11 Payment Plan

View the file

Other files for this federal contract opportunity

Other files attached to EELV Phase 1A GPS III Launch Services (FA8811-16-R-0006), newest first.
File Type Posted
08_Evaluation_Criteria_3_Aug_16_as_posted.pdf PDF
02c_CDRLs_Exhibit_C_3_Aug_16_as_posted.pdf PDF
03_PWS_3_Aug_16_as_posted.pdf PDF
02b_CDRLs_Exhibit_B_3_Aug_16_as_posted.pdf PDF
05_Small_Business_Plan_3_Aug_16_as_posted.pdf PDF
04_DD_254_3_Aug_16_as_posted.pdf PDF
01_Model_Contract_FA8811-16-R-0006_3_Aug_16_as_posted.pdf PDF
10_Government_Property_3_Aug_16_as_posted.pdf PDF
07_Instructions_to_Offerors_3_Aug_16_as_posted.pdf PDF
09_Mission_Requirements_Annex_Cover_Sheet_3_Aug_16_as_posted.pdf PDF
06_Acceptance_Criteria_3_Aug_16_as_posted.pdf PDF
02a_CDRLs_Exhibit_A_3_Aug_16_as_posted.pdf PDF
03_PWS_GPS_III_14_Jun_16.pdf PDF
02c_CDRLs_(GPSIII)_Exhibit_C_14_Jun_16.pdf PDF
10_Government_Property_Cover_Sheet_14_Jun_16.pdf PDF
01_Model_Contract_14_Jun_16.pdf PDF
02b_CDRLs_(GPSIII)_Exhibit_B__14_Jun_16.pdf PDF
Blank_CRM.xlsx XLSX spreadsheet
02a_CDRLs_(GPSIII)_Exhibit_A__14_Jun_16.pdf PDF
07_Instructions_to_Offerors_GPS_III_14_June_16.pdf PDF
08_Evaluation_Criteria_GPS_III_14_Jun_16.pdf PDF
11_Payment_Plan_GPS_III_14_Jun_16.pdf PDF
05_Small_Business_Plan_14_Jun_16.pdf PDF
06_Acceptance_Criteria_14_Jun_16.pdf PDF
04_DD_254_14_Jun_16.pdf PDF
09_Mission_Requirements_Annex_Cover_Sheet_14_Jun_16.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 9: Payment Plan for

FA8811-16-R-0006

3 August 2016

I. Basis of Payment The basis of payment for this effort shall be the successful accomplishment of event milestones scheduled for a Launch Service mission throughout the period of performance of any order issued under the contract. The milestones represent meaningful efforts or actions that are an integral and necessary part of order performance. The basis for an event should be either specifically described events or a measurable criterion of performance. Included within this Payment Plan is a description of what constitutes successful performance of each event. For purposes of establishing and calculating payment amounts, a percentage of the total contract price for all applicable firm fixed price (FFP) Contract Line Item Numbers (CLINs) pertaining to the mission (CLINs 0001 – 0003) will be assigned to each milestone. The dollar amount associated with each milestone will be calculated based on the percentages assigned to each milestone. This contract is for the procurement of a Global Positioning System III (GPS III) mission only; therefore, requirements with specific National Reconnaissance Office (NRO)-only references are not applicable. NRO-only references appear in grey text.

A. Milestone Success Criteria and Completion Evidence Each event milestone has associated measurable success criteria that serve to validate milestone accomplishment. All milestone success criteria must be met before the milestone payment will be authorized. When the Launch Vehicle Contractor (LVC) has successfully completed all applicable milestone success criteria, the LVC shall submit a written Notice of Completion (NOC) for the milestone to the Procurement Contracting Officer (PCO). The NOC shall include supporting documentation to substantiate meeting the milestone success criteria as provided in the completion evidence defined herein.

B. Event Milestone Payments and Event Timing Completion of milestones and subsequent NOCs may be submitted non-successively (e.g., if milestone two is completed before milestone one, then the LVC may submit a NOC for milestone two before a NOC for milestone one). Therefore, the NOC may be for multiple milestones. In the event the LVC completes a milestone ahead of the milestone completion date, the LVC may include that milestone in the monthly NOC and the Government will consider, on a case-by-case basis, the early payment of the milestone.

The PCO will determine whether or not the LVC has successfully met each of the milestone success criteria based on inputs provided by the United States Government (USG) Team (for Air Force missions) and the Mission Team (for NRO missions).

For Air Force missions, the USG Team consists of the Air Force Space and Missile Systems Center, Launch Systems Enterprise Directorate (SMC/LE), and Air Force Program Executive Officer for Space (AFPEO/SP) office personnel, but also includes The Aerospace Corporation, LE’s Systems Engineering and Integration (SE&I) Contractor, LE’s Systems Engineering and Technical Assistance (SETA) support Contractors, the NRO/OSL (as applicable), the SMC Independent Readiness Review Team (IRRT), Defense Contract Management Agency (DCMA), Defense Contract Audit Agency (DCAA), 30th Space Wing (30 SW), 45th Space Wing (45 SW), and other organizations as designated by the SMC/LE PCO.

