This document is a Vendor Questions and Answers (Q&A) file for the Loudermilk Phase II Construction Reclamation project solicited by the Office of Surface Mining Reclamation and Enforcement (OSMRE). The file contains a detailed exchange between a potential vendor and the government agency, addressing critical project requirements such as preconstruction plan submittals, including a Quality Control Plan, Site Access and Traffic Control Plan, and Health and Safety Plan. Key clarifications include confirmation that no offsite soil import is needed, a bid bond is required, and the Site Superintendent can dual-role as Site Safety if qualified.
The document outlines specific submittal requirements for the contract, which include a Bid Schedule, Construction Schedule, AML Contractor Information, Payment Bond, Surety, Bid Bond, Qualifications Statement with equipment list, and Performance Bond. The Period of Performance spans from 08/01/2025 to 07/31/2026, with 325 calendar days allocated for construction work. Additional technical details indicate that OK DOT Specifications will govern rock gradient, no additional jobsite office is required, and no site survey is needed for payment measures by acreage or cubic yards.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VENDOR QUESTIONS OSMRE RESPONSE
Can you confirm which preconstruction plan submittals are required for this project? For example, should we provide a Quality Control Plan, Accident Prevention Plan, Waste Management Plan, Traffic Control Plan, Environmental Protection Plan, and/or Salvage Plan?
Quality Control Plan to ensure compliance with technical and material standards.
Site Access and Traffic Control Plan - Ensures safety and coordination for: Heavy equipment transport, Material staging, Public safety (especially in urban or residential settings).
Health and Safety Plan (HASP) which is Required under OSHA and OSMRE guidelines.
Will there be a need for any imported materials aside from the road gravel and riprap? For instance, is there an anticipated need to import cover materials to complete the topsoil and seeding portion of the project?
No, offsite soil would be needed.
Is a Bid Bond Required. We see the Attachment 8 but only identify a reference to a payment bond in the solicitation.
Yes, a bid bond is required.
Are there any requirements for multiple site personnel in addition to the Site Superintendent? (i.e. Qualtiy Control Manager, SSHO)
No, just ample employees to complete the job.
Can the Site Superintendent dual role as the Site Safety as well if qualified? Yes
Please clarify the PoP. Per Section F of the IFB work shall commence within (1) day of NTP and be complete in 325 calendar days. Section G states the Period of Performance will be from 08/01/2025 to 07/31/2026, or 365 calendar days.
Is this a discrepancy or is it intended to provide (40) calendar days for pre-construction preparation.
it is intended for pre and post construction.
What submittals are required? Bid Schedule (attach 3), Construction Schedule (attach 4), AML Contractor Information, Payment Bond (attach 6), Surety (attach 7), Bid Bond (attach 8), Qualifications Statement to include equipment list and description (attach 9), Performance Bond (attach 10)
Measures for payment by acreage. Is a site survey required for justification? No Measures for payment by cubic yards. Is a site survey required for justification? No
Special provisions states “In case of ambiguity or conflict between Drawings and Specifications, the Specifications shall govern.” There are no technical specifications in the solicitations. Does this refer to the OK DOT Specs?
Yes, for rock gradient only.
Is a jobsite office required? If so, is an additional jobsite office required for use by the government.
No
If coffer dams are required, is an engineered design required and subject to approval?
No