Houston - 2024

Harris County Precinct 2

UPIN# 240102MF3HS01

https://harriscountytx.bonfirehub.com/portal/?tab=openOpportunities kvincent Snapshot

TABLE OF CONTENTS

1. Scope of Work

2. General Notice to Contractors

3. General Notes

4. Notice to Contractors- TBPE Policy

5. Notice to Contractors- Material Hauling

6. Notice to Contractors- Storm Water Quality and Environmental Issues

7. Notice to Specifications

8. SPARK LIGHTING Special Spec

ROADWAY IMPROVEMENTS - SOUTH HOUSTON - 2024 -PRECINCT 2

UPIN No. 240102MF3HS01

SCOPE OF WORK

SUMMARY

A. Avenue G Roadway Improvements – The “South Houston 2024” project site consists of converting Avenue G from Texas Avenue to Allen Genoa within the City of South Houston (Project overall length approximately 1 mile long) from a two-way-two-lane asphalt road to a one way one-way-one-lane asphalt road. After the removal of a section of width of Avenue G this will allow room for the installation of a 5-foot-wide sidewalk with pedestrian lighting alongside the length of Avenue G on both the North and South sides of the approximate 5,185 LF drainage ditch for pedestrian traffic to stay outside of the vehicular travel path. This will enhance safety and walkability within the underserved South Houston neighborhood.

B.

C. The overall objective for this project is to remove the existing two-way road and replace it with a one-way 13,795 sq-yd asphalt road and a new 5-ft concrete sidewalk.

D. The “Time of Completion” of this construction contract will be 180 working days

(defined as consecutive calendar days).

E. The Contractor is to use the BEYOND SOLAR solar-powered Pedestrian Bollard or an approved equivalent pavement to be approved by the Engineer.

CONTRACTOR’S USE OF RIGHT-OF-WAY

A. Access: The Harris County Engineering Department – Recovery and Resiliency Division (“HCED - RRD”) has acquired adequate right-of-way for access to the job.

Refer to the Plans for the location of the right-of-way limits. The access point into and out of the project site is off Texas St.

B. Work Area: The work area is defined as the project right-of-way or construction area within the project right-of-way identified on the Plan.

WORK SEQUENCE

The project consists of the construction of 22,255 sq-yds of new asphalt pavement as well as approximately 2.5 miles of sidewalk that follows the drainage ditch between South Avenue G and North Avenue G. The sequence of major work activities is as follows:

1. Conduct a site walk with the Engineer to review the existing ground survey and identify areas and sections of concern.

2. Set up erosion and sediment controls and conduct continuous inspection and update to SWPPP.

3. Develop and submit the Traffic Control Plan for approval. Coordinate with nearby schools and essential services to ensure no impact to traffic during active construction hours.

4. Implement approved Traffic Control Plan and construct necessary. The development and implementation of traffic control plan is incidental to Item 694.01.

5. Contractor will contact the City of South Houston to coordinate construction activities and lay down yard. The primary contact for the City of South Houston will be Lance Avant (713) 947-7700.

6. Coordinate with utility owners prior to construction near existing utilities.

7. Relocate existing utilities which conflict with the proposed construction as shown on the Plans.

8. Brace any power poles or light poles as necessary for the construction of the project due to the means and methods of the construction. This is incidental to the contractors’ work to be performed.

9. Remove any existing obstructions to new pavement stabilization and installation, including asphalt pavement, driveways, culverts, sidewalks, signs, mailboxes etc.

10. Ensure drainage is maintained to equal or better conditions than before construction started as well as during construction for temporary drainage installations.

11. Convert south side and north side lanes of traffic to one way in the orientation of the final proposed flow of traffic.

12. Begin construction on lane of traffic between residential driveways and the existing half of the road closest to the drainage ditch. Ensure existing half of asphalt road will remain for temporary access and allows vehicular driveway access. Contractor shall complete entire section of road on north or south side as well as the sidewalk before beginning on the opposite side. Only one side of the ditch shall have active construction at a time.

13. Perform sub-grade stabilization in accordance with the project geotechnical report. Approved stabilization materials include cement or lime-fly ash. The contractor shall furnish all labor, materials, equipment, and incidentals necessary to complete the stabilization work. Payment will be based on the type of stabilization material used.

