This is a technical specifications and requirements document prepared by Broward County Water Management Division for the Canal Pump Station (S-45) Improvements project, a fixed-price contract for the installation of a new drainage pump station, concrete lining of canal, restoration of sod areas, and all ancillary work required for project completion. The project is located at the intersection of the South Florida Water Management District Hillsboro Canal and the Broward County Water Management Division C-4 Canal in Coconut Creek, Florida. The scope encompasses comprehensive infrastructure construction including demolition of existing structures, site clearing, earthwork, dewatering, installation of submersible propeller pumps, discharge piping systems, flap gates, concrete work, asphalt paving, pavement markings, chain-link fencing, topsoil placement, and sodding. The contract includes detailed technical specifications across multiple divisions covering general requirements, sitework, concrete, electrical systems, and specialized equipment. Work hours are specified as Monday through Thursday 7:00 a.m. to 6:00 p.m. for the City of Coconut Creek and Monday through Friday 7:30 a.m. to 5:00 p.m. for Broward County Water Management Division, with all paving work at Adios Golf Club access driveway scheduled between May 26 and June 10, July 20 and August 4, or September 8 and September 15, 2026, during confirmed golf course closure periods.
The contractor is responsible for all mobilization costs, permits, bonds, insurance, and compliance with applicable codes and standards from the Florida Department of Transportation, Broward County, and the City of Coconut Creek. Payment is structured as lump-sum items for bonds and insurance (capped at 3 percent of total bid), mobilization, maintenance of traffic, and pump station improvements, with initial mobilization payment of 40 percent upon completion of specified items and the remaining 60 percent in equal monthly installments during the original contractual substantial completion period. The project is partially funded by a Florida Department of Environmental Protection Grant (No. 22FRP128), and the contractor must submit detailed shop drawings, as-built drawings certified by a Florida-registered professional surveyor and mapper, construction schedules using Critical Path Method software, progress reports, quality control documentation, and operating and maintenance manuals. All work must comply with OSHA requirements, environmental protection standards including NPDES and SWPPP compliance, and comprehensive testing and inspection protocols, with the contractor bearing costs for failed tests and required corrections at no additional expense to the owner.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BROWARD COUNTY WATER MANAGEMENT DIVISION
CONTRACT DOCUMENTS FOR THE
CONSTRUCTION OF THE
BROWARD COUNTY CANAL PUMP STATION (S-45)
IMPROVEMENTS
BC WMD PROJECT NO. 107751
BID NO. PNC2131527C2
JANUARY 2026
BID SUBMITTAL
VOLUME 2
VOLUME 1: BIDDING AND CONTRACT REQUIREMENTS
VOLUME 2: TECHNICAL SPECIFICATIONS
VOLUME 3: DRAWINGS
412 S.E. 18TH STREET, FORT LAUDERDALE, FLORIDA 33316
TEL.: (954) 761-1073
JAMES F THOMPSON, PE
FLORIDA REG. NO. 54731
T&A-JLucco Jim Statement
TABLE OF CONTENTS
CANAL PUMP STATION (S-45) RESILIENCE IMPROVEMENTS
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
TOC-1
SECTION TITLE PAGES
DIVISION 1 - GENERAL REQUIREMENTS
01110 Summary of Work ................................................................... 01110-1 - 01110-7 01111 Technical Provisions ................................................................ 01111-1 - 01111-5 01112 Permits .................................................................................... 01112-1 - 01112-1 01290 Application for Payment .......................................................... 01290-1 - 01290-2 01291 Measurement and Payment .................................................... 01291-1 - 01291-3 01311 Project Meetings ..................................................................... 01311-1 - 01311-3 01312 Field Engineering ..................................................................... 01312-1 - 01312-2 01320 Project Record Documents ...................................................... 01320-1 - 01320-6 01321 Schedules and Reports ............................................................ 01321-1 - 01321-11 01323 Construction Photography ...................................................... 01323-1 - 01323-2 01324 Construction Videography ....................................................... 01324-1 - 01324-4 01330 Shop Drawings, Product Data and Samples ............................ 01330-1 - 01330-4 01351 Cutting and Patching ............................................................... 01351-1 - 01351-3 01352 Alteration Project Procedures ................................................. 01352-1 - 01352-3 01410 Regulatory Requirements and Permits ................................... 01410-1 - 01410-1 01420 Reference Standards ............................................................... 01420-1 - 01420-2 01421 Abbreviations of Institutions ................................................... 01421-1 - 01421-3 01450 Quality Control ........................................................................ 01450-1 - 01450-2 01451 Testing Laboratory Services .................................................... 01451-1 - 01451-3 01505 Mobilization ............................................................................. 01505-1 - 01505-1 01510 Temporary Utilities .................................................................. 01510-1 - 01510-3 01540 Construction Aids .................................................................... 01540-1 - 01540-2 01550 Site Access and Storage ........................................................... 01550-1 - 01550-4 01555 Traffic Regulations ................................................................... 01555-1 - 01555-4 01561 Protection of Existing Facilities ............................................... 01561-1 - 01561-5 01570 Temporary Controls................................................................. 01570-1 - 01570-3 01580 Project Identification and Signs ............................................... 01580-1 - 01580-2 01610 Materials and Equipment ........................................................ 01610-1 - 01610-5 01740 Cleaning ................................................................................... 01740-1 - 01740-2 01750 Equipment Testing Startup ...................................................... 01750-1 - 01750-1 01770 Contract Closeout .................................................................... 01770-1 - 01770-3 01780 Guarantees and Bonds ............................................................ 01780-1 - 01780-2 01830 Operating and Maintenance Data ........................................... 01830-1 - 01830-5
