Q&A_Session.docx

DOCX document 13 KB Posted

Attached to
Abate Floor Tile and Mastic (EA common area) Federal contract opportunity
Solicitation number
15B2111900000001
Issued by
Department of Justice Bureau of Prisons Federal Correctional Institution Otisville

About this file

Q&A

View the file

Other files for this federal contract opportunity

Other files attached to Abate Floor Tile and Mastic (EA common area), newest first.
File Type Posted
SITE_VISIT.docx DOCX document
2018_11_20_11_17_19.pdf PDF
EA_abatement_Instructions_to_Offerors-signed.pdf PDF
NCIC_Form_BP_A0660.pdf PDF
IFB_Asbestos.pdf PDF
Abatement_Statement_of_Work.pdf PDF
Davis-Bacon.PDF PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

1. Is there a performance/payment bond if $30,000 or over?

a. Yes a payment bond or Irrevocable letter of credit will be required if the bid is $30,000 or greater.

2. Will the individual clearances be the short for or the long form?

a. The short form will be sufficient based upon the short time frame for this project.

3. Are you intending to start this project before Christmas?

a. Yes we intend to have this started and finished before the Christmas Holiday.

4. Are we required to go through tool count procedures in and out every day? If so would it be a typical 30 min in and out average?

a. Yes a tool inventory will have to be done daily in and out. The time needed for the inventory will depend upon your level of organization.

5. Aside from negative air machines will be required to mitigate the odor that will be emitted as well?

a. No the odor is expected

6. Is the tile and mastic on concrete or wood?

a. Concrete

7. Are we required to abate cove base mastic?

a. No

8. Are the tiles single layer or multiple layers?

a. Single Layer

9. What amount of tile and mastic is there?

a. Approximately 600 square feet

10. Do you want us to remove the baseboard rubber covering?

a. Yes and we do not need it replaced.

11. Will we be able to store our tools on site?

a. Tools must be removed daily from the unit, however a locked box truck may stay in the visitor parking area over night and may be driven behind the unit for access to the job site.

**Electricity and Water are in the area and provided by the Institution.

** There are three options for where the decontamination units can go, it will be up to the contractor to pick the most suitable place.