About this file

Attachment J.C.2- Contract Line Items and Anticipated Dates

View the file

Other files for this federal contract opportunity

Other files attached to Data Enclave for Restricted Access Microdata, newest first.
File Type Posted
1625DC-19-Q-00029_Questions_and_Answers.xlsx XLSX spreadsheet
1625DC-19-Q-00029_Amendment_1.pdf PDF
1625DC-19-Q-00029_8.14.pdf PDF
1625DC-19-Q-00029_Attachments_J.H.1_to_J.H.3.docx DOCX document
1625DC-19-Q-00029_Attachment_J.H.4.docx DOCX document
1625DC-19-Q-00029_Attachments_J.L.1_to_J.L.3.docx DOCX document
1625DC-19-Q-00029_Attachment_J.L.4.xlsx XLSX spreadsheet
1625DC-19-Q-00029_Attachment_J.C.1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Solicitation 1625DC-19-Q-00029 Attachment J.C.2- Contract Line Items and Anticipated Dates

Contract PeriodCLINEventAnticipated Date/TimeframeAnticipated Date/ Earliest Date for 0XXX CLINs OnlyAnticipated Latest Date (0XXX CLINs Only)Start Date of ContractThursday, October 31, 2019
Number of Days for Delivery of CLIN 0001 (Not to Exceed)105
Base Period0001All Tasks Due0-105 Days after Award of ContractThursday, October 31, 2019Thursday, February 13, 2020
0002Start of Performance of Tasks0-105 Days after Award of ContractThursday, October 31, 2019Thursday, February 13, 2020
0003First Quarterly Addition*Concurrently with Start of Performance of TasksThursday, October 31, 2019Thursday, February 13, 2020
Second Quarterly Addition*90-180 Days after Award of ContractWednesday, January 29, 2020Tuesday, April 28, 2020
0002Base Period End DateThursday, July 30, 2020Thursday, July 30, 2020Thursday, July 30, 2020
Option Year 11001Option Year 1 Start DateFriday, July 31, 2020Friday, July 31, 2020Not Applicable
1002First Quarterly AdditionAt Exercise of Option PeriodFriday, July 31, 2020
Second Quarterly Addition90 Days after Exercise of Option PeriodWednesday, October 28, 2020
Third Quarterly Addition180 Days after Exercise of Option PeriodTuesday, January 26, 2021
Fourth Quarterly Addition270 Days after Exercise of Option PeriodMonday, April 26, 2021
1001Option Year 1 End DateFriday, July 30, 2021Friday, July 30, 2021
Option Year 22001Option Year 2 Start DateSaturday, July 31, 2021Saturday, July 31, 2021
2002First Quarterly AdditionAt Exercise of Option PeriodSaturday, July 31, 2021
Second Quarterly Addition90 Days after Exercise of Option PeriodFriday, October 29, 2021
Third Quarterly Addition180 Days after Exercise of Option PeriodWednesday, January 26, 2022
Fourth Quarterly Addition270 Days after Exercise of Option PeriodWednesday, April 27, 2022
2001Option Year 2 End DateSaturday, July 30, 2022Saturday, July 30, 2022
Option Year 33001Option Year 3 Start DateSunday, July 31, 2022Sunday, July 31, 2022
3002First Quarterly AdditionAt Exercise of Option PeriodSunday, July 31, 2022
Second Quarterly Addition90 Days after Exercise of Option PeriodSaturday, October 29, 2022
Third Quarterly Addition180 Days after Exercise of Option PeriodFriday, January 27, 2023
Fourth Quarterly Addition270 Days after Exercise of Option PeriodTuesday, October 24, 2023
3001Option Year 3 End DateSunday, July 30, 2023Sunday, July 30, 2023
Option Year 44001Option Year 4 Start DateMonday, July 31, 2023Monday, July 31, 2023
4002First Quarterly AdditionAt Exercise of Option PeriodMonday, July 31, 2023
Second Quarterly Addition90 Days after Exercise of Option PeriodSaturday, October 28, 2023
Third Quarterly Addition180 Days after Exercise of Option PeriodFriday, January 26, 2024
Fourth Quarterly Addition270 Days after Exercise of Option PeriodFriday, April 26, 2024
4001Option Year 4 End DateTuesday, July 30, 2024Tuesday, July 30, 2024
Six Month Extension if Exercised after Option Year 45001Extension Period Start DateWednesday, July 31, 2024Wednesday, July 31, 2024
5002First Quarterly AdditionAt Exercise of Extension PeriodWednesday, July 31, 2024
Second Quarterly Addition90 Days after Exercise of Extension PeriodTuesday, October 29, 2024
5001Extension Period End DateThursday, January 30, 2025Thursday, January 30, 2025
*Due to the uncertainty of the completion timeline of CLIN 0001, the quantity of adjustment(s) (CLIN 0003) and their timing cannot be determined at the time of solicitation.