14. After Pulvamix is stabilized and asphalt overlay is placed next to driveways with driveway ties ins completed, excavation and removal of the leftover section of road can commence per geotechnical requirements in the plans.

15. Place select fill as required by plans within the void from the old section of road and prepare the sidewalk alongside avenue G.

16. Place concrete as shown in plans for the new sidewalk that runs along the new road layout.

17. Repeat steps 13 – 16 for the opposite side of the project to complete the parallel construction of Avenue G.

18. Conduct necessary site drainage and water/sediment controls throughout the construction period to ensure no stormwater impact to local communities or receiving water bodies.

19. Regrade the area between the ditch to the sidewalk as well as the sidewalk to the roadway per plans and ensure positive drainage. Modify ROW grading as necessary to prevent ponding and ensure unobstructed ditch flow to nearby inlets.

20. Construct proposed lighting along the proposed sidewalk.

21. Place proposed intersection striping in accordance with the Plans.

22. Finalize grading and stabilize the site with sodding.

23. After turf establishment is complete and site has been stabilized, remove stormwater pollution protection items and clean up the site of construction materials as needed. Haul debris to landfill.

24. Remove traffic control devices along and enhancements along Avenue G.

25. Remove any additional trash or debris in the project area.

REQUIRED QUALIFICATIONS

A. Manufacturer’s Qualifications: Manufacturer with a minimum of five years documented experience with products specified.

B. Installer Qualifications: Installer experienced in performing work of this section that has specialized in installation of work similar to that required for this project. Installer must also be able to provide skilled workman with satisfactory record of performance. Contractors must demonstrate prior experience with Spark Lighting products or other equivalent, engineering-approved products.

PROTECT EXISTING UTILITIES

A. Contractor is responsible for any damage to existing utilities in the project area.

There are also CenterPoint, AT&T, and City of South Houston utility lines in the project area. If any existing utilities need to be relocated or are damaged during construction, the Contractor is to contact the utility owner to resolve the issue.

GENERAL NOTICE TO CONTRACTORS

In accordance with House Bill 1059, a minimum of 25% of the work to be performed on this project shall be performed by the Bidder.

Special Notice: By law, the original price on firm fixed price contracts may not be increased by more than 25%. The original price may not be decreased by 18% or more without the consent of the contractor. Please monitor additions to your contract -additions in excess of 25% will not be paid under any circumstances.

On public works projects, all contractors shall supply a list of all suppliers and subcontractors with addresses and phone numbers, prior to work commencing.

At the time of the scheduled preconstruction meeting, the successful bidder shall supply to the County a list of representatives signed by an Officer of the Company who are authorized to sign official documents, i.e., Purchase Orders, Change Orders, Final Estimates, etc.

In determining who is a responsible bidder, Harris County may take into account the past performance of the bidder on Harris County projects. Commissioners Court adopted a written definition and criteria for determining the performance of a contractor which may be considered in determining the responsibility of a bidder.

Harris County is using an internet-based Construction Program Management Software, e-Builder to maintain consistent administrative and technical control for its projects throughout the County. The Contractor is required to use e-Builder on this project in accordance with procedures provided by the County.

At no cost to the Contractor, the County will provide system login account(s) and provide training for Contractor personnel. The Contractor must update e-Builder with any new or changed information within 24 hours of that information becoming known to Contractor. The Contractor must have access to a computer with internet access and a scanner to use eBuilder.

May 2019

NOTICE TO CONTRACTORS

ON STORM WATER QUALITY AND

ENVIRONMENTAL ISSUES

In addition to the regulatory requirements stated in the General Conditions, the Contractor shall recognize and comply with the following:

SECTION 1. STORM WATER POLLUTION PREVENTION PLANS

A. COVERAGE

Coverage under the Texas Pollutant Discharge Elimination System (TPDES)

General Permit TXR150000 for storm water discharges associated with construction activities is required for a project that disturbs 1 acre or greater (or is a part of a larger common plan of development with the potential to disturb 1 acre or greater). Coverage requires the preparation, implementation, inspection, and maintenance of a Storm Water Pollution Prevention Plan (SWPPP), in accordance with the TPDES General Permit.