For NRO missions, in addition to the USG Team listed above for Air Force missions, the Mission Team consists of the OMM, the OSL COTR, and their support personnel (to include Government, Aerospace Corporation, and SETA personnel). At their discretion, the OMM and COTR may solicit inputs from SMC/LE to assist in their determination of the LVC’s satisfactory completion of the milestone success criteria. Written concurrence from both the OMM and COTR that the LVC has successfully met the milestone success criteria is required before the PCO will authorize payment of the milestone.

To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC, the PCO will provide written notification to the LVC specifying which milestones contained in the NOC are determined to be “met” (complete) and, if necessary, which are considered “not met” (incomplete). For milestones identified as incomplete, the PCO will: (1) specify in the notification the issue(s) that led to the determination based upon the milestone success criteria and completion evidence provided herein, and

(2) the corrective action(s) required to complete the milestone. The Government and LVC will ensure agreement and understanding of the corrective actions, and the LVC will make a good faith effort to quickly reconcile any incomplete milestones. When the LVC accomplishes the corrective actions, the LVC will submit a NOC addendum to the PCO for Government review. To the maximum extent possible within fifteen (15) business days after receipt of the LVC’s NOC addendum, the PCO will provide a written notification to the LVC specifying whether the Government concurs that all corrective actions have been accomplished and the milestone has been “met” (completed).

For each milestone, the Estimated Completion Date is the estimated date that the LVC will complete the payment event and submit the associated NOC for payment of each milestone under this Plan. For each milestone, the value in the percentage “%” column of Table 1 indicates the percentage of the contract value of all applicable FFP CLINs (CLINs 0001 – 0003) that will be used to calculate the dollar amount to be paid to the LVC upon successful completion of the milestone. The Government reserves the right to withhold up to fifty percent (50%) of the total payment value for any unpaid milestone(s) in the event of a Government-approved Class 1 change required for the launch service that is not implemented/completed to meet the Government’s approval by the implementation deadlines specified in and IAW Performance Work Statement (PWS) section 3.2.4, Table 1.

C. Event Milestone Schedule Criteria for payment of each event milestones appear in Table 1. In no event shall the LVC receive payments in excess of 85% of the total contract price until after acceptance of the launch service in accordance with Milestone 11 [Space Vehicle (SV) delivery on orbit IAW contract clause Federal Acquisition Regulation (FAR) 52.212-04, Addendum to Contract Terms and Conditions—Commercial Items (Sep 2013)]. Given that defects in service for the last milestone 11, Acceptance of Launch Service, are not suitable for correction by re-performance, the Contracting Officer has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event of milestone 11 defect (e.g., mission failure) is to reduce the contract price by the amount of the full milestone 11 payment, which appropriately reflects the reduced value of the services performed.

Similarly, to milestone 11, defects in service for milestone 10, Upper Stage Disposal, Final ADCL, and Final ABCL, are not suitable for correction by re-performance; therefore, the Contracting Officer has determined that, pursuant to FAR 52.246-4(e), the appropriate relief for the Government in the event of milestone 10 defect is to reduce the contract price by the amount of the full milestone 10 payment, which appropriately reflects the reduced value of the services performed.

Table 1: Payment Event Schedule

Milestone

Payment Event Accomplishment Criteria

Est.

Comp.

Date

Total Payment (Dollar Value)*

% of FFP CLINs

0001-0003

Initial Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary; Initial Draft Integrated Master Schedule (IMS); Initial Hazardous Materials Management Program (HMMP) Plan;

Initial Payload Integration & Ops Plan; Initial Flight Critical Items List (FCIL);

Launch Service Provider Space Flight Worthiness (SFW) of Non-Recurring Engineering (NRE) work closure schedule;

Procurement initiated of Long lead hardware; and completed Mission Kickoff Meeting (KOM)

- First submission and Government acknowledgement of receipt of the following: initial CWBS and CWBS Dictionary IAW CDRL A005; initial draft IMS IAW CDRL A006; HMMP Plan IAW CDRL B004; initial Payload Integration & Ops Plan IAW CDRL B016; and initial FCIL IAW

CDRL B018.

- Submission and Government approval of the baseline schedule for NRE work closure IAW CDRL B020.

- Long lead hardware procurement or build initiated as required.

- KOM completed IAW PWS Appendix H.

ATP + 1

Month

To Be Filled In

By Offeror

10%

Initial As Designed Configuration List (ADCL);

IMS; and Launch Vehicle Familiarization Course (FAM Course) training materials

- Submission and Government acknowledgement of receipt of the initial ADCL for the launch vehicle

IAW CDRL A009.

-Submission and Government approval of the IMS IAW CDRL A006; and the FAM Course training materials IAW CDRL A007.

