Replace HVAC System in Building 13 and the Domestic Hot Water System Serving Buildings 13 and 14 at the Pittsburgh Job Corps Center
Solicitation number
1630DC-18-R-00023
Issued by

About this file

Amendment 0001

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1630DC-18-R-00023

X

X

5. PROJECT NO.

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NO.

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NO.

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning ____1_____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR AC- KNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 10-83)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. NOTE: The proposal due date has been extended to 2:00 PM EDT, June 14, 2018.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

BY

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(No., street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(If applicable)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

(X)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 8

3. EFFECTIVE DATE

7/11/2018 3908

ETA OCM JOB CORPS bramso

U.S. Department of Labor ETA/OCM/Division of Job Corps Procurement 200 Constitution Avenue, NW Room N-4643 Washington DC 20210

7/10/2018

N/A

Project Title: Design/Build – Replace the HVAC System in Building 13 and the Domestic Hot Water System Serving Buildings 13 and 14 at the Pittsburgh Job Corps Center Located in Pittsburgh, Pennsylvania

a. The purpose of this Amendment is as follows:

1) INCORPRATE the attached questions and answers into the solicitation.

2) Attachment 1 - Recommended bid template.

Maria J. Pizarro, CPCM CFCM Branch Chief, Contracting Officer

Division of Job Corps Procurement/ A/E & Construction Eastern Branch

AMENDMENT 0001 Page 2 of 8

QUESTIONS AND ANSWERS

SOLICITATION 1630DC-18-R-00017

REPLACE HVAC SYSTEM IN BUILDING 13 AND THE

DOMESTIC WATER SYSTEM SERVIING BUILDINGS 13 AND 14

PITTSBURGH JOB CORPS CENTER

1. Is a Performance Bond required?

Response: A Performance Bond will be required once the contract is awarded to the successful offeror.

2. Is a Payment Bond required?

Response: A Payment Bond will be required once the contract is awarded to the successful offeror.

3. Due to the fact that SAM’s computer system was recently hacked, GSA demanded that SAM require previously and newly registered companies to submit a notarized letter appointing the authorized Entity Administrator before the individual registration will be re-activated. SAM has gotten bombarded with thousands and thousands of such letters which is delaying our re-activation. We overnighted our letter to SAM on May 10, 2018 and have not yet even gotten acknowledgement that they have received it. We called SAM about the status of our re-activation and they had no idea where our re-registration was in the process. Until our letter is reviewed and approved, we cannot even access our information to check and update it as is our practice before we submit proposals requiring SAM registration. This is a government department problem that can severely impact our chances to be awarded this contract. How will this issue be handled by the Department of Labor regarding the proposals for this contract?

Response: The U.S. Department of Labor is aware of the situation, but cannot provide assistance.

The company will have to work the problem out with SAM Customer Service Department (Helpdesk).

4. Where an HVAC unit that is being replaced is in a room with an existing terrazzo floor, must the floor be patched with new terrazzo?

Response: Patching of the floor with terrazzo is required.

5. Section C, Article II. B.7 Existing Facility Investigative Survey requires the D/B contractor to perform an investigative survey to determine if there are any hidden conditions or elements that will impact the proposed design. Please clarify if this work is to be performed prior to Proposal submission or included as part of the services rendered by the D/B contractor.

Response: A follow-up survey to the Center is invited as needed and must be completed prior to the submission. Contractor must coordinate visit with the Center’s Administration Director.

6. In addition to rooms served by PTAC’s, the solicitation directs the removal of all cabinet heaters, radiators, and baseboard radiant heaters serving all second and third floor rooms. The solicitation directs the installation of PTHP’s (w/ electric back-up heat) in all dormitory rooms and Female lounge areas. The solicitation also directs the installation of electric cabinet unit heaters to serve each communal bathroom/shower room and laundry located on the second and third floors. What

AMENDMENT 0001 Page 3 of 8 are the requirements for Male lounge areas, staff rooms, conference rooms, offices, stairwells, corridors, toilet rooms, janitor closets and electric closets?

Response: Male lounge areas and corridors (at the location of existing steam radiators and/or wall cabinets), as it is indicated in the Section B, Subsection 3-HVAC, item t, will be provided with electric wall cabinet/heaters. No heating/cooling will be required for the rooms currently without any means for heating/cooling (e.g. janitor closets, and electric closets). The RA Offices, equipped with steam radiator heaters and/or wall cabinets, will be provided with electric resistant cabinet unit heaters in lieu of the existing steam radiators, and/or cabinet heaters.