B. PROJECT CLASSIFICATION

This project is classified as one of three categories listed below. The

Contractor shall be responsible for the storm water quality items, accordingly.

1. “Construction Sites That Do Not Require TPDES General Permit

Coverage” The project disturbs less than 1 acre (and is not part of a common plan of development with the potential to disturb 1 acre or more); therefore, coverage under the TPDES General Permit is not required. However, the Contractor shall implement good housekeeping measures to minimize the potential for pollutants, associated with the construction activities, to enter the storm sewer system. Item 725, “General Source Controls”, shall be implemented by the Contractor, as well as any other erosion, sedimentation, and pollution controls shown in the plans and project manual.

or

2. “Small Construction Sites”

The project disturbs 1 acre or more, but less than 5 acres, (or is part of a common plan of development with the potential to disturb 1 acre or more);

therefore, coverage under the TPDES General Permit is required. The Contractor shall implement, inspect, and maintain the Storm Water Pollution Prevention Plan shown in the plans and project manual.

Certification of a TCEQ Small Construction Site Notice (CSN) in accordance with Part II.E.2 of the TPDES General Permit is required. The Contractor, as a primary operator, as defined by TPDES General Permit, shall certify one Construction Site Notice (CSN) and provide this to Harris County at the time that the contract is awarded. Harris County (owner), as primary operator, as defined by TPDES General Permit, shall certify a second Construction Site Notice (CSN) at the time the contract is awarded. After the project is awarded, Harris County shall provide copies of the two certified Construction Site Notices (CSN) to the Contractor, and send copies to the local storm sewer operator for notification purposes. Prior to commencing construction activities, the Contractor shall laminate and post the notices on the project site in a location where they are readily available for public viewing. The Contractor shall maintain the posted notices until after completion of the construction activities and final stabilization of the project site as defined by the TPDES General Permit. When the project is completed and stabilization is achieved, as defined by the TPDES General Permit, then the Contractor shall note the date that the Small Construction Site Notice was removed from the project site. A copy of the completed Small Construction Site Notice shall be provided to the Engineer with the SWPPP records. The County shall then notify the local storm sewer operator that storm water associated with construction activities is no longer being discharged from the site.

3. “Large Construction Sites”

The project disturbs 5 acres or greater (or is part of a common plan of development with the potential to disturb 5 acres or more); therefore, coverage under the TPDES General Permit is required. The Contractor shall implement, inspect, and maintain the Storm Water Pollution Prevention Plan shown in the plans and project manual. Certification of a Notice of Intent (NOI) in accordance with Part II.E.3 of the TPDES General Permit is required and shall be completed in accordance with Harris County Specification Item Number 700. The Contractor shall not commence with any earth disturbing activities on the project site until:

• at least seven (7) days after submittal of the NOI (Harris County & Contractors) via U.S. Postal Service, or if Utilizing electronic submittal, prior to commencing construction activities,

• copies of signed NOI’s are submitted to any municipal separate storm sewer system (MS4) receiving discharge, at least seven (7) days prior to commencing construction activities. Contractor shall list in the SWPPP the names and addresses of all MS4 operators receiving a copy.

• copies of the Certified NOI’s are posted in a publicly accessible location (copies shall be laminated or placed in weather resistant display case),

• and copies (Harris County & Primary Contractors) of construction site notice for large sites (CSN) are posted in a publicly accessible location. After construction activities are complete and final stabilization is achieved (as defined by the TPDES General Permit), the Contractor shall certify one Notice of Termination (NOT) form and provide it to Harris County. Harris County shall certify a second NOT form. Harris County shall submit the two NOTs to the TCEQ and the local storm sewer system operator. After the NOTs have been submitted to the TCEQ, then the Contractor shall remove all temporary SWPPP controls, cease SWPPP inspections, and deliver copies of all SWPPP records to the Engineer who shall archive them for a minimum of three years. The final payment to the Contractor may be held until all SWPPP records are received by the Engineer.