ATP + 2

Months

To Be Filled In

By Offeror

5%

Preliminary mission Interface Control Document (ICD); Initial Launch Vehicle Test & Verification Plan (LVT&VP); Initial Systems Safety Program Plan (SSPP); Initial compliance document tailoring submission; and Final Mission Integration Management Plan (MIMP)

- Submission and Government acknowledgement of receipt of the following: preliminary mission ICD IAW CDRL B009; initial LVT&VP IAW CDRL A010; initial SSPP IAW CDRL B002; and initial compliance documents tailoring IAW CDRL B005.

- Submission and Government approval of the final MIMP IAW

CDRL B008.

ATP + 3

Months

To Be Filled In

By Offeror

5%

Initial Verification Planning Matrix (VPM); Initial Flight Hardware Interface Checks;

Updated FCIL; Updated ADCL; Updated Payload

- Submission and Government acknowledgement of receipt of initial VPM IAW CDRL B011 and initial Flight Hardware Interface Checks

IAW CDRL A011.

ATP + 6

Months

To Be Filled In

By Offeror

10%

Integration & Ops Plan; and Final LVT&VP

- Submission and Government approval of the following: updated FCIL IAW CDRL B018; updated ADCL IAW CDRL A009; updated Payload Integration & Operations Plan IAW CDRL B016; and final

LVT&VP IAW CDRL A010.

Preliminary Coupled Loads Analysis (CLA); Updated

ADCL

- Submission and Government acknowledgement of receipt of preliminary CLA complete and delivery of results IAW CDRL B010.

- Submission and Government approval of the updated ADCL IAW

CDRL A009.

ATP + 8

Months

To Be Filled In

By Offeror 5%

Updated ADCL; Baseline Mission ICD; Updated VPM; Final Payload Integration & Ops Plan;

Final FCIL; Initial ABCL;

Completion of all NRE Work Closure Plan tasks;

Final Technical Rationale for all Class 1A changes Mission Design Review (MDR) Completed; and Completed Flight Hardware Interface Checks

- Submission and Government approval of the following: Updated ADCL IAW CDRL A009; updated baseline mission ICD IAW B009;

updated VPM IAW CDRL B011;

final Payload Integration & Ops Plan IAW CDRL B016; final FCIL IAW

CDRL B018

- Submission and Government acknowledgment of receipt of the initial ABCL IAW CDRL A012.

- Evidence demonstrating the completion of all NRE Work Closure Plan tasks IAW CDRL B020; and

- Final technical rationale for all Class 1A changes IAW PWS Section 3.2.4.

- MDR completed IAW Appendix H.

- Flight Hardware Interface Checks completed IAW PWS Section 3.4.11.

L – 12 Months

To Be Filled In

By Offeror

20%

Launch countdown parameters and operational redline limits; Mission Assurance Data; Updated ADCL; Updated As Built Configuration List (ABCL);

and completion of the Mission Verification Review

(MVR)

- Submission and Government acknowledgement of receipt of the Launch countdown parameters and operational redline limits baseline IAW Performance Work Statement (PWS) Section 3.2.7; and, Mission Assurance Independent Assessment Data IAW CDRL B010 to include:

intermediate unguided three Degrees of Freedom (3DOF); Collision and Contamination Avoidance Maneuver (CCAM) memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis; engineering drawings; and transportation environments.

L – 6 Months

To Be Filled In

By

10%

- Submission and Government approval of the updated ADCL IAW CDRL A009 and updated ABCL

IAW CDRL A012.

- MVR completed IAW Appendix H.

Verification Evidence Record; Updated ADCL;

Updated ABCL; Completion of Ground Operations Readiness Review (GORR)

- Submission and Government acknowledgement of receipt of at least 30% of Verification Evidence Record IAW CDRL B012.

- Submission and Government approval of updated ADCL IAW CDRL A012 and updated ABCL

IAW CDRL A009.

- GORR completed IAW PWS Appendix H.

L – 3

Months

To Be Filled In

By Offeror

5%

Verification Evidence Record; Updated ADCL;

Updated ABCL; Mission Assurance Data; Completion of Hardware Pre-Ship Review(s) and Independent Hardware Review(s); and Completion of Component and Subsystem Readiness Review (CSRR)

- Submission and Government acknowledgement of receipt of at least 60% of Verification Evidence Record IAW CDRL B012; and, Mission Assurance Independent Assessment Data IAW CDRL B010:

controls tools input data; controls analysis outputs (except pad/launch drift analysis); acoustics, shock, and vibration testing; and interface environments.

- Submission and Government approval of updated ADCL IAW CDRL A009 and updated ABCL

IAW CDRL A012.

- Completion of major launch vehicle hardware pre-ship reviews and Government independent hardware review(s) complete IAW PWS 3.6.6 and 3.6.5 respectively.

- Completion of CSRR IAW PWS Appendix H.

L – 2 Months

To Be Filled In

By Offeror

10%

Upper Stage Disposal; Final ADCL; and Final ABCL approval of compliance with upper stage disposal requirements.

- Submission and Government approval of Final ADCL IAW CDRL A009 and final ABCL IAW CDRL A012.

