Summary

This Addendum No. 1 is issued by the Virginia Department of Transportation (VDOT) to Invitation for Bid (IFB) 160995 for the Bryant Area Headquarters Combo Building and Fuel Center project, dated October 22, 2026. The project encompasses construction of a 4,998-square-foot prototype combination building with administrative office space (approximately 2,416 square feet) and a two-vehicle storage and maintenance bay (approximately 2,582 square feet), along with a fuel facility featuring gasoline and diesel dispensers, automated fuel management system, underground storage tanks (2,000 gallons gasoline and 10,000 gallons diesel), and a 24-foot by 32-foot pre-engineered metal canopy at 33 Donahue Lane, Roseland, Virginia 22967. Sealed bids are due November 9, 2026, at 2:00 PM, with a pre-bid conference held on October 15, 2026. Site visits are available upon coordination with Mike Brooks at michael.brooks@vdot.virginia.gov. The addendum includes nine questions and answers addressing concrete masonry unit density classification, fuel center subcontracting opportunities, alternative fuel management systems, equivalent manufacturers and equipment acceptance procedures, interior sliding window specifications, epoxy paint specifications for CMU walls, solid surface countertop finishes, and AISC certification requirements for structural steel fabrication and erection.

The addendum clarifies that this is a single-prime contract with the prime contractor fully responsible for all work, though qualified specialty subcontractors may be utilized provided all installer qualifications, manufacturer certifications, licenses, and quality-assurance requirements are satisfied. VDOT will consider alternative systems and equivalent products only upon demonstration of full equivalency and compatibility with existing VDOT infrastructure; the burden of proof rests entirely with the proposer, and incomplete demonstrations will result in rejection. Prebid questions must be submitted in sufficient time to allow review and addendum issuance before the bid due date. The procurement does not identify a published list of plan holders, though interested subcontractors may contact Procurement Officer Joshua Saunders to inquire about plan-holder availability through the eVA system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF TRANSPORTATION

Stephen C. Brich, P.E. 1221 East Broad Street (804) 482-5818 Commissioner Richmond, Virginia 23219 October 22, 2026

ADDENDUM No. 1 TO ALL BIDDERS:

Reference-IFB: 160995 Commodity Bryant AHQ Combo Building and Fuel Center

Project Code: 501-18130-086

Dated: October 5, 2026

For Delivery To: Virginia Department of Transportation (VDOT)

Attention: Joshua Saunders

Bids Due: November 9, 2026 @ 2:00PM Prebid Conference October 15, 2026

The above is hereby changed to read:

1. In Reference to Addendum #1 sealed by Brian Goldman of Architectural Partners (7 pages) to include Pre-bid sign-in sheet.

Note:

Acknowledgement of this addendum or any subsequent addenda must be prior to the bid due date and time or signed and uploaded as an attachment with the electronic bid submission. Failure to acknowledge or submit the addendum may be grounds for declaring the bid non-responsive.

Sincerely, Joshua Saunders Joshua Saunders, VCCO, VCO, Senior Procurement Officer

Name of Firm

Signature Title Date

10 9th S treet , Lynchburg , Vi rginia 24504 p 434-846-8456 | f 434-846-4534 | www.archi tecturalpar tners.com

A d d e n d u m

PROJECT INFORMATION

OWNER NAME: VIRGINIA DEPT. OF TRANSPORTATION OWNER PROJECT MGR: JOHN DYER

PROJECT TITLE:

VDOT – BRYANT AHQ – COMBO

BUILDING & FUEL FACILITY

OWNER PROJECT NO.: 501-18130-086

A/E PROJECT MGR.: BRIAN E. GOLDMAN, RA

PROJECT LOCATION:

33 DONAHUE LANE,

ROSELAND, VA 22967

BIDS DUE: REFER TO VDOT ADDENDUM

IFB NO.: 160995 BID OPENED: SEE COVER LETTER

ADDENDUM #: 1

This addendum becomes part of the Construction Documents. The following changes, additions, and deletions shall be made to the following documents; all other conditions shall remain the same. Please attach to all copies of the Construction Documents which you are holding.

All Contractors are to state in their bid the receipt of this addendum. Instructions to Bidders:

PRE-BID SIGN-IN ATTACHED.

ADDENDUM TO THE DRAWINGS – DRAWINGS:

Number Drawing Detail No.

ADDENDUM TO THE PROJECT MANUAL VOLUME 1 & 2

Number

Spec Section

Specification Change

04 2200 Part 2 Product 2.4 CONCRETE MASON UNITS. Item D.2 Density Classification shall be changed to Normal Weight.

