This document is an amendment to a solicitation for the Medicine Creek Dam Concrete Repair and Access Improvement project. The key details are:
The purpose of this amendment is to provide answers to questions from potential offerors and update sections of the specifications and drawings. Notable changes include extending the period of performance from 485 to 850 calendar days, revisions to work restrictions and limitations (e.g. timing of culvert and spillway work), updates to security and submittal requirements, and replacement of the Submittals attachment. The solicitation is for concrete repair and access improvements at the Medicine Creek Dam in Nebraska, to be performed for the Bureau of Reclamation. Proposals are due September 13, 2024. The contract will be awarded to the successful offeror based on the evaluation factors outlined in the solicitation.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R6024R0020 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
ACTS# 2979807/19/20240004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/19/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment is to provide the Pre-Proposal Site Visit original agenda/information and sign-in sheet. See the continuation pages for details.
Period of Performance: 11/20/2024 to 03/19/2027
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Ryan Cope
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No. 140R6024R0020
Amendment No. 0004
MEDICINE CREEK CONCRETE REPAIR AND ACCESS IMPROVEMENT
CAMBRIDGE UNIT, PICK-SLOAN MISSOURI BASIN PROGRAM, NEBRASKA
A. Purpose of Amendment 0004: The purpose of this amendment to the subject solicitation is to provide answers to questions posed by potentially interested offerors and to update portions of Attachment 3 – Print-Ready Specifications and Attachment 4 – Print-Ready Drawings, under SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS because of questions and answers. The revised documentation is attached herein.
B. Pre-Proposal Questions & Answers: The following questions and answers are hereby provided.
1. QUESTION: Section 31 23 70: My supplier says that the specified material called out in the above specification is not pumpable with a concrete pumper truck. He is wanting to know if we could use 50 lbs of type 1L Cement, 250 lbs of C Ash and 10% air for CLSM material? This way we could use a pump truck to place material in the pipe and over the riprap.
ANSWER: Refer to Specification Section 31 23 70 Controlled Low Strength Material (CLSM), paragraph 2.05. The Contractor will be required to submit a mix design showing conformance with specified requirements for compressive strength and spread.
2. QUESTION: Can projects from sister companies be used for grading? Our company is divided into subsidiaries, but the same people work on these projects and we will have a wider selection of projects that showcase our experience if this is allowed.
ANSWER: No.
3. QUESTION: Our construction companies are all owned by the {company name redacted}.
We would like to know if we can use projects from any of our companies for qualification?
ANSWER: No.
4. QUESTION: Can you please clarify if Subcontractors also need to supply an entire list of projects performed in the last ten years?
ANSWER: Yes. Refer to Specification Section M, NOTE 1 on page M-3
5. QUESTION: Is there a schedule for water releases from spillway?
If so, will this be provided to GC?
ANSWER: There are no water releases planned from the spillway during construction.
6. QUESTION: Are ground water readings available for ground water?
ANSWER: There are no groundwater readings available.
7. QUESTION: Are dowels required to anchor patches to existing substrate?
ANSWER: No. New cast-in-place concrete will be secured with existing reinforcement steel.
Refer to Specification Section 03 81 10 Concrete Removal paragraph 3.04.N and revised Section 52 00 00 Drawings
8. QUESTION: Is there a specification or requirement for water stop?
ANSWER: Refer to specification Sections 03 15 12 PVC Waterstop and 03 15 14 PVC Retro-Fit Waterstop.
9. QUESTION: Will closing of the road across the dam be allowed? We may need to close the road 4-5 times for 1-day durations to allow concrete pumping.
ANSWER: Refer to Specification Section 01 55 20 Traffic Control.
10. QUESTION: Can we put rock or panels at the bottom of the spillway once it's drained?
ANSWER: Refer to Specification Sections 01 56 10 Protection of Existing Installations and 01 74 00 Cleaning and Waste Management.
11. QUESTION: Can we Hydrocut in place of saw cutting?
ANSWER: No. Refer to Specification Section 03 81 10 Concrete Removal paragraph 3.04.M.
12. QUESTION: What amount of control or containment is going to be required pertaining to slurry?
ANSWER: Refer to Specification Section 01 57 30 Water Pollution Control.
