Pre-Quote Meeting Minutes and Sign In Sheet - 15B10626Q00000017 - Signed.pdf
PDF 436 KB Posted
- Solicitation number
- 15B10626Q00000017
About this file
Pre-Quote Conference Meeting Minutes Summary
These are the meeting minutes from a pre-quote conference held on June 23, 2026, for solicitation 15B10626Q00000017, a Federal Bureau of Prisons (FBOP) contract for interior repairs and flooring system work at FCC Butner facilities. The work involves repairs to LSCI, FCI-I, and FCI-II buildings. Quoters must submit SF 1442 forms with UEID numbers, complete commodity or services schedule pricing on page 6 using unit price (JB = job) format, and register in SAM with NAICS code 238330. All questions must be submitted in Word format to Ashley Harding (a1huffman@bop.gov) no later than June 30, 2026, by 3:00 p.m. EST. Quote submission deadline is July 8, 2026, by 4:00 p.m. EST via email to a1huffman@bop.gov; mail and hand-carried submissions will not be evaluated. Past performance submissions are optional and should be sent to the Contract Specialist.
Work will be performed within the secure perimeter between 7:00 a.m. and 3:00 p.m., Monday through Friday. The Contracting Officer's Representative is Mr. Nicholas Fuller (Engineering Tech). All required licensing and permits must be obtained by the awarded contractor. Contractors must provide their own protective gear, maintain a Safety Representative on-site, comply with OSHA requirements, and properly store chemicals with Safety Data Sheets. Strict tool accountability is required with daily inventories; tools cannot be stored overnight on-site. Personnel must bring valid photo identification daily and adhere to strict security protocols, including prohibition of contact with inmates, firearms, drugs, and inappropriate clothing colors (green or khaki). The institution will maintain photographic documentation; cellular phones with cameras are prohibited on-site.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-QUOTE CONFERENCE MEETING MINUTES
15B10626Q00000017 – BUT INTERIOR REPAIRS – FLOORING SYSTEM
FCC BUTNER - PROJECT 26Z1AS5
DATE: 9:00 A.M. EST, TUESDAY, JUNE 23, 2026
Place: FCC BUTNER – LSCI, FCI-I, AND FCI-II
CONTRACTING OFFICER (Ashley Harding):
I. INTRODUCTIONS:
Round table introduction of all attendees.
*Please see attached sign in sheet*
II. PURPOSE OF MEETING:
Purpose of this meeting is to familiarize the contractor with the unique circumstances and requirements surrounding a correctional setting. This meeting is also to explain the solicitation, as issued, and not to furnish additional information.
Nothing said here shall be interpreted as a change to the solicitation without the issuance of a formal amendment through the Contracting Officer, Ashley Harding.
III. MINUTES:
Advised minutes will be recorded and distributed via www.sam.gov.
IV. SITE VISIT INFORMATION:
Walk to selected sites for BUT Interior Repairs – Flooring System immediately following the meeting.
V. FRONT COVER PAGE FORMS AND INSTRUCTIONS:
Submit: SF 1442 shall be uploaded as a single PDF attachment, including your UEID number, and submitted to a1huffman@bop.gov.
Quotes submitted by mail or hand carried will not be evaluated. It is the responsibility of the quoter to confirm receipt of quotes by contacting Ashley Harding a1huffman@bop.gov. All quotes received after the exact time specified for receipt shall be treated as late submissions and will not be considered except under facts and circumstances allowed by the Federal Acquisition Regulation (FAR).
VI. TIME FRAMES AND LOCATION FOR SUBMISSION OF QUOTES:
The deadline for submission of quotes for this project is July 8th, 2026 by 4:00 p.m. EST.
VII. GENERAL TOPICS:
The following submission/completion items will be addressed:
1. From the solicitation, each quoter MUST complete and submit the following forms, clauses, and statements with his/her bid. Failure to do so may cause your quote to be considered as non-responsive:
• SF 1442: Submit the entire 1442 packet with your UEID and Business name on page 1 and 2 with your quote amount on page 6.
• PAST PERFORMANCE SUBMISSION: Any relevant past performance can be submitted with your quote to Ashley Harding, Contract Specialist at a1huffman@bop.gov.
• COMMODITY OR SERVICES SCHEDULE (PAGE 6): Complete the Unit Price (JB = job) and
Amount blocks (these amounts will be the same).
• REPRESENTATIONS AND CERTIFICATIONS: All contractors submitting a quote must be registered in the System for Award Management (SAM) at www.sam.gov with the North American Industry Classification Standard code (NAICS) 238330 which is applicable to this acquisition.