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
TOC-2
SECTION TITLE PAGES
DIVISION 2 - SITEWORK
02210 Subsurface Investigation ......................................................... 02210-1 - 02210-1 02221 Demolition ............................................................................... 02221-1 - 02221-4 02230 Site Clearing ............................................................................. 02230-1 - 02230-4 02240 Dewatering .............................................................................. 02240-1 - 02240-3 02300 Earthwork ................................................................................ 02300-1 - 02300-21 02305 Excavation and Backfilling for Utilities .................................... 02305-1 - 02305-5 02310 Site Grading ............................................................................. 02310-1 - 02310-3 02370 Erosion Control and Slope Protection ..................................... 02370-1 - 02370-4 02501 Piping, General ........................................................................ 02501-1 - 02501-7 02502 Ductile Iron Pipe ...................................................................... 02502-1 - 02502-5 02505 Corrugated Metal Pipe ............................................................ 02505-1 - 02505-3 02511 Pump Station Discharge Piping System ................................... 02511-1 - 02511-3 02542 Flap Gate ................................................................................. 02542-1 - 02542-2 02632 Submersible Propeller Pump Station ...................................... 02632-1 - 02632-7 02635 Subterranean Structures For Pump Station ............................ 02635-1 - 02635-2 02741 Asphaltic Concrete Paving - General ....................................... 02741-1 - 02741-12 02761 Pavement Marking .................................................................. 02761-1 - 02761-2 02821 Chain Link Fence and Gate ...................................................... 02821-1 - 02821-5 02919 Topsoil ..................................................................................... 02919-1 - 02919-2 02922 Sodding .................................................................................... 02922-1 - 02922-6
DIVISION 3 – CONCRETE
03050 Concrete .................................................................................. 03050-1 - 03050-4 03100 Concrete Formwork ................................................................. 03100-1 - 03100-4 03200 Concrete Reinforcement ......................................................... 03200-1 - 03200-3 03290 Joints in Concrete .................................................................... 03290-1 - 03290-9 03300 Cast-in-Place Concrete ............................................................ 03300-1 - 03300-9 03315 Grout ....................................................................................... 03315-1 - 03315-4 03350 Concrete Finishes .................................................................... 03350-1 - 03350-4 03390 Concrete Curing ....................................................................... 03390-1 - 03390-2
DIVISION 4 - MASONRY
04100 Mortar ..................................................................................... 04100-1 - 04100-2
DIVISION 5 - METALS
05010 Metal Materials ....................................................................... 05010-1 - 05010-3 05050 Metal Fastening ....................................................................... 05050-1 - 05050-6 05500 Metal Fabrications ................................................................... 05500-1 - 05500-3 05531 Grating, Floor Plates and Access Hatches ............................... 05531-1 - 05531-4
DIVISION 11 - EQUIPMENT
11000 Equipment General Provisions ................................................ 11000-1 - 11000-13 11190 Pumps, General ....................................................................... 11190-1 - 11190-8 11234 Submersible Pumps ................................................................. 11234-1 - 11234-3
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
TOC-3
DIVISION 13 - SPECIAL CONSTRUCTION
13100 Data Flow RTU ......................................................................... 13100-1 - 13100-6
DIVISION 16 – ELECTRICAL
16015 Electrical Systems Analyses ..................................................... 16015-1 - 16015-6 16050 Electrical General Provisions ................................................... 16050-1 - 16050-4 16110 Raceways ................................................................................. 16110-1 - 16110-3 16120 Wires and Cables ..................................................................... 16120-1 - 16120-2 16452 Grounding ................................................................................ 16452-1 - 16452-1 16810 Control Panels ......................................................................... 16810-1 - 16810-7 16950 Miscellaneous Equipment and ATS ......................................... 16950-1 - 16950-3
EXHIBITS
Exhibit A Public Relations Requirements Exhibit B Permits Exhibit C Geotechnical Report
SECTION 01110
SUMMARY OF WORK
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-1
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. All applicable provisions of the BCF No. 170 Contract Requirements, and Division 1 - General Requirements shall govern the WORK under this section.
B. This Project is partially funded by the Florida Department of Environmental Protection (FDEP) Grant No. 22FRP128. The grant documents are incorporated by reference as part of the contract documents as Exhibit 1 of the BFC No. 170.
1.02 SCOPE
A. The WORK to be performed under this Contract shall consist of furnishing and installing all tools, equipment, materials, supplies, and manufactured articles and furnishing all labor, transportation, and services, including fuel, power, water, and essential communications, and performing all WORK, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The WORK shall be complete, and all WORK, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the WORK in good faith shall be provided by the CONTRACTOR as though originally so indicated, at no increase in cost to the
OWNER.
1.03 WORK COVERED BY CONTRACT DOCUMENTS
A. The WORK of this Contract comprises the construction of the infrastructure site WORK for the Broward County Water Management Division. The WORK will include but not be limited to the installation of a new drainage pump station, concrete lining of canal, restoration of sod areas, all ancillary work required to complete the project satisfactorily to the OWNER.