L + 2 Months

To Be Filled In

By Offeror

5%

Government Acceptance of Launch Service approval of final post-flight assessment report IAW CDRL B006;

and Government approval of the launch (launch has not been deemed “mission failure”) IAW Federal

L + 2 Months

To Be Filled In

By

15%

Acquisition Regulation (FAR) 52.212-04 and the Launch Service Acceptance Criteria (LSAC) outlined in contract Attachment 4.

*The dollar amount for each milestone is to be filled in by the Offeror, and is equal to the percentage listed in the last column multiplied by the value of the contract (CLINs 0001 – 0003) prior to award of each milestone. No adjustment to the payment will occur after milestone award.

MILESTONE 1: Initial CWBS and CWBS Dictionary, Initial Draft IMS, Initial HMMP Plan, Initial Payload Integration & Ops Plan, Initial FCIL, Approval of NRE work closure schedule, Procurement Initiated of Long Lead Hardware, and Completed Mission Kickoff Meeting

Description:

(1) Initial CWBS and CWBS Dictionary. LVC’s initial CWBS and CWBS Dictionary delivered and

Government has acknowledged receipt IAW CDRL A005.

(2) Initial Draft IMS. LVC’s initial draft IMS delivered and Government has acknowledged receipt

IAW CDRL A006.

(3) HMMP Plan. LVC’s initial HMMP plan delivered and the Government has acknowledged receipt

IAW PWS paragraph 3.1.15 and Contract Data Requirements List (CDRL) B004.

(4) Initial Payload Integration and Ops Plan. LVC’s initial Payload Integration and Operations plan delivered and the Government has acknowledged receipt IAW PWS paragraph 3.5.1.9.1 and

CDRL B016.

(5) Initial FCIL. LVC’s initial FCIL delivered and the Government has acknowledged receipt IAW PWS paragraph 3.6.5 and CDRL B018.

(6) NRE Work Closure Schedule. LVC’s baseline launch service provider NRE work closure schedule and plan delivered and approved by the Government IAW CDRL B020.

(7) Long Lead Hardware Procurement or Production Initiated. LVC has initiated procurement orders for or production of long lead hardware required for the mission.

(8) Mission Kickoff Meeting. LVC has conducted the KOM IAW PWS Appendix H with actions and action closure plans and accepted by the Government.

Success Criteria:

(1) The LVC has delivered and Government has acknowledged receipt of initial CWBS and CWBS Dictionary IAW CDRL A005.

(2) The LVC has delivered and Government has acknowledged receipt of initial draft IMS IAW

CDRL A006.

(3) The LVC has delivered and Government has acknowledged receipt of initial HMMP IAW CDRL B004.

(4) The LVC has delivered and Government has acknowledged receipt of initial Payload Integration and Ops Plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.

(5) The LVC has delivered and Government has acknowledged receipt of initial FCIL IAW PWS paragraph 3.6.5 and CDRL B018.

(6) The LVC has delivered and Government has approved the baseline launch service provider SFW NRE work closure schedule and plan IAW CDRL B020.

(7) The LVC has initiated procurement orders for or production of long lead hardware required for the mission.

(8) The LVC has conducted the KOM IAW PWS Appendix H with actions and action closure plans and accepted by the Government.

Completion Evidence:

(1) CDRL A005 initial draft CWBS and CWBS Dictionary accepted by the PCO, appropriate COR, or appropriate COTR.

(2) CDRL A006 initial draft IMS accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL B004 initial draft HMMP plan accepted by the PCO, appropriate COR, or appropriate COTR.

(4) CDRL B016 initial draft Payload Integration and Operations plan accepted by the PCO, appropriate COR, or appropriate COTR.

(5) CDRL B018 initial FCIL accepted by the PCO, appropriate COR, or appropriate COTR.

(6) CDRL B020 baseline launch service provider SFW NRE work closure plan and schedule accepted by the PCO, appropriate COR, or appropriate COTR.

(7) Long lead hardware procurement or build initiated as required. Copies of signed, written procurement or build orders for all long lead hardware required for the mission received and accepted by the PCO, appropriate Contracting Officer Representative (COR) or appropriate Contracting Officer Technical Representative (COTR).

(8) KOM meeting minutes documenting meeting completion, action items, and action item closure plans.

MILESTONE 2: First Submission ADCL, Approved IMS, and Launch Vehicle FAM Course Materials Approval

Description:

(1) ADCL. LVC’s initial ADCL delivered and Government has acknowledged receipt IAW

CDRL A009.

(2) IMS. The LVC has delivered and the Government has approved the IMS IAW PWS paragraph 3.1.4 and CDRL A006.

(3) Launch Vehicle FAM Course Materials. LVC’s LV familiarization training materials required by CDRL A007 delivered and approved by the Government IAW PWS paragraph 3.1.10 and CDRL A007.

Success Criteria:

(1) The LVC has delivered and the Government has acknowledged receipt of the initial

ADCL IAW CDRL A009.

(2) The LVC has delivered and the Government has approved the IMS IAW PWS paragraph

3.1.4 and CDRL A006.

(3) The LVC has delivered and the Government has approved the submission of all LV familiarization training materials required by and IAW CDRL A007.

