This document is a draft bid tabulation from the City of Lubbock, Texas for RFP 25-19043-TF, which involves the Northeast Intermediate Lift Station project. The request for proposal was set to close on August 21, 2025, at 2 PM CST, with five contractors submitting bids from locations across Texas including Umbarger, Lubbock, Amarillo, and Levelland. The project involves construction of an intermediate lift station, with bidders providing both base bid and deductive alternate pricing, and proposing project completion timelines ranging from 175 to 300 consecutive calendar days for substantial completion.

The bid responses show significant variation in pricing, with base bids ranging from $1,451,360.80 (Deerwood Construction) to $4,040,000.00 (MH Civil Constructors, Inc.). The overall total bids, including base and deductive alternate items, span from $1,682,773.20 to $4,083,700.00. Each contractor proposed different project completion timelines, with Bo Simon Inc offering the shortest substantial completion period of 175 days, while MH Civil Constructors, Inc. and Utility Contractors of America proposed the longest at 300 days. The document is explicitly marked as a draft tabulation, with a disclaimer that entries may contain errors and are subject to change during further bid response analysis.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Lubbock, TX

Draft Tabulation

RFP 25-19043-TF

Title: Northeast Intermediate Lift Station

Closing Date: August 21, 2025, at 2PM CST

Contractor Bo Simon Inc Deerwood

Construction

MH Civil

Constructors, Inc.

Rink's Lease

Service

Utility

Contractors of

America

Location: Umbarger, TX Lubbock, TX Amarillo, TX Levelland, TX Lubbock, TX

Base Bid

Total Items (1-1 through 1-17):

$1,657,730.00 $1,451,360.80 $4,040,000.00 $1,638,640.00 $1,564,275.00

Deductive Alternate

Total Items (2-1through 2-2):

$319,200.00 $231,412.40 $43,700.00 $300,200.00 $218,500.00

Overall Total (Items 1-1 through 2-2): $1,976,930.00 $1,682,773.20 $4,083,700.00 $1,938,840.00 $1,782,775.00

Total Consecutive Calendar Days to

Substantial Completion:

175 250 300 270 300

Total Consecutive Calendar Days to

Final Completion:

205 280 330 300 330