B. The general location of this Project is as follows:
1. The project boundary is located in the intersection of the South Florida Water Management District Hillsboro Canal and the Broward County Water Management Division C-4 Canal, as shown on the plans. The work area is within the City of Coconut Creek, Florida. Broward County Water Management Division will own and operate the pump station.
1.04 NOTICE TO BIDDERS
A. The successful bidder will, at the time of the pre-work conference, be required to show that each subcontractor is in compliance with Chapter 9 of the Broward County Code of Ordinances.
1.05 STANDARD SPECIFICATION
A. Except as noted, all materials and quality of work shall meet the requirements of the latest editions of the following publications:
1. Florida Department of Transportation Standard Specifications for Road and Bridge Construction, and its supplements (latest revision).
2. The Florida Department of Transportation "Roadway and Traffic Design Standards" (latest revision).
3. The Florida Department of Transportation "Structures Standards" (latest revision).
4. Broward County Water and Wastewater Services/Water and Wastewater Engineering
Division "Minimum Design and Construction Standards" (latest revision).
5. Minimum Standards Applicable to Public Right-of-Way under Broward County Jurisdiction.
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-2
6. City of Coconut Creek Engineering Department Standards, latest revision.
7. City of Coconut Creek Building Department Requirements.
8. Any other construction standards of the Authorities Having Jurisdiction over the construction area.
1.06 SITE INVESTIGATION
A. The CONTRACTOR, by virtue of signing the Contract, acknowledges that the CONTRACTOR and all subcontractors have satisfied themselves to the nature and location of the WORK, the general and local conditions including, but not restricted to: those bearing upon transportation; disposal, handling and storage of materials; access roads to the site; the conformation and conditions of the WORK area; and the character of equipment and facilities needed preliminary to and during the performance of the WORK. Failure on the part of the CONTRACTOR to completely or properly evaluate the site conditions shall not be grounds for additional compensation.
B. Soil boring information may be furnished to the CONTRACTOR for general information. Such data is not warranted to be correct; the CONTRACTOR, by virtue of signing the Contract, acknowledges that the CONTRACTOR and all subcontractors have satisfied themselves as to the nature and extent of soil and (underground) water conditions on the project site. Unless approved in writing by the ENGINEER, no additional payment will be made to the CONTRACTOR because of differences between actual conditions and those shown by the boring logs.
1.07 WORK BY OTHERS
A. Concurrent WORK by other contractors. The CONTRACTOR's attention is directed to the fact that WORK may be conducted at the site by other contractors during the performance of the WORK under this Contract. The CONTRACTOR shall conduct its operations so as to cause little or no delay to WORK of such other contractors, and shall cooperate fully with such contractors to provide continued safe access to their respective portions of the site, as required to perform WORK under their respective contracts.
B. Interference with WORK on Utilities. The CONTRACTOR shall cooperate fully with all utility forces of the OWNER or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities which interfere with the progress of the WORK, and shall schedule the as to minimize interference with said relocation, altering, or other rearranging of facilities.
1.08 WORK SEQUENCE
A. The CONTRACTOR shall schedule and perform the WORK in such a manner as to result in the least possible disruption to the public's use of roadways, driveways, and utilities. Utilities shall include but not be limited to water, sewerage, drainage structures, gas, electric, television and telephone.
Prior to commencing with the WORK, CONTRACTOR shall perform a location investigation of existing underground utilities and facilities in accordance with Section 01561 entitled "Protection of Existing Facilities" and shall have obtained all required permits and permissions, CONTRACTOR shall also deliver written notice to Broward County Water Management District Customer Service Section, City, ENGINEER, and property occupants (private and public) of all planned disruption to roadway, driveways, and utilities 72 hours in advance of disruption.
B. Because other projects will be connected to portions of WORK constructed as part of this project, it may be necessary to sequence portions of this project. CONTRACTOR shall be responsible to coordinate construction activities with CONTRACTOR of adjacent phases and sections.
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-3
C. CONTRACTOR shall sequence the WORK so as to minimize impact on residents. CONTRACTOR shall notify The City of Coconut Creek, the Golf Course, Broward County Schools, Post Office, residents, Broward County Traffic Engineering, Emergency Service providers, etc. 14 days prior to disruption of roadway.
1.09 WORK SCHEDULE
A. Time is of the essence in completing this project. Because time is of the essence the CONTRACTOR shall commit the necessary resources to this project to complete it in a timely manner. Those resources may include multiple working crews, working overtime, etc. Because time is of the essence the CONTRACTOR's construction progress will be monitored closely on a weekly basis.
The Construction progress will be measured with the construction schedule submitted by the CONTRACTOR. If the ENGINEER determines that the CONTRACTOR does not meet the Critical Path Method (CPM) as specified in Section 01321 entitled " Schedules and Reports", the CONTRACTOR will be required to commit those resources necessary to ensure the completion of the project in a timely manner including working overtime, adding other WORK crews, etc. All costs incurred to implement measure to complete the WORK in timely manner will be borne by the CONTRACTOR at no additional cost to the OWNER.
B. Schedule:
1. CONTRACTOR shall submit scheduling information for the WORK as required in Section 01321 entitled "Schedules and Reports".
