This Scope of Work document pertains to the Oregon Department of Corrections (ODOC) and outlines the warehouse re-roofing and building improvements project at the Oregon State Correctional Institution (OSCI) located at 3405 Deer Park Drive SE, Salem, Oregon. The project encompasses roof demolition and replacement of the existing 24-year-old roofing system, skylight replacement, roof equipment curbs and sleepers replacement, new ladder procurement and installation, roof and overflow drain replacement with new piping and insulation, new sheet metal flashing and trim, walk pads, fall protection systems, carport demolition and reconstruction with new concrete walls and waterproofing, and new concrete paving. The project manager is Rachael Halstead-Jeffreys with ODOC, and the prime consultant engineer is Nate Carter of Solarc Architecture. Work is permitted between 6:00 AM and 5:00 PM, Monday through Friday, excluding state holidays unless otherwise approved. Substantial completion of re-roofing on the main warehouse is required within 60 calendar days after Notice to Proceed, with all other work to be completed within 75 calendar days, and final completion required within 90 calendar days after Notice to Proceed.

The contract requires contractors to provide Safety Data Sheets for all chemicals used on site and to coordinate with the owner to shut down air intake equipment and maintain indoor air quality during roofing operations. An existing roof-mounted communication antenna will be offline early August 2026 and relocated temporarily to the loading dock area for approximately two months before being restored to service by September. The contractor is responsible for arranging and paying for roofing manufacturer inspection services, which must occur between years one and two following substantial completion, with this cost included in the contract sum. The existing roof consists of polyiso insulation with a 2-ply built-up roof system with lead flashing and single primary drains set within the sump.

View the file

Other files

File Type Posted
17403 ITB_GTC_SGC_SPECS~2.pdf PDF
Structural Calculations.pdf PDF
Check Off sheet ITB~15.pdf PDF
17180 Plans.pdf PDF
OSCI_Analysis Report.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

S-29100-00017180 OSCI Warehouse Re-Roof & Building Improvements Summary of Work 01 10 00 - 1

DEPT OF CORRECTIONS

OSCI WAREHOUSE RE-ROOFING PROJECT

SECTION 01 10 00 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information

2. Background

3. Work covered by Contract Documents

a. General Description

b. Other, Miscellaneous

4. Work Hours

5. Completion Dates

1.3 PROJECT INFORMATION

A. Project Identification: Oregon State Correctional Institution (OSCI) Warehouse Roof Replacement

1. Project Location: OSCI, 3405 Deer Park Drive SE, Salem, OR 97310-9385

2. Owner: Oregon Department of Corrections (ODOC)

3. Owner's Representative: Rachael Halstead-Jeffreys, ODOC Project Manager

4. Prime Consultant Engineer: Nate Carter, Solarc Architecture

1.4 BACKGROUND

A. The OSCI Warehouse Building roof is approximately 24 years old and requires replacement.

B. Existing roof consists of Poly ISO with a 2-ply BUR, small aggregate broadcast in asphalt.

01 10 00 - 2

C. Penetrations are flashed with lead flashing materials.

D. Flashing consists of ply-sheet and asphaltic material and silver coating.

E. Single primary drains set with lead flashing within the sump.

1.5 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists generally of the following:

1. Roof demolition down to existing deck.

2. New roofing system.

3. Skylight replacement.

4. Roof equipment curbs and sleepers replaced as indicated.

5. New ladder procurement and installation.

6. New roof and overflow roof drains, piping and insulation.

7. New sheet metal flashing and trim.

8. New walk pads.

9. New fall protection system as indicated.

10. Demolition of existing carport.

11. Demolition of existing CMU retaining walls and concrete paving at carport.

12. Replacement of carport new concrete wall with waterproofing.

13. New drainage at concrete wall including drainage pipe and waterproofing.

14. New concrete paving at carport.

B. Other, Miscellaneous:

1. Communication Antenna: Existing antenna on roof will be offline early August 2026 and fed to a new temporary location in front of loading dock for approximately two months.

01 10 00 - 3

Rooftop antenna is anticipated to be powered back up (by others) end of September once new radio communications equipment is installed on existing antenna.

2. Submittals: In addition to those specified in each specification section, contractor shall provide Safety Data Sheet (SDS) submittals for each chemical used onsite.

3. Contractor shall coordinate with Owner to shut down air intake equipment in the vicinity of the Work. Cover air intake louvers before proceeding with roofing work that could affect indoor air quality or activate smoke detectors in the ductwork. Contractor is responsible for maintaining indoor air quality.

4. Roofing Manufacturer Inspection Services: By manufacturer's technical representative, to report maintenance responsibilities to Owner necessary for preservation of Owner's warranty rights. The cost of manufacturer's inspections is included in the Contract Sum.

a. Inspection to occur between Year 1 and 2, after Substantial Completion Date.

1.6 WORK HOURS

A. Contract may normally perform work between 6AM – 5PM, Monday through Friday, except State of Oregon Holidays, unless approved in advance by Owner.

1.7 COMPLETION DATES

A. Substantial Completion - Re-Roofing on Main Warehouse: 60 Calendar Days after Notice to Proceed.

B. Substantial Completion - All Other Work: 75 Calendar Days after Notice to Proceed.

C. Final Completion: 90 Calendar Days after Notice to Proceed.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 10 00