Attachment_B_-_140R6026Q0102_-_Amend_0002_-_Questions_and_Responses_0002.pdf

PDF 62 KB Posted

Attached to
MTE Mobile Crane Support Service
Solicitation number
140R6026Q0102
Issued by

About this file

This is a Questions and Answers document (Attachment B) from Amendment 0002 to the MTE Mobile Crane Support Service contract (140R6026Q0102). The document addresses contractor inquiries regarding lift plan requirements for two primary tasks.

Q12 and A12 clarify that the contractor shall provide a single lift plan incorporating all requirements for lifting bulkhead segments (stoplogs) at the Mt Elbert Forebay Inlet-Outlet structure, transporting them to the Government storage yard, and unloading/staging activities at that location. The contractor is not required to prepare a separate lift plan for activities occurring after arrival at the storage yard, as the revised Performance Work Statement for Task 1 specifies that Government personnel will handle subsequent operations. Q13 and A13 confirm that for Task 2, the contractor may consolidate loading, transportation, and restaging activities into a single lift plan, eliminating the need for separate lift plans for loading test weights at the outdoor storage yard, transporting them to the powerhouse, returning them, and final restaging.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MTE Mobile Crane Support Service

Amendment 0002 – 140R6026Q0102

Attachment B

Questions and Answers

Q12. Is a separate Lift Plan required for unloading/staging the bulkhead (stoplog) segments at the Government storage yard, or may the removal, transportation, and unloading/staging activities be incorporated into the overall Task 1 Lift Plan?

A12. The contractor shall provide one lift plan incorporating the requirements for lifting the bulkhead segments (stoplogs) at the Mt Elbert Forebay Inlet-Outlet structure and transporting to the storage yard. The contractor does not require a lift plan after arrival at the storage yard – See revised Performance Work Statement (PWS) revising Task 1 – “Government Personnel will” section.

Q13. Is a separate Lift Plan required for loading the test weights at the outdoor storage yard, or may the loading, transportation to the powerhouse, return transportation, and final restaging activities be incorporated into the overall Task 2 Lift Plan?

A13. The loading, transportation to the powerhouse, return transportation, and final restaging activities may be incorporated into a single lift plan.

File details come from the government source that posted it. Updated .