SECTION 2. STORM WATER QUALITY MANAGEMENT PLANS

A. COVERAGE

If this project meets the definition of “new development” or “significant redevelopment” as defined in the Harris County regulations or City of Houston ordinance on storm water quality and the project is not “grandfathered” or “exempt” as defined by the regulation or ordinance, then a Storm Water Quality Management Plan (SWQMP) is required for the project, as shown in the construction plans.

B. CLASSIFICATION

This project is classified as one of three categories listed below. The Contractor shall be responsible for the storm water quality items, accordingly.

1. “SWQ Permit Within Unincorporated Harris County”

If a Storm Water Quality Management Plan with permanent storm water quality controls is shown in the construction plans and the project is located in unincorporated Harris County, then a Storm Water Quality Management Plan is required prior to the start of construction. Prior to the start of construction, the Engineer shall submit the plans and Written Storm Water Quality Management Plan to the Harris County Permits Group and obtain the necessary signatures acknowledging acceptance of the Storm Water Quality Management Plan. The Contractor shall construct the SWQMP structural controls in accordance with the construction plans, and maintain the SWQMP structural controls until completion of the project and until the Engineer can certify that the SWQMP structural controls are constructed in accordance with the plans.

2. “SWQ Permit Within City of Houston” If a Storm Water Quality Management Plan with permanent storm water quality controls is shown in the construction plans and the project is located in the jurisdiction of the City of Houston, then a Storm Water Quality Management Permit is required prior to the start of construction.

Prior to the start of construction, the Engineer shall submit to the City of Houston the construction plans, the City of Houston Storm Water Quality Management Plan Application for Permit, and all other related documents shown on the permit application and obtain the Storm Water Quality Management Permit. Prior to the start of construction, the Contractor shall post a performance bond to the City of Houston for the construction of the storm water quality structural controls. The Contractor shall post a copy of the issued permit on the project site, construct the SWQMP structural controls in accordance with the construction plans, and maintain the SWQMP structural controls until completion of the project and until the Engineer can certify that the SWQMP structural controls are constructed in accordance with the plans.

The Engineer shall submit the Storm Water Quality Permit As-built Certificate to the City of Houston and Harris County shall begin implementation of the SWQMP.

3. “Grandfathered or Exempt from SWQ Permit” or “Storm Water Quality

Bank” If a Storm Water Quality Management Plan, or permanent storm water quality feature, is not shown in the construction plans, then a Storm Water Quality Management Permit is not required prior to the start of construction because it is grandfathered, exempt, or has provided storm water quality measures through the Storm Water Quality Bank.

SECTION 3. OTHER ENVIRONMENTAL ISSUES

A. BIOLOGICAL ISSUES

In accordance with requirements under the federal Migratory Bird Treaty Act, if in the course of construction, a bird rookery, an identified special migratory bird habitat, or a nesting site is discovered on the project site, then the Contractor shall cease work in the area and immediately notify the Engineer.

In accordance with the Federal Endangered Species Act and the Texas Parks and Wildlife Code, if a biological mitigation plan for specially protected flora and fauna species has been provided within the construction plans, then the Contractor shall comply with all requirements noted within the plan.

B. WATERS OF THE UNITED STATES INCLUDING ADJACENT WETLANDS

In accordance with Section 404 and Section 401 of the Clean Water Act and Section 10 of the Rivers and Harbors Act, waters of the United States including adjacent wetlands shall not be impacted by the Contractor unless a Department of the Army Permit has been obtained from the U.S. Army Corps of Engineers for the project.

If Harris County has obtained a Department of the Army Permit for this project, a copy of the permit is provided in the project manual. The Contractor shall comply with all requirements of the Department of the Army Permit. The Contractor shall not impact any waters of the United States and adjacent wetlands greater than the area and volume shown in the permit. If the Contractor impacts waters of the United States including adjacent wetlands on the project site that exceeds the area and volume shown in the permit, then the Contractor shall be responsible for any violations that may be issued by the regulatory agencies. If the Contractor deems it necessary to impact waters of the United States including adjacent wetlands that exceed the permit, then the Contractor must first notify the Engineer and the Engineer may obtain the necessary regulatory clearances prior to allowing the additional impacts to occur.