7. The solicitation directs the D/B Contractor to submit an energy analysis per ASHRAE 90.1-2010 Appendix G showing that the design reduces energy consumption by at least 20% compared to the baseline building. In this case, the baseline building system referenced for Residential by Appendix G (which includes dormitory) is System 2, PTHP w/ Electric heat, the exact system required by the solicitation. Will the analysis be required? If so, there is little chance of improving the energy consumption by at least 20% without making major renovations to the building envelope, kitchen equipment, lighting and power distribution systems. Will the D/B contractor be obligated to meet the 20% energy reduction by any means necessary?

Response: No; however, selected PTHP w/ Electric heat units shall meet the minimum efficiency requirements of 14 SEER, in accordance with ASHRAE 90.1-2013, Table 6.8.1-1 and the best energy efficiency ratings available at the time of purchase.

8. By reference to JCH-814, the solicitation directs the D/B Contractor to compare the merits of at least 3 HVAC systems. The solicitation also directs the installation of a specific system (PTHPs w/ Electric Heat). Will a comparison of 3 HVAC systems be required?

Response: No, however; benchmarking between three manufacturers of the same type of a system in terms of performance, energy efficiency, initial, operation and maintenance costs, life span, and ease of maintenance shall be provided.

9. By reference to JCH-814, the solicitation directs the D/B Contractor to use the Job Corp HPSB compliance tool. Again, since you are directing the installation of a specific HVAC system type, is this required? If so, please forward or provide a link to the compliance tool.

Response: No, it is not required.

10. By reference to JCH-814, the solicitation directs the D/B Contractor to perform a Whole Building energy use simulation. Please confirm this requirement.

Response: Simulation is not required, but contractor shall provide the energy efficiency rating of the selected units in accordance with ASHRAE 90.1-2013, Table 6.8.1-1.

11. By reference to JCH-814, the solicitation directs the D/B Contractor to reduce the energy cost budget by 20% below the pre-renovation baseline. Since you are directing the installation of a specific HVAC system type, is this required?

Response: No, but provide the energy efficiency ratings of the selected units in accordance with ASHRAE 90.1-2013, Table 6.8.1-1.

AMENDMENT 0001 Page 4 of 8

12. Refer to Section C Description/Specifications Article IV. Extent of Work. B.2 Electrical: The solicitation clearly states that power for the replacement PTHP’s is to be extended from existing panels. The solicitation also requires power be constructed to serve each new electric terminal heater. With the exception of providing new subpanels to accommodate additional circuit breakers, is the intent of the project to utilize existing power infrastructure to serve the electric terminal heat?

Response: Yes, the intent to utilize the existing power infrastructure. Exception is if design calculations determine it necessary to enlarge the existing building electrical service. As a reminder, male lounge areas and corridors (at the location of existing steam radiators and/or wall cabinets), as it is indicated in the Section B, subsection 3-HVAC, item t, will be provided with electric wall cabinet/heaters. No heating/cooling will be required for the rooms currently without any means for heating/cooling (janitor closets, and electric closets). The RA Offices equipped with steam radiator heaters and/or wall cabinets will be provided with electric resistant cabinet unit heaters in lieu of the existing steam radiators, and/or cabinet heaters. These areas must also be included in the load calculations and verification of current infrastructure adequacy.

13. By reference to JCH-814, the solicitation directs the D/B Contractor to contact Utility companies and coordinate service to all buildings on the property. It further states that the A/E (in this case the D/B Contractor) is responsible to design adequate utility services. Do these requirements apply to an existing building served by an existing electrical service? If calculations determine that a service upgrade is required of the building, or any part of the facility’s electrical infrastructure, will the D/B contractor be obligated to provide it at no additional cost?

Response: Any contact with the utility company will be made via the Center’s Administration Director. For bidding purposes, the electrical utilities are assumed adequate, though the Contractor is responsible for design of adequate electrical service, including possible upgrade of the existing service, if determined to be necessary. If calculations prove that an electrical upgrade is necessary, the contractor will be invited to submit a Request for Change for consideration by the Department of Labor.