Completion Evidence:

(1) CDRL A009 initial ADCL accepted by the PCO, appropriate COR, or appropriate

COTR.

(2) CDRL A006 IMS accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL A007 submission of LV FAM Course training materials accepted by the PCO, appropriate COR, or appropriate COTR.

MILESTONE 3: Preliminary ICD, Initial LVT&VP, Initial SSPP, Initial Compliance Document Tailoring, and Final MIMP Contractor

Description:

(1) ICD. LVC’s initial baseline mission ICD delivered and the Government has acknowledged receipt IAW PWS paragraph 3.4.4 and CDRL B009.

(2) LVT&VP. LVC’s initial LVT&VP delivered and the Government has acknowledged receipt IAW CDRL A010.

(3) SSPP. LVC’s first draft SSPP delivered and the Government has acknowledged receipt IAW PWS 3.1.7 and CDRL B002.

(4) Compliance Document Tailoring. LVC’s initial compliance documents tailoring delivered and the Government has acknowledged receipt CDRL B005.

(5) MIMP. The LVC has delivered and the Government has approved the final MIMP IAW

CDRL B008.

(1) The LVC has delivered and the Government has acknowledged receipt of the initial, first draft baseline mission ICD IAW CDRL B009.

(2) The LVC has delivered and the Government has acknowledged receipt of the initial LVT&VP

IAW CDRL A010.

(3) The LVC has delivered and the Government has acknowledged receipt of the initial, first draft

SSPP IAW CDRL B002.

(4) The LVC has delivered and the Government has acknowledged receipt of initial Compliance Documents Tailoring IAW CDRL B005.

(5) The LVC has delivered and the Government has approved the final MIMP IAW CDRL B008.

(1) CDRL B009 initial, first draft baseline mission ICD accepted by the PCO, appropriate

Contracting Officer Representative (COR) or appropriate Contracting Officer Technical Representative (COTR).

(2) CDRL A010 initial LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL B002 first draft SSPP accepted by the PCO, appropriate COR or appropriate COTR.

(4) CDRL B005 initial Compliance Documents Tailoring accepted by the PCO, appropriate COR or appropriate COTR.

(5) CDRL B008 final MIMP accepted by the PCO, appropriate COR or appropriate COTR.

MILESTONE 4: Initial VPM, Initial Flight Hardware Interface Checks, updated FCIL, updated ADCL, updated Payload Integration & Ops Plan, and Final LVT&VP

Description:

(1) VPM. LVC’s first draft VPM delivered and the Government has acknowledged receipt IAW

CDRL B011.

(2) Flight Hardware Interface Checks. LVC’s initial Flight Hardware Interface Checks delivered and the Government has acknowledged receipt IAW CDRL A011.

(3) FCIL. The LVC has delivered and the Government has approved the updated FCIL IAW PWS paragraph 3.6.5 and CDRL B018.

(4) ADCL. The LVC has delivered and the Government has approved the updated ADCL

IAW CDRL A009.

(5) Payload Integration & Ops Plan. The LVC has delivered and the Government has approved the updated integration and operations plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.

(6) LVT&VP. The LVC has delivered and the Government has approved the final LVT&VP

IAW CDRL A010.

(1) The LVC has delivered and the Government has acknowledged receipt of the first draft VPM

IAW CDRL B011.

(2) The LVC has delivered and the Government has acknowledged receipt of the initial Flight

Hardware Interface Checks IAW CDRL A011.

(3) The LVC has delivered and the Government has approved the updated FCIL IAW PWS paragraph 3.6.5 and CDRL B018.

(4) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(5) The LVC has delivered and the Government has approved the updated integration and operations plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016.

(6) The LVC has delivered and the Government has approved the final LVT&VP IAW CDRL A010.

(1) CDRL B011 first draft VPM accepted by the PCO, appropriate COR, or appropriate COTR.

(2) CDRL A011 initial Flight Hardware Interface Checks accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL B018 updated FCIL accepted by the PCO, appropriate COR, or appropriate COTR.

(4) CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

(5) CDRL B016 updated Integration and Ops Plan accepted by the PCO, appropriate COR, or appropriate COTR.

(6) CDRL A010 final LVT&VP accepted by the PCO, appropriate COR, or appropriate COTR.

MILESTONE 5: Preliminary Coupled Loads Analysis and Updated ADCL submission

Description:

(1) Preliminary CLA. LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL B010.

(2) Updated ADCL. The LVC has delivered and Government has approved the updated ADCL

IAW CDRL A009.

Success Criteria:

(1) LVC has completed preliminary CLA, submitted the preliminary CLA data, and the Government has acknowledged receipt of the CLA data IAW CDRL B010.

(2) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(1) CDRL B010 Mission Assurance Independent Data preliminary CLA data accepted by the PCO, appropriate COR, or appropriate COTR.

(2) CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

MILESTONE 6: Updated ADCL, Updated Baseline Mission ICD, Updated VPM, Final Payload Integrations & Ops Plan, Final FCIL, Initial ABCL, Launch Service Provider SFW NRE Work Closure Plan Complete, Submission for Rationale for All Class 1A Changes MDR completed, and Flight Hardware Interface Checks Complete

Description:

(1) Updated ADCL. LVC’s updated ADCL delivered and Government has approved IAW

CDRL A009.