QUESTIONS/ANSWERS AND CLARIFICATIONS:

Number

A1Q1 Question Subject: IFB 160995 – Fuel Center Subcontracting Opportunities: For IFB 160995, can a specialized fuel systems company participate as a subcontractor for the Fuel

Center scope, including fuel dispensers, automated fuel management, underground storage tanks, and associated monitoring and control systems? If so, is there an available list of prospective general contractors or plan holders that interested subcontractors may contact?

Answer The procurement is a single-prime contract. The prime Contractor is fully responsible for the entire Work. There is no prohibition on the use of qualified specialty subcontractors provided:

- The prime remains solely responsible for performance, scheduling, coordination, warranties, and compliance.

http://www.architecturalpartners.com/

- All installer qualifications, manufacturer certifications/training, licenses, and quality-assurance requirements in the Contract Documents are satisfied (including those in Sections 231313, 231333, and 335700).

- The subcontractor is acceptable to the prime and meets any Commonwealth of

Virginia or VDOT prequalification/security requirements applicable to the project.

Plan holders / prospective GCs: No official published list of plan holders or prospective prime bidders is included with the IFB. Interested subcontractors may contact the Buyer (Joshua Saunders, Joshua.Saunders@vdot.virginia.gov) to inquire whether a plan-holder list is being maintained and, if so, whether it can be released.

Registration and document access are handled through the eVA system. All official project communications remain by Addendum. The Pre-Bid Conference Sign-in sheet has been included with this addendum which may include some of the potential GCs that will bid on this project.

A1Q2 Question Fuel-Master Compability - Regarding the automated fuel management system specified for the Fuel Center, will VDOT consider an alternative system that provides equivalent functionality and can demonstrate compatibility with the existing VDOT fuel cards, dispensers, and monitoring equipment? If alternatives are permitted, what technical documentation or approval process is required?

Answer VDOT will consider an alternative system only if it:

- Provides fully equivalent functionality (accounting, security, authorization, reporting, real-time monitoring, etc.).

- Demonstrates complete compatibility with existing VDOT fuel cards, dispensers, monitoring equipment, and related systems without requiring modifications to

Owner’s existing infrastructure, cards, or operational procedures.

- Meets all other technical, safety, certification, and performance requirements of the

Contract Documents.

The burden of proof of equivalency and compatibility rests entirely with the proposer. Documentation (product data, interface details, compatibility statements, prior VDOT installations if available, testing protocols) should be submitted. Any alternative will be evaluated against the basis established in the specifications

(coordination with Fuel Master and Veeder-Root TLS-350 Plus leak detection).

Approval is not automatic; incomplete demonstration of compatibility will result in rejection.

Alternatives may be proposed via prebid question (for potential Addendum).

A1Q3 Question Acceptance of Equivalent Manufacturers and Equipment - Regarding Specifications

Sections 231313 (Facility Underground Fuel Storage Tanks), 231333 Storage Tanks), 231333 Detection System), and 335700 (Bulk Fuel Dispensing Equipment), will

VDOT accept equivalent products from manufacturers other than those identified in the specifications, provided all applicable technical, safety, certification, and performance requirements are met? If so, what is the required procedure and deadline for submitting proposed equivalents for review?

Answer Key basis-of-design references in the documents:

- 231313 (USTs): Double-wall FRP tanks meeting UL 1316; listed manufacturers include Ace Tank & Fueling Equipment, ZCL Composites, Xerxes, Containment

Solutions (or equal).

- 231333 (Liquid-Level & Leak Detection): Basis of Design is Veeder-Root TLS-350 mailto:Joshua.Saunders@vdot.virginia.gov

Plus; other manufacturers listed subject to compliance include Omntec, Franklin

Fueling Systems, Pneumercator.

- 335700 (Bulk Fuel Dispensing): Performance-specified dispensers (UL 87, dual-pulse interface for fuel-control/tank-monitoring systems, specific display/totalizer, hose, nozzle, emergency shutoff, sump, etc.). No single manufacturer is named as the sole acceptable product.

Required procedure:

1. Prebid: Submit a complete technical package (product data, compliance matrix annotated against the specification sections, certifications, warranty comparison, interface details, and any required professional-engineer sealed documentation) as a prebid question on Form DGS-30-272. If the proposed equivalent is determined acceptable, it will be incorporated by Addendum. Submissions must be received in sufficient time to allow review and Addendum issuance before the bid date

(11/9/2026). Check the Instructions to Bidders for the exact prebid-question cutoff.

2. Post-award: Governed by Section 012500 Substitution Procedures (CSI Form

13.1A, detailed side-by-side comparison, coordination impacts, cost/time effects, Contractor certification of compliance and compatibility, waiver of future claims, etc.). Architect/Engineer and Owner approval is required; acceptance is formalized by Change Order. Use of a non-approved product is not permitted.

The Contractor/proposer bears the full burden of demonstrating equivalency. The

Owner and Architect/Engineer are not obligated to accept products that do not meet every specified requirement or that introduce compatibility, warranty, or operational risks.