2. No separate payment shall be made for preparation and/or revision of the schedule.
C. Local Jurisdiction Requirements:
1. City of Coconut Creek work hours – Monday to Thursday 7:00 am to 6:00 pm, no County Holidays.
2. Broward County Water Management Division work hours – Monday to Friday 7:30 am to 5:00 pm
1.10 COMPUTATION OF CONTRACT TIME
A. It is the CONTRACTOR's responsibility to provide clear and convincing documentation to the ENGINEER as to the effect additional WORK will have with respect to additional contract time extension that may be justified. If additional quantities of WORK can be carried out concurrent with other existing construction activities without disrupting the critical path of the project then no contract time extension will be granted. CONTRACTOR is obligated to provide documentation to the ENGINEER if additional elements of WORK affect the critical path of the project. If WORK set forth in the original scope of the project is deleted, the contract time may be reduced. This contract is a calendar day contract. While the CONTRACTOR may be granted time to suspend WORK operations for vacations or holidays, contract time will not be suspended. During suspensions CONTRACTOR shall be responsible for all maintenance of traffic and liability without additional compensation from the OWNER.
1.11 CONTRACTOR USE OF PREMISES
A. The CONTRACTOR's use of the project site shall be limited to its construction operations. Storage of materials will be arranged for by the CONTRACTOR and a copy of an agreement for use of other property shall be furnished to the ENGINEER. All Storage yard agreements need to be approved by the OWNER. The agreements need to be specific about the intended use (i.e. materials stored or stockpiled, trailers, offices, storage units, equipment, etc.). No storage of fuel tanks, oil tanks, BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-4 or any other hazardous material will be permitted.
PRE-CONSTRUCTION CONFERENCE
A. After the award of Contract a Pre-construction WORK Conference will be held between the CONTRACTOR, the ENGINEER, the OWNER, other interested Agencies, representatives of Utility Companies and others affected by the WORK. The time and place of this conference will be set by the ENGINEER. The CONTRACTOR shall bring to the conference a copy of the proposed WORK schedule for the approval by the ENGINEER of the proposed methods and manner of executing the WORK including sequences of operation and time schedule. The WORK shall be performed in accordance with such schedule or approved amendments thereto.
1.12 UTILITY LOCATIONS
A. As far as possible, all existing utility lines in the project area have been shown on the plans.
However, Broward County does not guarantee that all lines are shown, or that said lines are in their true location. It shall be the CONTRACTOR's responsibility to identify and locate all underground or overhead utility lines or equipment affected by the project. No additional payment will be made to the CONTRACTOR because of discrepancies in actual and plan location of utilities and damages suffered as a result thereof.
B. The CONTRACTOR shall notify each utility company involved at least thirty (30) days prior to the start of construction to arrange for positive underground location, relocation or support of its utility where that utility may be in conflict with or endangered by the proposed construction.
Relocation of water mains or other utilities for the convenience of the CONTRACTOR shall be paid for by the CONTRACTOR. All charges by utility companies for temporary support of its utilities shall be paid for by the CONTRACTOR. All costs of permanent utility relocations to avoid conflict shall be the responsibility of the CONTRACTOR and the utility company involved.
C. The CONTRACTOR shall schedule and coordinate the WORK in such a manner that it is not delayed by the utility companies relocating or supporting their utilities. No compensation will be paid to the CONTRACTOR for any loss of time or delay.
D. All overhead, surface or underground structures and/or utilities encountered are to be carefully protected from damage or displacement. All damage to said structures and/or utilities is to be completely repaired within a reasonable time; needless delay will not be tolerated. The OWNER reserves the right to remedy any damage by ordering outside parties to make repairs at the expense of the CONTRACTOR. All repairs made by the CONTRACTOR are to be made to the satisfaction of the utility owner and shall be inspected by a representative of the utility owner and the ENGINEER.
E. The CONTRACTOR should be aware of the Sunshine State One Call Center, which has a free locating service for contractors and excavators:
1. Within forty-eight hours before excavating, dial toll free 1-800-432-4770, and a locator will be dispatched to the WORK location. CONTRACTOR shall reasonably notify other utility companies not notified by Sunshine State One Call Center.
F. In the event that during the course of the WORK CONTRACTOR encounters subsurface or concealed conditions or unknown physical conditions of an unusual nature at the Project site which differ materially from those shown on the Contract Documents, which are not marked in the field by locating services or Utility Department, and which differ from those ordinarily encountered and generally recognized as inherent in WORK of the character called for in the
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-5
Contract Documents, CONTRACTOR, without disturbing the conditions and before performing any WORK affected by such conditions, shall, within twenty-four (24) hours of their discovery, notify OWNER and ENGINEER in writing of the existence of the aforesaid conditions. ENGINEER and OWNER shall, within two (2) business days after receipt of CONTRACTOR’s written notice, investigate the site conditions identified by CONTRACTOR. Should ENGINEER determine that the conditions of the Project site are not so materially different to justify a change in the terms of the Contract, ENGINEER shall so notify OWNER and CONTRACTOR in writing, stating the reasons, and such determination shall be final and binding upon the parties hereto.
G. No request by CONTRACTOR for a change to the Contract Price or Time under this provision shall be allowed if the CONTRACTOR has not given written notice in strict accordance with these provisions, or if it is made after the date certified by the ENGINEER as the date of Substantial Completion.
1.13 LINE AND GRADE
A. The ENGINEER has provided vertical and horizontal control for layout of the WORK in the form of benchmarks and reference points located adjacent to the WORK. From these controls provided, the CONTRACTOR shall develop and make all detailed surveys needed for construction and shall establish all working points, lines and elevations necessary to perform the WORK. This surveying WORK shall be supervised by a Professional Surveyor and Mapper registered in the State of Florida. The CONTRACTOR shall not rely on any electronic files from the ENGINEER for any layout.