(2) Updated Baseline Mission ICD. LVC’s updated baseline mission ICD IAW CDRL B009 has been approved by the Government.

(3) Updated Verification Planning Matrix (VPM). LVC has submitted and the Government has approved the updated VPM IAW CDRL B011.

(4) Final Payload Integration & Ops Plan. The LVC has delivered and the Government has approved the final Integration and Ops Plan IAW PWS paragraph 3.5.1.9.1 and CDRL B016. CDRL A012 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate COTR.

(5) Final FCIL. The LVC has delivered and the Government has approved the final FCIL IAW

CDRL B018.

(6) Initial ABCL. LVC’s initial ABCL delivered and Government has acknowledged receipt

IAW CDRL A012.

(7) Launch Service Provider SFW NRE Work Closure Plan Complete. LVC’s launch service provider SFW NRE work is complete with Government-approved exceptions allowed and all action items have been closed with Government-approved exceptions allowed IAW the LVC’s Government-approved baseline SFW NRE work closure plan and schedule, CDRL B020.

(8) Rationale for All Class 1A Changes. LVC’s has submitted technical rationale for all Class 1A changes and approved by the Government IAW PWS Section 3.2.4.

(9) Flight Hardware Interface Tests. The LVC shall perform tests to verify the compatibility of the physical and electrical interfaces and clearances between the LV and SV IAW PWS sections

3.4.11 and 3.4.12 and CDRL A011. The LVC shall perform mechanical fit-checks of the adapter harness to the standard electrical interface panel for each SV. The testing shall verify that all physical interfaces meet mission ICD requirements. These tests shall be performed, with Space Vehicle Contractor (SVC)/Launch System Integration Contractor (LSIC) support, to satisfy all applicable requirements in the ICD, contract PWS, and CDRL A011.

(1) CDRL A009 updated ADCL submission received and approved by the Government.

(2) CDRL B009 updated ICD submission received and approved by the Government.

(3) CDRL B011 updated VPM submission received and approved by the Government.

(4) CDRL B016 final Payload Integration & Ops Plan submission received and approved by the

Government.

(5) CDRL B018 final FCIL submission received and approved by the Government.

(6) LVC has delivered and the Government has acknowledged receipt of the initial ABCL IAW

CDRL A012.

(7) CDRL B020 baseline launch service provider SFW NRE Work Closure Plans submission received and approved by the Government.

(8) Technical rationale for all Class 1A changes IAW PWS Section 3.2.4 submission received and approved by the Government.

(9) Flight hardware interface checks have been performed IAW PWS sections 3.4.11 and 3.4.12 and

CDRL A011.

a. CDRL A011 second submission of as-run interface check procedures received and accepted by the Government.

(1) CDRL A009 updated ADCL submission accepted by the PCO, appropriate COR, or appropriate

COTR.

(2) CDRL B009 updated ICD submission accepted by the PCO, appropriate COR, or appropriate

COTR.

(3) CDRL B011 updated VPM submission accepted by the PCO, appropriate COR, or appropriate

COTR.

(4) CDRL B016 final Payload Integration & Ops Plan submission accepted by the PCO, appropriate COR, or appropriate COTR.

(5) CDRL B018 final FCIL submission accepted by the PCO, appropriate COR, or appropriate

COTR.

(6) CDRL A012 initial ABCL submission accepted by the PCO, appropriate COR, or appropriate

COTR.

(7) CDRL B020 submission accepted by the PCO, appropriate COR, or appropriate COTR.

(8) Rationale submission accepted by the PCO, appropriate COR, or appropriate COTR.

(9) CDRL A011 Flight hardware interface checks submission accepted by the PCO, appropriate

COR, or appropriate COTR.

MILESTONE 7: Launch Countdown Parameters and Operational Redline Limits, Mission Assurance Data, Updated ADCL, Updated ABCL, and completion MVR

Description:

(1) Launch countdown parameters and operational redline limits. LVC’s Launch countdown parameters and operational redline limits delivered and Government has acknowledged receipt IAW PWS Section 3.2.7.

(2) Mission Assurance Data. LVC’s Mission Assurance Independent Assessment Data delivered and Government has acknowledged receipt IAW CDRL B010.

(3) Updated ADCL. The LVC has delivered and Government has approved the updated ADCL

IAW CDRL A009.

(4) Updated ABCL. The LVC has delivered and Government has approved the updated ABCL

IAW CDRL A012.

(5) Completion MVR. LVC’s shall conduct MVR IAW PWS Appendix H.

Success Criteria:

(1) The LVC has delivered and the Government has acknowledged receipt of the Launch countdown parameters and operational redline limits baseline IAW PWS Section 3.2.7.

