Scope of Work.docx
DOCX document 13 KB Posted
- Attached to
- REPLACE VACUM CONDENSATE SYSTEM
- Solicitation number
- 15B50724Q00000017
About this file
This document is a Scope of Work for the Federal Bureau of Prisons (FBOP), Federal Correctional Institution (FCI) El Reno to purchase supplies and materials for in-house vacuum condensate system repairs. The key requirements include a JVC-18-45-255 Skidmore Duplex Vacuum Condensate System with specific components, such as a 60-gallon steel tank, JV-18 duplex vacuum producer, and NEMA 1 700 series control panel. All supplies and materials must be submitted with full product detail sheets and specifications, and deliveries must be made between 8:00 AM and 2:30 PM, Monday through Friday, excluding federal holidays. This Scope of Work is associated with Solicitation Number 15B50724Q00000017 for the "REPLACE VACUUM CONDENSATE SYSTEM" contract opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24Z5AR9 - REPLACE VACUM CONDENSATE SYSTEM RFQ.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work The Federal Bureau of Prisons (FBOP), Federal Correctional Institution (FCI) El Reno intends to purchase supplies and material for in-house vacuum condensate system repairs at FCI El Reno, located at 4205 Highway 66 West, El Reno, OK 73036.
All supplies and materials must be submitted with full product detail sheets and specifications.
B. Material and Supplies Requirements FREIGHT INCLUDED JVC-18-45-255 SKIDMORE DUPLEX VACUUM CONDENSATE SYSTEM COMPLETE WITH THE FOLLOWING:
NOTE: UNIT MUST BE AN EXACT REPLACEMENT FOR S/N 128382
(1) 60 Gallon Steel Hurling Tank
(1) JV-18 Duplex Vacuum Producer 200/3/60 - 3500 RPM - ODP Rated18 CFM @ 5 1/2" HG
(1) 3/8" Solenoid Make Up Valve Strainer
(1) Reverse Acting Float Switch
(1) Temperature Limiting Switch
(1) Gauge Glass Assembly
(2) Vacuum Switches
(1) 45 Gallon Rectangular CI RCV
(1) Mechanical Alternator
(2) CHECK VALVES
(1) Thermometer
(1) Vacuum Relief Valve
(1) Compound Gauge
(1) Gauge Glass Assembly
(1) NEMA 1 700 SERIES CONTROL COMPLETE WITH THE FOLLOWING:
(1) 24" x 24" Enclosure
(1) Disconnect Switch
(4) Fuse Blocks With Fuses
(8) "0" Magnetic Starters
(4) H.O.A. Selector Switches
(1) 208/110V Control Transf
(1) Terminal Strip
(1) Ground Lug C. Delivery of Supplies
1. Construction related deliveries which are directly shipped to the institution can be received between the hours of 8:O0 AM - 2:30 PM, Monday - Friday, excluding federal holidays.