1.14 PROTECTION AND RESTORATION OF SURVEY MONUMENTS
A. The CONTRACTOR shall carefully protect from disturbance all survey monuments, stakes and benchmarks, whether or not established by the CONTRACTOR, and shall not remove or destroy any surveying point until it has been properly witnessed by the ENGINEER. All major survey monuments that have been damaged by the CONTRACTOR such as section corners, 1/4 section corners, property corners or block control points shall be replaced at the CONTRACTOR's expense with markers of a size and type approved by the ENGINEER. The replacement shall be under the supervision of a Florida Registered Professional Surveyor and Mapper where directed by the ENGINEER. The CONTRACTOR shall document survey movements prior to construction and shall submit the location and type of all markers to the ENGINEER in writing.
1.15 EQUIPMENT
A. All equipment necessary and required for the proper construction of all facilities shall be in first-class working condition.
1.16 STORAGE SITES
A. The CONTRACTOR shall furnish, without any cost to the OWNER, properly zoned areas suitable for field office and material storage including but not limited to; earthen spoil suitable for fill and/or backfill and equipment service and storage. No material may be stored in the public right of way without prior authorization by the agency having jurisdiction. The CONTRACTOR shall keep these areas in a clean and orderly condition so as not to cause a nuisance or sight obstruction to motorists or pedestrians. Storage sites shall be fenced for public safety (minimum 6 foot chain link fence and locked gates).
1.17 OWNERSHIP OF EXISTING MATERIALS
A. All materials removed or excavated from the job site shall remain the property of Broward County until released by the Contract Administrator, at which time it shall become the property of the
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-6
CONTRACTOR, who shall dispose of it in a manner satisfactory to the ENGINEER. Where directed by the ENGINEER, the CONTRACTOR shall remove existing fences, trees, shrubs, etc. and places them on adjacent private property for future use by others.
1.18 EXCESS MATERIAL
A. Upon direction of the ENGINEER all vegetation, debris, concrete or other unsuitable materials shall be disposed of in areas provided by the CONTRACTOR and approved by the ENGINEER. Any excess material desired to be retained by the OWNER shall be delivered by the CONTRACTOR to a designated area within a 5-mile radius of the project, at no extra cost to the OWNER.
1.19 ADJUSTING EXISTING VALVES, METERS, CATCH BASINS, MAINTENANCE ACCESS STRUCTURES
A. It shall be the CONTRACTOR's responsibility to coordinate and have all adjustments made to existing water meters, valves, and structures encountered during construction, in order to meet all final grades, unless otherwise instructed by the ENGINEER or the respective utility owner. All valves and maintenance access structures shall be accessible during all phases of the WORK for emergency access. Omission of such structures from the Contract Plans does not relieve the CONTRACTOR from making such adjustments as may be deemed necessary. The CONTRACTOR shall take this provision into account when personally investigating the site. No additional payment shall be made for these adjustments.
1.20 CONFLICT STRUCTURES
A. The CONTRACTOR shall abide by the following criteria concerning conflicts between new drainage, water, or sewer construction and existing utilities.
1. The CONTRACTOR shall verify the location of all utilities suspected of being potential conflicts prior to ordering drainage or sewer structures for these locations and inform the ENGINEER as to the findings.
2. The ENGINEER shall have full authority to direct the placement of conflict structures, the relocation of structures shown in the plans, and the addition, deletion, or relocation of any pipe shown in the plans in order to facilitate construction, expedite completion and avoid conflicts with existing utilities.
3. Where an existing utility is to pass through a conflict structure, the CONTRACTOR shall protect the utility from damage by whatever means the utility owner and the ENGINEER deem necessary.
4. In no case shall there be less than 0.5 feet between any two (2) pipe lines within the structure or less than 2 feet of clearance between pipe lines and the structure.
1.21 ENVIRONMENTAL PROTECTION
A. The CONTRACTOR shall furnish all labor and equipment and perform all WORK required for the prevention of environmental pollution during and as a result of the WORK under this contract.
The CONTRACTOR shall be responsible for preparing and complying with the requirements of the National Pollution Prevention Discharge Elimination System (NPDES) and Storm Water Pollution Prevention Plan (SWPPP), including preparation and submittal of the Notice of Intent (NOI) prior to start of construction. For the purpose of this contract environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life, affect other species of importance to man, or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution requires consideration of air, water, land and involves noise, solid waste management and management of radiant energy and
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01110-7 radioactive materials, as well as other pollutants.
B. The CONTRACTOR shall take all steps necessary to protect water quality in the connected waters around the project and shall utilize such additional measures as directed by the ENGINEER. Silt screens, hay bales, turbidity curtains, or other control measures adjacent to outfall construction shall not be removed until the turbidity of the affected waters is equal to or lower than the ambient turbidity of undisturbed segments of adjacent surface waters.
1.22 BASIS OF PAYMENT
A. The CONTRACTOR's Professional Surveyor and Mapper will measure all "As-built" quantities for payment. In the event of disputes as to quantity, the ENGINEER shall make the final determination; no additional compensation will be made for surveying services. This WORK shall be supervised by a Florida Licensed Registered Professional Surveyor and Mapper.
B. The CONTRACTOR shall not be permitted to invoice for quantities of WORK beyond those contained in the contract and all previously approved change orders. Invoice for partial payment shall not be accepted by ENGINEER as complete without the following.
