RFQ Attachment 004 Site Visit Meeting Minutes.pdf

PDF 411 KB Posted

Attached to
Replace Commercial Boilers Federal contract opportunity
Solicitation number
15B60924Q00000001
Issued by
Department of Justice Bureau of Prisons

About this file

This document contains the site visit meeting minutes for RFQ 15B60924Q00000001 to replace boilers at the FCI Safford correctional facility. The purpose of the site visit was to familiarize potential contractors with the unique requirements of a correctional setting. Key details include:

The work hours are 7:30 AM to 2:30 PM, Monday through Friday, excluding weekends and federal holidays. All contractor tools and hazardous materials must be strictly accounted for and cannot be stored on-site overnight. Contractors will not be allowed to bring cell phones. Questions must be submitted via email by March 29, 2024 to allow time for responses prior to the bid due date. The solicitation is for replacing 2 commercial natural gas water heaters, 4 storage tanks, 2 expansion tanks, and 2 recirculating pumps at the FCI Safford facility.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Commercial Boilers, newest first.
File Type Posted
RFQ Attachment 006 Wage Rates az25.pdf PDF
RFQ Attachment 005 Site Visit Questions and Answers.pdf PDF
15B60924Q00000001 0002 AMENDED RFQ Ocotillo Boilers.pdf PDF
Site Visit Information.pdf PDF
15B60924Q00000001 AMENDED RFQ Ocotillo Boilers.pdf PDF
Questions Boilers.pdf PDF
15B60924Q00000001 RFQ Ocotillo Boilers.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SITE-VISIT MEETING MINUTES

RFQ: 15B60924Q00000001 Replace Boilers for FCI Safford

FCI Safford – Project 24Z6AP7

Date: Wednesday, March 27, 2024, at 9:00a.m. MST

Contrac�ng Officer Nicasio Garcia:

I. Introduc�ons:

Introduc�ons with all atendees.

Atendance:

Represen�ng the Government:

Nicasio Garcia, Supervisory Contract Specialist Tucker Lucas, General Foreman Christopher Cleland, Engineering Technician

Represen�ng Vendors:

Kim Peters – Atlan�c Pacific Standard (APS) Ray White – Patriot AZ Jacobo Murillo – Bear Creek Electrical Corp.

Barry Walker - Bear Creek Electrical Corp.

II. Purpose of Site Visit:

Familiarize the contractor with the unique circumstances and requirements surrounding a correc�onal se�ng. This visit is also to explain the solicita�on, as issued, and not to furnish addi�onal informa�on.

State - nothing said during the visit shall be interpreted as a change to the solicita�on without the issuance of a formal amendment through the Supervisory Contract Specialist, Nicasio Garcia.

III. MINUTES:

Minutes will be recorded and distributed via www.sam.gov.

IV. SITE VISIT INFORMATION:

Walk to selected site for Boiler Replacement immediately following introduc�ons. The tour was greeted with a reminder that any ques�ons posed throughout the visit needed to be addressed via amendment to solicita�on, to allow all poten�al bidders availability of the ques�ons and answers.

RFQ Attachment 004

SITE-VISIT MEETING MINUTES

RFQ: 15B60924Q00000001 Replace Boilers for FCI Safford

FCI Safford – Project 24Z6AP7

V. General Topics:

• Work Hours: Work Hours for the contractor are 7:30 AM – 2:30 PM, Monday - Friday, excluding weekends and federal holidays. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and condi�ons in the correc�onal facility, as working hours may not cons�tute a full eight-hour workday.

• Ques�ons: Oral ques�ons asked at Site Visit of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpreta�on. All ques�ons shall be sent via email to Nicasio Garcia, Supervisory Contract Specialist. To provide sufficient response �me prior to the bid due date, the Government has establishing that ques�ons be submited no later than March 29, 2024.

• Storage of Materials: All construc�on materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor.

• Tool Accountability: Strict accountability and control of all contractor tools and hazardous materials must be always maintained. All contractor tools to be used inside the secure perimeter must be inventoried and accounted for at the conclusion of the workday. Contractor tools may not be stored on-site overnight. The contractor should provide for enough �me at the conclusion of the workday for the return and accoun�ng of all tools issued during the workday.

Lost or missing tools must be reported to the COR the Captain immediately.

• Addi�onal Considera�ons: Contractors will NOT be allowed to bring cell phones.

Mee�ng minutes recorded by:

Nicasio Garcia, Supervisory Contract Specialist FCI Safford

NOTICE:

MEETING MINUTES ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THEY ARE NOT

INTENDED TO CHANGE ANY SPECIFICATIONS, TERMS OR CONDITIONS OF THE

SOLICITATION. ANY AND ALL CHANGES TO THE SOLICITATION SHALL BE ISSUED IN

SUBSEQUENT AMENDMENTS ISSUED BY THE CONTRACTING OFFICER ON A STANDARD

FORM 1442 (SF-1442).