A1Q4 Question Will there be an opportunity for another site visit?

Answer Yes. Please let Mike Brooks know when you plan to visit the site so that he can coordinate with our Bryant AHQ staff. His contact information:

michael.brooks@vdot.virginia.gov (434) 363-0465 mobile

A1Q5 Question When is the last day and time for questions?

Answer Refer to "Instructions to Bidders, Form DGS-30-055 (CO-7a)" included in Project

Manual, Volume 1.

A1Q6 Question Specification 05 1200 pg.2 par.1.7 Can the requirement for AISC certification be waived for fabrication and erection?

Answer Fabricator is required to either comply with Section 051200 1.7.A or the Contractor may request the Owner to engage a qualified testing agency to perform special inspections of the shop and fabricated items during fabrication of the project work.

The Owner will charge the contractor for all costs incurred for such testing and inspection.

[If requested: Qualified testing agency’s special inspector will perform tests and inspections and submit reports based upon inspection required by the VCC, VUSBC

Statement of Special Inspections, and as follows. Special inspector will verify that manufacturer maintains detailed fabrication and quality-control procedures and will review the completeness and adequacy of those procedures to perform the Work.

Special inspector will test and inspect shop connections for structural steel framing according to the following: Shop-bolted connections shall be inspected according to

RCSC's "Specification for Structural Joints Using High Strength Bolts". In addition to visual inspection, shop-welded connections shall be tested and inspected according to AWS D1.1. Product will be considered defective if it does not pass tests and inspections.]

The Installer is required to either comply with Section 051200 1.7.B or may be an experienced erector who specializes in erecting and installing work similar in material, design, and extent to that indicated for this Project and who is acceptable to manufacturer. Quality Control (QC) inspection tasks for erection shall be performed by the erector’s quality control inspector (QCI) in accordance with

Chapter N of AISC 360.

A1Q7 Question Please provide specifics for interior sliding window shown on sheet A9, detail A.

Answer Provide aluminum, medium-duty interior sliding service window. Refer to Drawing

A9 for size.

• Frame shall be constructed of 6063-T5 extruded aluminum, with overhead track, side jambs, and two framed window sections.

• Each window frame rolls on bottom-mounted heavy-duty ball bearing wheels that ride on aluminum lower channels recessed into solid surface shelf. Provide manufacturer’s standard catch locks.

• Aluminum finish will be selected as part of the submittal process.

• Glazing shall be 1/4" clear tempered glass.

A1Q8 Question Drawing A1 indicates epoxy paint to be used for CMU walls in Room 113. No

Specification for epoxy paint exists in project documents. Provide specification for epoxy paint.

Answer Refer to Specification Section 099123 Interior Painting for submittals, maintenance materials, mockups, delivery / storage, field conditions, and preparation information.

Part 2 PRODUCTS

2.1 BLOCK FILLERS

A. Epoxy Block Filler: Solvent-based, two-component, epoxy, high-solids coating;

formulated to bridge and fill porous surfaces of CMU substrates in preparation for specified subsequent coatings.

2.2 INTERIOR HIGH-PERFORMANCE COATING SCHEDULE, MASONRY

SUBSTRATES

A. CMU Substrates:

1. Epoxy System for Wet Environments: MPI INT 4.2G.

a. Block Filler: Epoxy block filler, MPI #116.

b. Intermediate Coat: Epoxy, matching topcoat.

c. Topcoat: Epoxy, gloss, MPI #77.

A1Q9 Question Please provide a level/class of finish for the Solid Surface Countertops. Currently finish is not specified.

Answer Refer to specification section 123661.16 2.1.

Colors and patterns are to be selected by the A/E from the manufacturer’s full range.

The solid surface material is to be Class A Finish Material and NSF/ANSI 51

Certified.

END OF ADDENDUM

10/20/2026

PC: 501-18130-086 BRYANT AHQ COMBO BUILDING & FUEL CENTER IFB N0. 160995

Pre-Bid Conference 10/15/2026, 10:00 AM

NAME COMPANY/ADDRESS PHONE E-MAIL

Brian Goldman Architectural Partners

(Architect) 10 9th Street 434-846-8456 brian@architecturalpartners.com

Lynchburg, VA 24504

Joshua Saunders VDOT

(Procurement Officer) Central Office 804-729-6845 joshua.saunders@vdot.virginia.gov

Richmond, VA

John Dyer VDOT

(Capital Outlay Project Manager) Central Office 804-382-3861 john.dyer@vdot.virginia.gov

Richmond, VA

Grant Beasley Master Engineers and Designers

(Electrical Engineer) 904 Lakeside Drive 434-846-1350 GBeasley@MasterEngineers.com

Lynchburg, VA 24501