This Request for Quote (RFQ) 15M30025QA3700005 is for Heavy Maintenance C-check on a Boeing 737-400 aircraft for the U.S. Marshals Service (USMS) Justice Prisoner Air Transportation System (JPATS). The RFQ includes a comprehensive set of questions and responses addressing maintenance scope, timeline, and logistics. Key details include a requirement to complete all heavy check maintenance requirements within 45 days, with specific maintenance tasks to be priced as standalone items. The government will provide maintenance work packages via USB drive and will cover fuel and flight crew costs associated with aircraft delivery and return to service flights.
The document also includes technical drawings showing the aircraft's emergency equipment layout and interior configuration, detailing items such as life rafts, life vests, halon extinguishers, seat belt extensions, and other safety equipment. The maintenance check involves removing left and right engines for pylon inspections and potentially removing the APU (Auxiliary Power Unit), which is a GTCP85-129H model. The maintenance will be performed according to the tasks listed in the Performance Work Statement Section 11, with the specific date of maintenance tasks set for 10-FEB-2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTE (RFQ) 15M30025QA3700005
Heavy Maintenance C-check Boeing 737-400
Questions and Responses
3 September 2025
1. Is this contract looking to get all of the listed checks performed in the 45 day window or is it expected to be performed over an extended period of time with each visit being completed within 45 days?
GOV RESPONSE: The expectation is to have all heavy check maintenance requirements listed in PWS Section 11 completed within 45 days.
2. Is there any way we could get an example of the work cards that are contained in the listed checks?
GOV RESPONSE: If you would like to review the maintenance work package, please provide a shipping address so I can send you a USB drive.
3. Are there any Engine/APU removals or replacements scheduled? a. If so, which ones specifically and will these components/materials be provided by JPATS?
GOV RESPONSE: Yes. The left and right engines are required to be removed for pylon inspections as part of the heavy maintenance check. The APU may have to be removed.
4. Are there any Major Component overhauls or replacements scheduled? a. If so, which ones specifically and will these components/materials be provided by JPATs?
GOV RESPONSE: No
5. Can you provide the Cabin LOPA that includes all Emergency Equipment?
GOV RESPONSE: Attached
6. Is there any Emergency Equipment that is scheduled for replacement/Overhaul? a. If so, which ones specifically and will these components/materials be provided by JPATS?
GOV RESPONSE: No
7. What APU is installed?
GOV RESPONSE: GTCP85-129H
8. What is the APU Total Time (TT)?
GOV RESPONSE: Unknown
9. Should each A- and C-check package be priced as standalone or should it be assumed that there will be task overlap? a. For instance, if a 6C check is due, shall lower-level A- and C-checks be treated as included?
GOV RESPONSE: Each item listed in U.S. Marshals Service (USMS) Justice Prisoner Air Transportation System (JPATS) Boeing 737- 400 Aircraft Heavy Maintenance Check Performance Work Statement Section 11 must be priced as a standalone item.
10. Can JPATS provide the CAMPs task list that will be due on 10-FEB-2026?
GOV RESPONSE: JPATS will provide a USB drive of all tasks required in U.S. Marshals Service (USMS) Justice Prisoner Air Transportation System (JPATS) Boeing 737- 400 Aircraft Heavy Maintenance Check Performance Work Statement Section 11 once a point of contract and mailing address is provided.
11. Please confirm that JPATS will cover the cost of Ground and Flight Operations
a. For example, all fuel costs and flight crew for RTS flights
GOV RESPONSE: JPATS will provide all fuel and flight crew costs associated with aircraft delivery and the return to service flight.
46Y41B
737-400 LAYOUT -
EMERGENCY EQUIPMENT
40949CM006 B
MRO Services Engineering Services
Digitally signed by Sarah Helmondollar
Digitally signed by Aaron Ozolin
40949CM006 B
MRO Services Engineering Services
| RFQ 15M30025QA3700005 Questions and Responses 3 Sep 25 |
| 40949CM006-B |
| N279AD LOPA |
File details come from the government source that posted it. Updated .