(2) The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance

Independent Assessment Data IAW CDRL B010 to include: intermediate unguided three Degrees of Freedom (3DOF); Collision and Contamination Avoidance Maneuver (CCAM) memo; acoustics, shock, and vibration environments; vibroacoustic modeling and analysis;

engineering drawings; and transportation environments.

(3) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(4) The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.

(5) The LVC has conducted the MVR IAW PWS Appendix H with actions and action closure plans identified and accepted by the Government.

Completion Evidence:

(1) Written acknowledgement of receipt by the PCO, appropriate COR, or appropriate COTR of the launch countdown parameters and operational redline limits baseline

(2) CDRL B010 Mission Assurance Independent Assessment Data accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

(4) CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.

(5) MVR meeting minutes documenting meeting completion, action items, and action item closure plans.

MILESTONE 8: Verification Evidence Record, Updated ADCL, Updated ABCL, and Completion of GORR

Description:

(1) Verification Evidence Record. LVC’s receipt of at least 30% of Verification Evidence Record delivered and Government has acknowledged receipt IAW B012.

(2) Updated ADCL. The LVC has delivered and Government has approved the updated ADCL

IAW CDRL A009.

(3) Updated ABCL. The LVC has delivered and Government has approved the updated ABCL

IAW CDRL A012.

(4) Completion GORR. LVC’s shall conduct GORR IAW PWS Appendix H.

(1) The LVC has submitted and the Government has acknowledged receipt of at least 30% of the

Verification Evidence Record IAW CDRL B012.

(2) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(3) The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.

(4) The LVC has conducted the GORR IAW PWS Appendix H with actions and action closure plans identified and accepted by the Government.

(1) At least 30% of the CDRL B012 Verification Evidence Record accepted by the PCO, appropriate

COR, or appropriate COTR.

(2) CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.

(4) GORR meeting minutes documenting meeting completion, action items, and action item closure

MILESTONE 9: Verification Evidence Record, Updated ADCL, Updated ABCL, Mission Assurance Data, Completion of Hardware Pre-Ship Review(s) and Independent Hardware Review(s), and completion of Component and Subsystem Readiness Review (CSRR)

Description:

(1) Verification Evidence Record. LVC’s receipt of at least 60% of Verification Evidence Record delivered and Government has acknowledged receipt IAW B012.

(2) Updated ADCL. The LVC has delivered and Government has approved the updated ADCL

IAW CDRL A009.

(3) Updated ABCL. The LVC has delivered and Government has approved the updated ABCL

IAW CDRL A012.

(4) Mission Assurance Data. LVC’s Mission Assurance Data delivered and Government has acknowledged receipt IAW CDRL B010 to include:

a. Controls tools input data

b. Controls analysis outputs (except pad/launch drift analysis)

c. Acoustics, shock, and vibration testing

d. Interface environments

(5) The LVC shall conduct and complete pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.6. These major launch vehicle elements shall include:

a. Core booster(s)

b. Upper stage

c. Payload fairing

d. Payload adapter, and

e. Solid rocket motors (as applicable)

(6) CSRR. LVC’s shall conduct CSRR IAW PWS Appendix H.

Success Criteria:

(1) The LVC has submitted and the Government has acknowledged receipt of at least 60% the Verification Evidence Record IAW CDRL B012.

(2) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(3) The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.

(4) The LVC has delivered and the Government has acknowledged receipt of the Mission Assurance

Data to IAW CDRL B010 to include:

(1a) The LVC has submitted and the Government has acknowledged receipt of the controls tools input data (CDRL B010).

(1b) The LVC has submitted and the Government has acknowledged receipt of the controls analysis outputs (except pad/launch drift analysis) (CDRL B010).

(1c) The LVC has submitted and the Government has acknowledged receipt of the acoustics, shock, and vibration testing results (CDRL B010).

(1d) The LVC has submitted and the Government has acknowledged receipt of the interface environments (CDRL B010).

(5) The LVC has delivered and the Government has acknowledged receipt of the pre-ship reviews for the major launch vehicle elements prior to shipment to the launch site IAW PWS paragraph 3.6.6 to include:

(2a) The LVC has conducted, completed, and the Government has acknowledged completion in writing of a pre-ship review for the core booster(s) IAW PWS paragraph 3.6.6.1.

(2b) The LVC has conducted, completed, and the Government has acknowledged completion in writing of a pre-ship review for the upper stage IAW PWS paragraph 3.6.6.1.

(2c) The LVC has conducted, completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload fairing IAW PWS paragraph 3.6.6.1.

(2d) The LVC has conducted, completed, and the Government has acknowledged completion in writing of a pre-ship review for the payload adapter IAW PWS paragraph 3.6.6.1.

(2e) The LVC has conducted, completed, and the Government has acknowledged completion in writing of a pre-ship review for the solid rocket boosters (as applicable) IAW PWS paragraph 3.6.6.1.

(6) The LVC has conducted the CSRR IAW PWS Appendix H with actions and action closure plans identified and accepted by the Government.

Completion Evidence:

(1) At least 60% of CDRL B012 Verification Evidence Record accepted by the PCO, appropriate

COR, or appropriate COTR.