14. Refer to of Section C Description/Specifications Article IV. Extent of Work, B.1 Mechanical and Plumbing Requirements, Kitchen Steam Operating Cooking Equipment (item d, page C-17):

Please clarify the requirements for steam cooking equipment: Is the intent to provide…

a) A self-contained, gas fired steam generator that is piped to (2) 40 gallon steam kettles, one kettle in the Main kitchen and another in the Culinary Arts kitchen,

b) or a self-contained, gas fired steam generator that is piped to (2) 40 gallon steam kettles in the Main kitchen, and another self-contained, gas fired steam generator that is piped to (2) 40 gallon steam kettles in the Culinary Arts kitchen,

c) or (2) self-contained, gas fired convection steamers, one in the Main kitchen and another in the Culinary Arts kitchen.

d) or (2) self-contained, gas fired steam pan cookers, one in the Main kitchen and another in the Culinary Arts kitchen

e) or something other than listed above

Response: Two self-contained, gas fired steam pan cookers/generators with capability of providing steam to two 40-gallon steam kettles in each kitchen (Main and Culinary Arts) shall be provided.

AMENDMENT 0001 Page 5 of 8

15. Refer to of Section C Description/Specifications Article IV. Extent of Work, B.1 Mechanical and Plumbing Requirements, HVAC (item J, page C-15): The solicitation directs the D/B Contractor to provide condensate drain and pump kits for each PTAC unit. Are the existing PTAC units served by existing condensate drain piping? Is the intent of the Solicitation for the D/B contractor to furnish and install new condensate drain piping when none presently exists? Is the intent of the Solicitation for the D/B contractor to replace existing condensate drain piping?

Response: It shall be the contractor’s responsibility to field-verify conditions of the existing condensate drain lines. In a situation where there is no condensate drain piping provided, consider repurposing of the pre-existing steam condensate return and convert it to the PTAC condensate drain. The existing condensate drain lines shall be cleaned, assuring their operability prior to connection of the PTAC pan drains to the system.

16. Refer to of Section C Description/Specifications Article IV. Extent of Work, B.1 Mechanical and

Plumbing Requirements, Domestic Hot Water (item e, page C-16): The solicitation directs the D/B Contractor to provide design calculation, drawings and construction for two new condensing type high efficiency hot water boilers in parallel configuration to be connected to three 300-gallon hot water storage tanks. Our field notes indicate the existing storage tanks are 500 gallon each.

Is the intent of the solicitation to replace the existing tanks with 300 gallon tanks?

Response: No. The new condensing hot water boilers will be connected to the existing 500-gallon domestic hot water storage tanks.

17. Refer to of Section C Description/Specifications Article IV. Extent of Work, B.1 Mechanical and Plumbing Requirements, Kitchen Steam Operating Cooking Equipment (item d, page C-17): The solicitation directs the installation of new steam generators in the main and culinary arts kitchens.

Please identify suggested locations for the steam generators so we can estimate the cost of flue piping and gas line installations for this equipment.

Response: The steam generators in each kitchen should be installed at the location of the existing steam pan cookers, under the existing cooking exhaust hood, to the most extent possible in accordance with the IMC, 2015 and manufacturer’s installation requirements.

18. Refer to of Section C Description/Specifications Article II. Design Build Requirements, D.1 Phasing of the Work (Page C-9), Article VII Project Schedule (page C-34), and the Phasing Diagrams provided on pages C-53 and C-54: The solicitation directs the D/B Contractor to perform the construction in 9 phases, during Monday through Friday between the hours of 8:00 am and 4:00 pm. It also directs the contractor to allow a 2-week transition period between phases.

The solicitation indicates a construction period of 270 calendar days, which only allows 104 week days for construction when the transition periods and off-limit weekend days are factored in.

Meeting the indicated schedule will materially affect the cost of the work. Please review the schedule and reiterate the intent of the Solicitation. If the completion dates can be extended, please indicate so in your response. If construction work may proceed during the transition periods, please indicate that as well.

Response: The specified two-week (maximum) transition of students through swing spaces may take as little as one or two days in most instances, but will not exceed two weeks. The Contractor shall base their proposal on a 2-week transition period. The workday may be extended at the discretion and approval of the Contracting Officer and Center. Other project work may proceed during the transition periods if safely executed and coordinated with the Contracting Officer and Center Director in advance.

AMENDMENT 0001 Page 6 of 8

19. The area around the building is quite congested, will there be laydown areas provided to the contractor large enough for containers to be onsite for material storage. If not, will there be area inside the building available to store materials?

Response: The laydown area will be inside the fenced area between Buildings 12 and 7.

20. Since most of the building will be occupied during construction, how much of the building will be vacant and available for construction at a time? Also, will there be a delay between completion of one phase and the beginning of another to move students in and out of areas?

Response: For bidding purposes, the building will be considered occupied except for the phased work area. Transition of students through swing space is specified as a 2-week period. Other project work may proceed during the transition periods if safely executed and coordinated with the Center Director.