During construction of the project, if the Contractor uses off-site areas (not owned by Harris County) for placement of borrow material, disposal of construction debris, staging of construction materials, usage as a field office, or other types of construction related activities, then the Contractor shall be solely responsible for obtaining all environmental permits for the off-site activity, as well as providing all environmental controls and compensatory mitigation requested by the permitting agency. If a regulatory violation occurs as a result of this off-site activity, then the Contractor shall be solely responsible for this violation.

C. STATE OWNED SUBMERGED LANDS

The Contractor shall not impact submerged lands regulated under the authority of the Texas General Land Office, or other local agency, without an easement agreement. If an easement agreement is necessary for the construction activities, then the easement agreement shall be obtained by Harris County.

D. CULTURAL RESOURCES

In accordance with the National Historic Preservation Act and the Antiquities Code of Texas, the Contractor shall not remove or disturb, or cause or permit to be removed or disturbed, any historical, archeological, architectural, or other cultural artifacts, relics, vestiges, remains, or objects of antiquity from the project site. In the event that such items are discovered on the project during construction activities, the Contractor shall immediately notify the Engineer. The site and the potentially significant material shall be protected by the Contractor from further disturbance until a professional examination of them can be made and/or until clearance to proceed with construction has been provided by the Engineer.

E. HAZARDOUS AND PETROLEUM SUBSTANCES

If during the course of construction, the Contractor discovers hazardous or petroleum substances or wastes on the project site, then the Contractor shall immediately cease work in the area and remove all personnel from the area. The contractor shall temporarily close the area to the public, as well; temporary fencing or caution tape shall be installed around the area. The Contractor shall notify the Engineer immediately. Work in the area shall not be permitted until the Engineer has determined that safety and environmental issues have been properly addressed.

NOTICE OF SPECIFICATIONS

For the construction of this project, the Contractor shall use the attached Special Provisions, Special Specifications, and Harris County Engineering Department (HCED) Specifications Book – 2023 Harris County Standard Specifications for the Construction of Roads and Bridges, effective date October 10, 2023. The current HCED specifications may be found at the HCED website: https://www.eng.hctx.net/Consultants/Standards- Specifications/Standard-Engineering-Design-Specifications

When applicable, the Contractor shall use the Harris County Flood Control District (HCFCD) 2020 Standard Specifications Book. The current HCFCD specifications may be found at the HCFCD website: https://www.hcfcd.org/Resources/Technical-Manuals/Standard- Specifications-Related-Drawings?folderId=15985&view=gridview&pageSize=10

When applicable, the Contractor shall also use the Texas Department of Transportation (TxDOT) 2014 Standard Specifications Book. The current TxDOT specifications may be found at the TxDOT website: https://www.txdot.gov/business/resources/txdot-specifications.html

When applicable, the Contractor shall also use the City of Houston (COH) Standard Specifications. The current COH specifications may be found at the COH website:

https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards https://www.eng.hctx.net/Consultants/Standards-Specifications/Standard-Engineering-Design-Specifications https://www.eng.hctx.net/Consultants/Standards-Specifications/Standard-Engineering-Design-Specifications https://www.hcfcd.org/Resources/Technical-Manuals/Standard-Specifications-Related-Drawings?folderId=15985&view=gridview&pageSize=10 https://www.hcfcd.org/Resources/Technical-Manuals/Standard-Specifications-Related-Drawings?folderId=15985&view=gridview&pageSize=10 https://www.txdot.gov/business/resources/txdot-specifications.html https://www.txdot.gov/business/resources/txdot-specifications.html https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards

Spark Lighting (TECL: 32741) 9135 Spring Branch Dr., Suite 202

Houston, TX 77080 832-413-2551

Harris County Precinct Two November 3, 2023 Leonel Castillo CC Solar Page 39 of 51 Spark Lighting, LLC

*CONFIDENTIAL DOCUMENT*

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 40 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 41 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 42 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 43 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 44 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 45 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 46 of 51 Spark Lighting, LLC

Regulated by The Texas Department of Licensing and Regulation, P. O. Box 12157, Austin, Texas 78711, 1-800-803-9202, 512-463-6599; website: www.tdlr.texas.gov

Leonel Castillo CC Solar Page 47 of 51 Spark Lighting, LLC