About this file

This document appears to be a set of questions and answers (Q&As) related to a federal contract opportunity for replacing the fire sprinkler system at the Food Service Warehouse at the Federal Correctional Complex (FCC) in Coleman, Florida.

The key details are: The contract will consist of installation/labor only, as the required materials are already on site. The contractor should inventory the materials and provide a list of any additional items needed prior to mobilization. The contractor can potentially work off-shift hours, but cannot expect to work weekends or federal holidays. The contractor should not expect to use the facility's restrooms and will need to provide a portable toilet. The Statement of Work lists the specific pipe sizes, fittings, and other materials already available on site for the project. The solicitation number is 15B30224Q00000029 and the site visit will be held on September 17, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to FCC COLEMAN, REPLACE SPRINKLER SYSTEM at FOOD SERVICE WAREHOUSE PROJECT 3D6F, newest first.
File Type Posted
Material List_09.26.2024.pdf PDF
project 3d6f site visit_0001.pdf PDF
DSCN7248.JPG JPG image
DSCN7244.JPG JPG image
DSCN7240.JPG JPG image
DSCN7249.JPG JPG image
DSCN7247.JPG JPG image
DSCN7252.JPG JPG image
DSCN7243.JPG JPG image
DSCN7254.JPG JPG image
DSCN7250.JPG JPG image
DSCN7253.JPG JPG image
DSCN7251.JPG JPG image
DSCN7242.JPG JPG image
Floorplan_Sprinkler_Asbuilt.pdf PDF
DSCN7246.JPG JPG image
DSCN7255.JPG JPG image
DSCN7245.JPG JPG image
DSCN7241.JPG JPG image
DSCN7239.JPG JPG image
NCIC Form.pdf PDF
PDFRetriever (2).pdf PDF
8 - 3D6E.Sources.TAL.pdf PDF
7 - 3D6F.SOW.Sprinkler_Install_09.2024.TAL.GL.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

From Enviro-Tech Systems:

1. “The system shall be installed like for like and the facility has the materials.” How does the Fire

Protection contractor request additional materials if needed?

ANS: As discussed at the site visit, upon award of the contract, the contractor should inventory the materials already on site for the project. Prior to mobilization, Contractor should provide a written list of materials (preferably emailed to the Facility Manager) needed to complete the project. These materials should list specific items with sufficient information to be ordered by the FBOP (such as type of material, manufacturer’s part number, quantities, lengths, etc.). The period of performance will not begin until these materials arrive on site.

2. We were unable to locate the required NEW Fire Sprinkler heads for installation. These will need to be purchased. There is a head count in the DoR. 12” Dry Pendent heads are the most common.

ANS: No question is being asked above. FBOP will procure the needed dry pendent heads.

3. The Description of Requirements states; Contractor shall install approximately one-hundred ninety-four (194) 12”, 155°F QR dry pendent type sprinkler heads with 401 bell style, escutcheon rings in the freezers and coolers. The current NFPA standard requires Dry Pendent heads in freezers/coolers to be intermediate temperature heads. Intermediate temperature heads shall be less than 175°F (79°C) and not more than 225°F (107°C).

ANS: If the current code requires the intermediate temperature heads, the FBOP will procure that type of head to be installed by the contractor.

4. Can we get a scanned copy of the existing Fire Sprinkler system plan? f a plan is unavailable, what is the square footage and height of warehouse?

ANS: Existing fire plan for the building was provided and uploaded to the solicitation along with pictures from the site visit. Dimensions of the building are provided on the drawing.

5. The Description of Requirements states; Contractor shall create taps for approximately seventy

(70) new heads. What area is this for and how will Fire Protection contractor know what pipe size to use to install these NEW heads?

ANS: The requirement to create taps for approximately 70 new heads should be ignored and not included with anyone’s bid. That work was already completed under a previous project and was erroneously left in this scope of work.

6. The Description of Requirements states; working “off shift” hours. Can we have an employee(s) fabricate materials during the day and employee(s) install fabricated material at night?

ANS: Working multiple shifts is possible; however, contractor should not expect to work on

Saturdays, Sundays, nor Federal holidays.

7. Can we use facility toilets while on property?

ANS: No. Contractor should plan on providing a portable toilet to be used by their personnel.

8. The Description of Requirements states; Contractor shall ensure the new sprinkler system communicates with the designated fire suppression control panel to notify the attendant of activation. There is no work required at system risers.

ANS: There is no question asked in #8; therefore, we cannot provide an answer.