21. When electrical terminations are being made and power to certain areas may be interrupted, will it be required to complete electrical terminations afterhours or on the weekends?

Response: See Section C, para V.A.2.a) Temporary Facilities and Controls, General.

22. What is the process for facility access, will the contractor / subcontractors be issued facility passes for the length of the project or will they be issued daily?

Response: All contractor personnel will be stopped at the security gate each day. Driver MUST have a valid driver’s license. Vehicles will be searched on a daily basis.

23. What is the process for building access, will the contractor / subcontractors have access to the building through all doors and access to all elevators (closest to work being performed) or will the access points be limited?

Response: The center will provide building access through designated doors. Elevators will be available on request, as needed. The contractor shall promptly repair/replace any damage to structures, elements, utilities, finishes, etc. occurring due to construction, the cost of which will be borne by the contractor.

24. Will the contractor/subcontractors be required to be escorted through the building at all times?

Response: Escorts are not required, as long as contractor personnel remain in designated project work areas.

25. What will be normal working hours and will the campus be accessible on federal holidays?

Response: Contractor work hours are limited to the hours between 8:00 AM and 4:00 PM.

26. Are the existing Electric Utilities to each room capable of the new or required load proposed in th e upgrade?

Response: For bidding purposes, the electrical utilities to each room are assumed adequate. The Contractor is responsible for design of adequate electrical service and includes possible upgrade of the existing service, if determined to be necessary. If calculations prove that an electrical upgrade is necessary, the contractor will be invited to submit a Request for Change for

AMENDMENT 0001 Page 7 of 8 consideration by the Department of Labor. Any contact with the utility company will be made via the Center’s Administration Director.

27. Will CAD backgrounds be provided for design team to base their design efforts?

Response: Simple CAD files of the basic floor plans will be made available. It is the Contractor’s responsibility to field verify all dimensions.

28. Bathroom Ventilation: Are modifications to existing system in bathrooms required to be changed as part of the upgrade?

Response: No, there are no modifications required on the existing bathroom exhaust ventilations.

29. PTAC Condensate. Please confirm if the existing condensate drains are able to be used for the ne w units? If no existing condensate, please confirm if condensate for PTACs and directed out the exterior louver.

Response: It shall be the contractor’s responsibility to field-verify conditions of the existing condensate drain lines. In a situation where there is no condensate drain piping provided, consider repurposing of the pre-existing steam condensate return and convert it to the PTAC condensate drain. The existing condensate drain lines shall be cleaned, assuring their operability prior to connection of the PTAC pan drains to the system.

30. Pipe Enclosures for PTACs. Do any existing Pipe enclosures need replaced?

Response: No. Unused piping enclosures passing through each dormitory room to the room next dormitory room shall be removed. Provide drywall repairs and match color to the existing wall paint color to the most extent possible. Reused piping enclosures shall be repaired to the same condition received prior to the project.

31. Are there any pre-existing building controls and if so, who is the contractor of record?

Response: No. There are no pre-existing building controls.

32. Lounge – At the walkthrough the Lounge area is belived to be served by a split system unit without outside a ir requirements. Confirm that OA is required to be brought to these areas? What other areas will r equire new Outside Air ductwork?

Response: Provide modifications on the existing return air ductwork for the unit serving the second floor Male lounge area to meet the minimum fresh/outdoor air requirements in accordance with IMC, 2015 Section 403.1.1.1 and ASHRAE 62.1-2013. No other building spaces will require providing fresh outdoor air.

33. Will contractors be allowed to use elevator for transporting materials, equipment etc.?

Response: Yes. The contractor shall promptly repair/replace any damage to structures, elements, utilities, finishes, etc. occurring due to construction, the cost of which will be borne by the contractor.

AMENDMENT 0001 Page 8 of 8

34. Can contractors use facility restrooms or do we need to provide portable toilets and trailer?

Response: Yes. The facilities shall be maintained in an acceptable, sanitary condition during the course of construction.

