REQUEST FOR INFORMATION.pdf

PDF 91 KB Posted

Attached to
Repair Sidewalk and Blacktop at MDC Brooklyn (NY)
Solicitation number
15BBR025Q00000011
Issued by

About this file

This is a Request for Information (RFI) document addressing questions about sidewalk and pavement repair work at MDC Brooklyn. The document clarifies five key points about the project: NYC permits are not required for work on 29th street but may be needed for work on 2nd and 3rd avenue since the Bureau of Prisons does not own that property; a bid bond is required; the government will provide a secure laydown area to be determined at project start; there is a discrepancy between the report (1755 sf) and SAM.gov (2000 sf) measurements, with the larger amount accounting for potential NYC miscalculations; and contractors must follow NYCDOT specifications for sidewalks and asphalt to ensure a smooth, trip-free area.

The associated opportunity (15BBR025Q00000011) is for removing and replacing 2000 sq ft of concrete cement walkway and repairing 700 sq ft of staff parking lot with hot roadway blacktop at MDC Brooklyn. The project has a 49-day performance period, with a mandatory site visit scheduled for January 23, 2025, at 10:00 AM. Quotes are due January 27, 2025, at 10:00 AM, and evaluation will be based on past performance, lowest price, and delivery time using best value determination.

View the file

Other files

File Type Posted
STATEMENT OF WORK.pdf PDF
WAGE DETERMINATION 15-4187.txt TXT text file
CONTRACTOR INFORMATION SHEET.pdf PDF
NYC DOT SIDEWALK MANAGEMENT MAP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION

SIDEWALK AND PAVEMENT REPAIR

MDC BROOKLYN

Please see below RFI regarding the sidewalk and pavement repairs at MDC.

1. Are NYC permit required?

The work on 29th street do not require a permit but the work on 2nd and 3rd avenue may a permit as the Bureau of Prisons does not own that property.

2. Is a bid bond required?

YES

3. Will the Gov provide a secure laydown area?

Yes, will be determined when job starts.

4. Report states 1755sf vs Sam.gov 2000 sf.

The 2000 SF allows for miscalculation by NYC

5. Is the contractor following NYCDOT specs for sidewalks and asphalt.?

Yes, all work shall make for a smooth trip free area.