1. Certificate of payment to subcontractors.
2. County Business Enterprise (CBE) Program Performance Report.
3. Updated Construction Schedule.
4. "As-built" DRAWINGS for the WORK being invoiced.
1.23 APPLICATION FOR PAYMENT FOR STORED MATERIALS
A. Application for payment for stored materials may not be made by the CONTRACTOR.
1.24 VIBRATORY COMPACTION
A. The use of vibratory compaction equipment shall be limited to a total gross weight of three (3) tons. The use of vibratory equipment shall be limited to compacting backfill of utility trenches and subgrade of roadways only. If approved in writing by the ENGINEER, larger vibratory compaction equipment may be allowed if operated in a static mode only.
1.25 REPORTING OF DAMAGE CLAIMS
A. The CONTRACTOR shall comply with the reporting requirements specified in the Contract Documents.
1.26 PROJECT AND COMMUNITY COORDINATION
A. The CONTRACTOR shall comply with the Public Relations Requirements. Notices to property owners are the specific responsibility of the CONTRACTOR and are delineated further in the Public Relations Requirements section of this contract, Exhibit “A”.
1.27 PROJECT JURISDICTION
A. The work area includes the Rights of Way of the City of Coconut Creek, Broward County, and South Florida Water Management District. The CONTRACTOR shall comply with the requirements of the corresponding Authority having jurisdiction.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01110
SECTION 01111
TECHNICAL PROVISIONS
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01111-1
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. All applicable provisions of the BCF No. 170 Contract Requirements, and Division 1 - General Requirements shall govern the WORK under this section.
1.02 SCOPE
A. WORK under this contract includes furnishing materials, labor, tools, equipment, supervision, and incidentals necessary to construct infrastructure improvements.
1.03 GENERAL
A. The provisions of this Section shall amplify either the "GENERAL CONDITIONS", Standard Form Construction Contract Documents, (BCF No. 170) or the general requirements of the Broward County Construction Standards and its latest version including updates through the bid date of this project, in specific instances and shall have full force and effect as if contained in those documents.
B. TECHNICAL SPECIFICATIONS consist of this section, Section 01111, described as TECHNICAL PROVISIONS, Volume II of the Contract Documents, the Broward County Construction Standards, latest revision, and the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest revision.
C. In case of a conflict between the Broward County Construction Standards and the project DRAWINGS, these TECHNICAL PROVISIONS AND GENERAL CONDITIONS OF BCF No. 170, GENERAL CONDITIONS shall govern.
D. The BCWWS/WWED "Minimum Design and Construction Standards" are not attached to the TECHNICAL SPECIFICATIONS but can be obtained at www.broward.org/waterservices.
E. Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest revision are not attached to the TECHNICAL SPECIFICATIONS but can be obtained at www.fdot.gov.
F. Work within the City of Coconut Creek, Broward County, and South Florida Water Management District Rights of Way shall conform to the Respective Standards of Construction.
1.04 ITEMS SPECIFIED ON DRAWINGS
A. Items of material, equipment, machinery, and the like may be specified on the DRAWINGS and not in the Technical Specifications. Such items shall be provided by the CONTRACTOR in accordance with the General Notes on the DRAWINGS.
1.05 FIELD LAYOUT OF THE WORK AND RECORD DRAWINGS
A. See GENERAL CONDITIONS, Article 46, BCF No. 170.
B. On completion of construction the CONTRACTOR shall provide two sets of Record DRAWINGS and one set of AutoCAD release 2018 format with all the As-Built information; all locations, dimensions and elevations of the constructed facilities, certified, signed and sealed thereon by a Professional Surveyor and Mapper registered in the State of Florida. All elevations shall refer to NAVD 1988 (North American Vertical Datum 1988) and all horizontal locations still refer to NAD '83 with '90 adjustment. The cost of such field layout and recording WORK shall be the responsibility of the CONTRACTOR. The as-built utility information shall meet Broward County’s standards.
C. All property block corners damaged or destroyed during construction shall be replaced by the http://www.broward.org/waterservices http://www.fdot.gov/
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01111-2
CONTRACTOR. CONTRACTOR shall submit a drawing to the ENGINEER showing all block corners signed and sealed by a Professional Surveyor and Mapper registered in the State of Florida.
1.06 SALVAGE
A. Any existing equipment or material, including but not limited to valves, pipes, fittings, couplings, etc., which is removed as a result of construction under this project may be designated as salvage by the CONTRACT ADMINISTRATOR, and if so, shall be delivered clean to the OWNER at a location directed by the CONTRACT ADMINISTRATOR. Any equipment or material not worthy of salvaging shall be disposed of by the CONTRACTOR at a suitable location in accordance with all applicable regulations, ordinances, and laws at no additional cost to the OWNER.
1.07 POWER
A. The CONTRACTOR shall furnish and pay for all electrical power required for the construction, testing and trial operation, prior to final acceptance by the OWNER.
1.08 WATER SUPPLY
A. All water required for testing, flushing and construction shall be furnished and paid for by the CONTRACTOR. The OWNER will provide a water meter for use of the CONTRACTOR. The CONTRACTOR shall make all arrangements and incur all expense involved in installing the necessary water meters. The quantity of water used shall be determined by reading the meter at the start and at the finish of construction. Each water service line shall be provided with a vacuum relief or backflow preventer which shall meet the requirements of ASA A40.6, latest revision, and the local jurisdictional authority and water system owner.