2. Other general items to be addressed:
• LICENSING AND PERMITS: All required licensing and permits are required to be obtained by the contractor who receives contract award.
• WORK HOURS: Work hours within the secure perimeter shall be between 7:00 am and 3:00 pm
Monday through Friday.
• COR: The contracting Officer’s Representative (COR) is Mr. Nicholas Fuller, Engineer Tech at FCC Butner.
• PERIOD OF PERFORMANCE: The start date will be set between the COR and the contractor upon award and notice to proceed.
• QUESTIONS: Oral questions asked at Site Visit of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation. All questions must be sent in WORD FORMAT to Ashley Harding, FCC Butner Contract Specialist, via email at a1huffman@bop.gov.
In order to provide sufficient response time prior to the quote due date, the Government has established that questions be submitted no later than Tuesday, June 30, 2026 by 3:00 p.m. EST.
• ACCESS TO SITE/PARKING OF VEHICLES: Only public parking will be available for contractor work vehicles.
• STORAGE OF MATERIALS: Storage of materials will be coordinated with the COR.
• CONTRACTOR TEMPORARY OFFICE: No temporary office space will be provided.
SAFETY MANAGER:
3. SAFETY POINTS:
• The contractor is responsible for providing required protective gear to all contractor workers, should it be required. Contractor will ensure that all workers have proper safety gear at all times.
• Contractor is responsible for the prevention of accidents on the project site and has spill kit onsite and containment procedures. OSHA requirements will be adhered to.
• The Contractor will have a Safety Representative on site at all times during the completion of this project.
• Proper storage of any chemicals in lay down yard with SDS present.
• The safety department can stop any project if unsafe acts occur.
CAPTAIN:
4. SECURITY
• ADVERSE WEATHER: Whenever adverse weather conditions or other institution emergency contingencies are in effect, contract workers will not be permitted passage into the secure institution. Should emergency conditions be implemented while contract workers are inside the secure perimeter, they will be required to secure their tools, remove vehicles and equipment, and leave the institution grounds until the emergency situation has been resolved.
• SECURITY CLEARANCES: Contract workers are subject to security investigative procedures.
Please refer to the contract for details.
• EMPLOYEE IDENTIFICATION: Contractor personnel working on project site must bring valid photo identification to the institution each day. The identification will be surrendered upon entry to and returned upon exit from institution property.
• TOOL ACCOUNTABILITY: Strict accountability and control of all contractor tools and hazardous materials must be maintained at all times. All contractor tools to be used inside the secure perimeter must be inventoried and accounted for at the conclusion of the work day Contractor tools may not be stored on-site overnight. The contractor should provide for enough time at the conclusion of the work day for the return and accounting of all tools issued during the work day. Lost or missing tools must be reported to the COR the Captain immediately.
• ILLEGAL ITEMS ON FEDERAL PROPERTY: Firearms, ammunition, knives, other weapons, drugs, narcotics, and alcoholic beverages are not permitted inside/outside the secure perimeter or anywhere else on Federal property at any time. This includes the private vehicles of contract workers. Violators will be subject to criminal prosecution. All persons, vehicles, and equipment are subject to search by institution authorities at any time.
• NO CONTACT WITH INMATES: Contract workers are not to have any contact with inmates at any time. No photographs may be taken of inmates.
• CONTRACTOR EMPLOYEE WORK DRESS: Green or khaki‐colored clothing is not allowed, as inmates wear these colors.
• PHOTOGRAPHS: The institution’s Facilities Department maintains a digital camera that will be utilized by FBOP staff to document the project work. The Contractor may request copies of these photos and may request that photos be taken for specific conditions. Cellular telephones equipped with photographic capabilities are prohibited on the project construction site.
VIII. ADDITIONAL NOTES:
Meeting minutes recorded by:
Ashley Harding, Contract Specialist FCC Butner
NOTICE:
MEETING MINUTES ARE PROVIDED FOR INFORMATIONAL PURPOSES ONLY. THEY ARE NOT
INTENDED TO CHANGE ANY SPECIFICATIONS, TERMS OR CONDITIONS OF THE
SOLICITATION. ANY AND ALL CHANGES TO THE SOLICITATION SHALL BE ISSUED IN
SUBSEQUENT AMENDMENTS ISSUED BY THE CONTRACTING OFFICER.
| 2026-06-23T14:02:39-0400 | |
| ASHLEY HARDING |
File details come from the government source that posted it. Updated .