PITTSBURGH JCC

PROJECT: REPLACE HVAC SYSTEM BUILDING 13

CONTRACTOR'S PROPOSAL

DATE:

TOTAL Contractor Price $0.00

LABOR/EQUIPMENT MATERIALS/SUBCONTRACTOR

ITEM RATE HOURS TOTAL Unit QTY UNIT RATE Total ITEM TOTAL Dormitories Move units up stairs to areas all materials up to 2nd and 3rd fllors and to work areas $0.00 Remove old PTAC units 78 dorm $0.00 Dispose of old units $0.00

Cap piping to old PTAC's - Plumbers $0.00 New PTAC units - one per dorm $0.00

Seal and make units weather tight $0.00 Lounges and Bathrooms Move units up stairs to areas $0.00 2nD floor lounges remove old PTAC units $0.00

2nd floor lounges new PTAC units $0.00

Seal and make units weather tight $0.00 Install new unit heaters bathrooms and hallways $0.00 Restrooms and hallwys remove old raditor units $0.00 Cap old radiator units - Plumbers $0.00 Patch walls from removed radiator units $0.00

Cap piping to old PTAC's - Plumbers $0.00 Electrical $0.00 Connnect dorm room PTAC's $0.00 For lounges 3/4" EMT and 3#10 wire 500' with a protective cover $0.00 Conduit and wire for bathrooms 1/2" EMT and #12's 1000' total $0.00 30 amp 2 pole breaker $0.00 Connection to lounge and bathroom PTAC's $0.00 Remove and replace boilers Boilers Test & balance all PTAC's and 1st floor heating $0.00

Final clean-ups $0.00

Design Initial Site Visit $0.00 Electrical Engineer $0.00 Mechanical Engineer $0.00 Senior Architect $0.00 Project manager $0.00 Travel $0.00 60% Design Electrical Engineer $0.00 Mechanical Engineer $0.00 Senior Architect $0.00 Project manager $0.00

CADD $0.00

Spec Writer $0.00 100% Design Electrical Engineer $0.00 Mechanical Engineer $0.00 Senior Architect $0.00 Project manager $0.00

CADD $0.00

ATTACHMENT 1

Spec Writer $0.00 Submittal drawings $0.00 Submittal specifications $0.00

Submittal reviews and Site Visits Electrical Engineer $0.00 Mechanical Engineer $0.00 Senior Architect $0.00 Project manager $0.00 Travel $0.00

$0.00 $0.00 $0.00 $0.00

Local and State sales tax materials only $0.00

SUBTOTAL $0.00

Contractor OH $0.00 Subtotal $0.00 Contractor profit $0.00 Esimated Total $0.00 bond/insurance $0.000

TOTAL BID $0.00

GENERAL CONDITIONS

UNIT COST UNIT COST UNIT COST

Project Manager (Labor) 0.0 Hours -$ -$

Project Scheduler (Labor) 0.0 Hours -$ -$

Quality Control Manager (Labor) 0.0 Hours -$ -$

Superintendent (Labor) 0.0 Hours -$ -$

General Requirements - Salari 0.0 Hours -$ -$

Project Superintendent Vehicle 0.0 Days -$ -$ QCM Vehicle 0.0 Days -$ -$ General Requirements - Vehicles -$

Project Manager Per Diem 0.0 Days -$ -$ Project Superintendent Per Diem 0.0 Days -$ -$ QCM Per Diem 0.0 Days -$ -$ General Requirements - Per D 0.0 -$ -$

Project Manager Lodging 0.0 Days -$ -$ Project Superintendent Lodging 0.0 Days -$ -$ QCM Lodging 0.0 Days -$ -$ General Requirements - Lodging -$ -$

Project Manager Cell Phone 0.0 Days -$ -$ Project Scheduler Cell Phone 0.0 Days -$ -$ Project Superintendent Cell Phone 0.0 Days -$ -$ QCM Cell Phone 0.0 Days -$ -$ General Requirements - Cell Phone -$ -$

Field Office Printer/Copier 0.0 MNTHS -$ -$ As-builts 0.0 LS -$ -$ Field Office Supplies 0.0 MNTHS -$ -$ Safety Material 0.0 MNTHS -$ -$ Temp Lighting 0.0 DAYS -$ -$ Office Trailer 0.0 mths -$ -$ Office Trailer Setup 0.0 LS -$ -$ Sanitary Faciltiies 0.0 mths -$ -$ Commissioning 0.0 LS -$ -$ Tools 0.0 weeks -$ -$ Construction Waste Disposal 0.0 weeks -$ -$

TOTAL GENERAL CONDITIONS -$

O&P -$ bond -$

TOTAL GENERAL CONDITIONS -$

TOTALITEM DESCRIPTION QTY UNITS MATERIAL LABOR EQUIPMENT

Amendment 0001-Pittsburgh HVAC and Hot Water System
Questions and Answers for Pittsburgh JCC
Recommended Bid Template for Pittsburgh HVAC Project
Bid Template

Sign in Sheet for Pittsburgh

File details come from the government source that posted it.