1.09 MAINTENANCE
A. The CONTRACTOR shall fully cooperate at all times with the OWNER in order to maintain the operation of the existing water and/or sewer system with the least amount of interference and interruption possible. The schedule, plans, and WORK of the CONTRACTOR shall at all times be subject to alteration and revision if necessary for public health and safety considerations. The creation of a public nuisance will not be permitted.
B. It may be necessary to interrupt the operation of the existing water and/or sewer system. In all cases where the CONTRACTOR must cause an interruption, the CONTRACTOR shall prepare and submit to the ENGINEER five (5) working days prior to commencing the WORK, a complete description of the proposed procedure and a guaranteed time schedule. At least twenty-four (24) hours prior to the time proposed for starting the WORK, the CONTRACTOR will be notified by the ENGINEER whether or not the WORK will be permitted as proposed.
1. The ENGINEER reserves the right to require the CONTRACTOR to WORK 24 hours per day in all cases where interference with operation of the system may result in dangerous health hazards or offensive conditions.
2. In no case will the CONTRACTOR be permitted to interfere with the existing system until all materials, supplies, equipment, tools, and incidentals necessary to complete the WORK are on the site. Backup equipment on key equipment items shall be required on WORK necessitating interference with the existing system.
1.10 SITE RESTORATION
A. The CONTRACTOR shall remove all excess material and shall clean up and restore the site to its original condition or better. All damage, as a result of WORK under this Contract, done to existing
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01111-3 structures, pavement, driveways, paved areas, curbs and gutters, sidewalks, shrubbery, grass, trees, fences, walls, utility poles, utility pipe lines, conduits, drains, catch basins, flagstones, rocked graveled or stabilized areas or driveways, and including all obstructions not specifically named herein, shall be repaired, or replaced, as determined by the ENGINEER. Site restoration shall be done in a timely manner as the WORK progresses. Site restoration WORK shall be completed on private property within 30 days after being disturbed. See GENERAL CONDITIONS, Article 50, "Cleaning Up; County’s Right to Clean Up", BCF No. 170.
1.11 SANITARY FACILITIES
A. The CONTRACTOR shall provide temporary facilities at the site as directed by the ENGINEER.
1.12 STANDARDS
A. Wherever in these TECHNICAL SPECIFICATIONS or in the DRAWINGS certain standards or regulations are referred to by name and/or number, the applicable publication shall be the latest revision thereof. Reference by abbreviation is made in accordance with the Section 01421 entitled "Abbreviations of Institutions."
1.13 QUALITY OF ITEMS
A. All material furnished for this project shall be new and unused. Any material which has become excessively weathered or damaged since manufacture shall not be considered as new. ENGINEER shall be the sole judge as to what constitutes excessive weathering or damage. See GENERAL CONDITIONS, Article 24, "Warranty", BCF No. 170.
1.14 TESTING
A. The Broward County Construction Standards latest revision may require during shop drawing review, that materials and supplied equipment meet given standards and testing to demonstrate conformance to the standards as a part of those standards. The cost of these tests shall be the obligation of the CONTRACTOR and no extra charge shall be made to the OWNER on account of such testing.
B. The OWNER will select a recognized, independent testing laboratory to make tests on concrete, reinforcing steel, soils, and other materials for the construction phase which the OWNER may decide to test for conformity with the TECHNICAL SPECIFICATIONS. The CONTRACTOR shall supply the necessary samples for this testing without cost to the OWNER. The costs for actual testing shall be paid by the OWNER except for tests which fail to meet the minimum specified tolerances set forth in the DRAWINGS and the TECHNICAL SPECIFICATIONS. The cost of the tests that fail will be charged to the CONTRACTOR by deducting the cost from the Contract price or will be paid directly to the testing laboratory by the CONTRACTOR.
C. Construction in areas where installation and restoration must satisfy the additional requirements of a local, state, or federal authority may require testing to demonstrate conformance. The CONTRACTOR shall ascertain the extent of testing required by regulatory agencies within these areas. The CONTRACTOR is responsible for performing such tests, including but not limited to, tests of compaction, and all costs for these tests shall be the obligation of the CONTRACTOR and no extra charge shall be made to the OWNER on account of such testing.
D. See GENERAL CONDITIONS, Article 35, Payment by County for Tests, BCF No. 170.
1.15 UTILITY CROSSINGS
A. It is intended that wherever existing utilities must be crossed that the pipe may be deflected up to
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01111-4
50 percent of the manufacturer's recommended limits and adequate cover shall be used to adequately clear the obstruction. However, when in the opinion of the ENGINEER, this procedure is not feasible the ENGINEER may direct the use of fittings to clear a utility crossing as detailed on the DRAWINGS. The cost of such crossing including joint restraints shall be on the basis of the schedule of pay items applied.
B. Deflections and adjustments of the proposed water and/or sewer mains to avoid all other existing utilities shall be verified/determined in the field during construction.
1.16 BASIS OF MEASUREMENT
A. Where mains are to be paid for on a unit price per linear foot basis, the number of linear feet will be determined by measurement along the centerline of the pipe in place, including fittings and valves.
B. Where items are to be paid for on a unit price per square yard basis, the number of square yards will be determined by measurement the actual square yards installed.