(2) CDRL A009 updated ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL A012 updated ABCL accepted by the PCO, appropriate COR, or appropriate COTR.

(4) CDRL B010 Mission Assurance Data accepted by the PCO, appropriate COR, or appropriate

COTR.

(5) Delivery of the Hardware Pre-Ship Review(s) and Independent Hardware Review(s) IAW PWS

3.6.5 and 3.6.6 accepted by the PCO, appropriate COR, or appropriate COTR. (2a-e) Written acknowledgment by the Government that pre-ship reviews have been completed for the core booster(s), upper stage, payload fairing, payload adapter, and (as applicable) solid rocket booster(s) IAW PWS paragraph 3.6.6.1.

(6) CSRR meeting minutes documenting meeting completion, action items, and action item closure

MILESTONE 10: Upper Stage Disposal, Final ADCL, and Final ABCL

(1) The LVC shall identify which upper stage disposal method was planned and flown (random atmospheric reentry, controlled atmospheric reentry, maneuvering to a storage orbit, direct retrieval) IAW CDRL B006.

(2) The LVC shall provide telemetry data confirming the depletion of propellant by blowdown or depletion burn and the release compressed gases IAW CDRL B006.

(3) Upper Stage Disposal Approach: The LVC shall provide the following information appropriate to the selected method of disposal for the as-flown upper stage IAW CDRL B006.

a. Random atmospheric reentry. Value for risk of human casualty, state vector for end of mission upper stage disposal orbit, disposal orbit lifetime for upper stage based on as-flown end of mission, description of analysis that produced the upper stage disposal orbit lifetime value.

b. Controlled atmospheric reentry. Latitude and longitude of upper stage reentry impact location and comparison to Notice to Airmen and Mariners (NOTAM) box.

c. Maneuvering to storage orbit. Orbital elements at end of mission for as flown upper stage

d. Direct retrieval. Description of retrieval operation. Time after end of mission when upper stage will be removed.

(4) Final ADCL. The LVC has delivered and Government has approved the final ADCL IAW

CDRL A009.

(5) Final ABCL. The LVC has delivered and Government has approved the final ABCL IAW

CDRL A012.

Success Criteria:

(1) Upper stage disposal method identified IAW CDRL B006.

(2) Telemetry data confirming the depletion of propellant by blowdown or depletion burn and the propellant and compressed gas depletion was performed on the upper stage prior to end of mission IAW CDRL B006.

(3) Upper Stage Disposal Approach:

a. Random atmospheric reentry.

i. Risk of human casualty is less than 1 in 10,000.

ii. Disposal orbit lifetime is no longer than 25 years.

b. Controlled atmospheric reentry. Impact location is within the Notice to Airmen and

Mariners (NOTAM) box.

c. Maneuvering to storage orbit. End of mission disposal orbit is within one of the storage orbit regimes described in the USG Orbital Debris Mitigation Standard Practices (4-1b).

d. Direct retrieval. Upper stage is removed within the time defined in Space Debris

Assessment Report (SDAR) for this mission.

(4) The LVC has delivered and the Government has approved the updated ADCL IAW CDRL A009.

(5) The LVC has delivered and the Government has approved the updated ABCL IAW CDRL A012.

(1) Orbital Debris Compliance - CDRL B006, Final Post Flight Assessment Report (to include post-mission disposal of the upper stage). This CDRL shall include the required items appearing in the description portion of this milestone.

(2) CDRL B006 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO, appropriate COR, or appropriate COTR.

(3) CDRL B006 final post flight assessment report accepted by the PCO, appropriate COR, or appropriate COTR. Telemetry data confirming upper stage disposal accepted by the PCO, appropriate COR, or appropriate COTR.

(4) CDRL A009 final ADCL accepted by the PCO, appropriate COR, or appropriate COTR.

(5) CDRL A012 final ABCL accepted by the PCO, appropriate COR, or appropriate COTR.

MILESTONE 11: Government Acceptance of Launch Service

(1) The LVC has delivered and Government has approved the Final Post Flight Assessment Report

IAW CDRL B006.

(2) The Launch Service Order has been accepted by the Government IAW contract clause FAR

52.212-04 and contract Attachment 4, Launch Service Acceptance Criteria (LSAC).

Success Criteria:

(1) The LVC has delivered and the Government has approved the Final Post Flight Assessment

Report IAW CDRL B006.

The mission has not been deemed a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.

(2) The Launch Service Order has been accepted by the PCO IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.

(1) CDRL B006 final submission accepted by the PCO, appropriate COR, or appropriate COTR.

(2) No written determination by the Director, Space and Missile Systems Center, Launch Systems Enterprise Directorate (SMC/LE) deeming the Launch Service Order a “Mission Failure” IAW contract clause FAR 52.212-04 and Attachment 4, LSAC.

PCO’s written notification to the LVC that the mission launched has been accepted by the Government IAW contract clause FAR 52.212-04 and contract Attachment 4, LSAC.

Orbital Debris Compliance - CDRL B006 final submission, Final Post Flight Assessment Report (to include post-mission disposal of the upper stage).