1.17 ADJUSTMENT AND RELOCATION OF EXISTING LINES
A. It is intended that wherever the DRAWINGS indicate that existing lines must be deflected, the pipe shall be deflected up to 50 percent of the manufacturer's recommended limits and the CONTRACTOR will be so directed by the ENGINEER. If the ENGINEER determines that the use of new pipe and fittings is required for deflection, the CONTRACTOR will be directed to use this method. The price for either method shall be based upon the unit prices bid. This does not apply to connections to existing system (paragraph 1.17, this section).
1.18 CONNECTION TO EXISTING SYSTEM
A. The CONTRACTOR shall perform all WORK necessary to locate, excavate and prepare for connection to the existing mains as shown on the DRAWINGS. The cost of this WORK and for the actual connection to the existing main shall be based upon the unit prices for installing the pipe and appurtenances and shall not result in any additional cost to the OWNER. The cost of ductile iron sleeves shall be included in the fitting’s unit price.
B. During all phases of the WORK, (i.e. installation, testing and restoration), the CONTRACTOR shall ensure at all times the safe operation of the existing water and/or sewage systems. Service to the customers shall be maintained with the least amount of interference and interruption as possible.
1.19 RELOCATIONS
A. The CONTRACTOR shall be responsible for the relocation of structures that are shown on the DRAWINGS, including, but not limited to, light poles, signs, fences, piping, conduits and drains that interfere with the proposed positioning of the water/sewer mains. The cost of all such relocations shall be included in the prices bid for the appropriate items. Such relocations shall be identified in advance of construction. CONTRACTOR shall coordinate all relocations with the appropriate utility.
1.20 UTILITIES
A. Existing utilities are shown on the DRAWINGS insofar as information is reasonably available;
however, it will be the responsibility of the CONTRACTOR to preserve all existing utilities whether shown on the DRAWINGS or not. If utility conflicts are encountered by the CONTRACTOR during construction, the CONTRACTOR shall give sufficient notice to their owners so that they may make the necessary adjustments. Damage to any utility, which in the opinion of the OWNER is caused by carelessness on the part of the CONTRACTOR shall be repaired at the expense of the
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01111-5
CONTRACTOR. See GENERAL CONDITIONS, Article 33, "Location and Damage to Existing Facilities, Equipment or Utilities", BCF No. 170.
1.21 GUARANTEE
A. The CONTRACTOR shall guarantee the equipment, material and labor performed under the Contract against any and all failures in proper use and operation for a period of one (1) year from date of written acceptance by the OWNER.
B. The CONTRACTOR shall also obtain warranties from manufacturers for each piece of equipment furnished so that the manufacturer's warranty fully covers the equipment for a period of one (1) year from the date of written acceptance by the OWNER.
C. See GENERAL CONDITIONS, Article 26, “Defective Work”, BCF No. 170.FRM.
1.22 PERFORMANCE OF WORK
A. The CONTRACTOR shall provide all labor and equipment required to complete all WORK specified herein and on the DRAWINGS. In an emergency situation, if the OWNER determines that it must provide workers and/or equipment to assist the CONTRACTOR in the satisfactory performance of the Contract terms and conditions, the OWNER shall be reimbursed by the CONTRACTOR at the applicable prevailing wage rates as specified in County Ordinance No. 83-72.
B. CONTRACTOR shall provide 48-hour advance notice to the OWNER for approval to WORK overtime on weekdays or to WORK on the weekends.
C. See GENERAL CONDITIONS, Article 8, “Labor and Materials”, BCF No. 170.
1.23 BARRICADING (SAFETY)
A. The CONTRACTOR shall be responsible for the furnishing and maintaining of all required drum barricades, or as required by the City and Broward County, to ensure the public's safety during open trench WORK or for any other potentially unsafe or hazardous construction activities.
Barricades shall be located and displayed in conformance with the most stringent regulations required by the governing agencies. All costs for barricading, including any permits, shall be the responsibility of the CONTRACTOR.
B. See GENERAL CONDITIONS, Article 47, “Safety and Protection”, BCF No. 170.
C. All WORK in public rights-of-way and on private property shall be done in strict compliance with these specifications and Broward County Minimum Standards. Failure to so comply will result in cessation of operations and the removal of project related obstructions from the right-of-way until compliance is achieved.
PART 2 - PRODUCTS (Not Applicable)
END OF SECTION 01111
SECTION 01112
PERMITS
BROWARD COUNTY CANAL PUMP STATION (S-45) IMPROVEMENTS
BC WMD PROJECT NO. 107751
01112-1
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. All applicable provisions of the BCF No. 170 Contract Requirements, and Division 1 - General Requirements shall govern the WORK under this section.
1.02 SCOPE
A. The OWNER has obtained applicable engineering permits and plan approvals from the agencies listed below. The CONTRACTOR is responsible for compliance with any and all permit conditions.
In the event that the OWNER must obtain permits in addition to those listed below, the CONTRACTOR shall not have any claim for damages arising from any delay caused by the OWNER'S obtaining said additional permits.
1. South Florida Water Management District
a. Right-Of-Way
b. Water Use
2. City of Coconut Creek Engineering Permit
a. Engineering Department
3. Broward County Resilient Environment Department
a. Surface Water Management – General License
b. Environmental Resource License
4. Cocomar Water Control District
a. Plan Approval
B. The CONTRACTOR shall obtain a Construction/Building and/or Landscape permit from the City of Coconut Creek, if required.
C. The CONTRACTOR shall obtain a Construction/Building permit from the City of Coconut Creek, if required, for work performed on private property.
D. The CONTRACTOR shall obtain…