13. QUESTION: Can the pond below the spillway be pumped downstream to allow access to lower panels?
ANSWER: Refer to Specification Section 02 70 10 Removal and Control of Water.
14. QUESTION: What precautions/BMP’s are required to pump outflow?
ANSWER: Refer to Specification Section 02 70 10 Removal and Control of Water.
15. QUESTION: Is there going to be a scheduled site visit? I haven’t seen an amendment scheduling one but pdf page 2 of the documents state that one will be scheduled.
ANSWER: The organized site visit was detailed in Amendment 1 posted on July 22, 2024.
16. QUESTION: Pdf page 2 of the documents under the project foreword bullet point 4 mentions that repair of cracked concrete on the spillway bridge piers will be required. I can’t find estimated quantities, nor a specification section addressing the limits and processes involved in this portion of the work. The crack repair is mentioned in the contract drawings as well but again there isn’t enough information to ascertain the quantity of work to be performed.
ANSWER: Refer to revised Drawing 325-600-60077. The estimated quantity is covered under Section B Price Schedule for 03 30 00 Cast-In-Place Concrete, and 03 81 10 – Concrete Removal.
17. QUESTION: The instructions to proposers states 3 projects may be submitted for past experience. Is it acceptable to submit more than 3 projects? We intend to submit 3 of our projects as prime contractor and 3 projects for our key subcontractor performing the hydro demolition for a total of 6 projects.
ANSWER: Refer to Sections L, Factor 2. Provide at least 3 projects. Also, Refer to Specification Section M, Note 1. Provide company experience for sub-contractors as well.
18. QUESTION: Plan sheet 328-600-60077 section A Pier profile calls out to “coat exposed portions of front face”
ANSWER: There is no coatings work. Refer to revised Drawing 328-600-60077 in revised Specification Section 52 00 00 Drawings.
19. QUESTION: Can the government shut the outlet works discharge water flow off to facilitate installation of the culverts and discharge channel crossing.
ANSWER: The outlet works will be closed during the non-irrigation season to allow installation of the culvert crossing. See revised Specification Section 01 14 12 – Work Restrictions and Limitations paragraph 1.02, B.
20. QUESTION: Following installation of the discharge channel culverts and crossing will the government than open the outlet works discharge pipe to allow lake water to be drawn and used for construction purposes.
ANSWER: Releases from the outlet works will be made to maintain the reservoir and for irrigation releases. No additional releases will be made for construction purposes.
21. QUESTION: Relating to questions 2 and 4 below – what CLIN should proposers put the costs of the crack repair and coating works under? None of the existing CLINS lend themselves to these scopes of work.
ANSWER: There is no coatings work. Crack repairs on pier should be included under CLIN 4 Cast-In-Place Concrete. Refer to revised Drawing 328-600-60077 in revised Specification Section 52 00 00 Drawings.
22. QUESTION: Can the date for questions be extended given the site visit hasn’t occurred yet and the August 14th date has passed.
ANSWER: Amendment 2 extended the deadline for questions.
23. QUESTION: Can the proposal due date be extended.
ANSWER: Amendment 2 extended the deadline for proposals.
24. QUESTION: We would like to better understand the timing limitation outlined in spec 01
14 12 If possible (there maybe reasons for the restriction we are unaware of) we believe the work on the culverts needs to be starting in March or April 1 of 2024 and finishing in April or even early May as its necessary to gain access to the spillway. The anticipated Notice to Proceed is 11-29-24, at that time submittals will began being created and sent to the Bureau for review, I fear with the holidays and possibility of some submittals being rejected on their first review that we may not be ready to start work February 1, 2025. I don’t see a problem with work on the upstream side of the spillway occurring between Sept 1, 2025 – March 31, 2026 – only the culverts/access road to the spillway.
ANSWER: Refer to revised Specification Section 01 14 12 Work Restrictions and Limitations and revised Section F.
25. QUESTION: Is the 24/7 continuous pumping only required until completion and approval of the culvert portion of the road construction?
ANSWER: Refer to Specification Section 02 70 10 – Removal and Control of Water.
26. QUESTION: Does this project require a Full-Time Superintendent, Quality Control Manager and a Safety Officer? Or can the select personnel fulfill multiple roles (i.e.
Superintendent “dual hatting” as Safety Officer)? Note: There will be a significant amount of QC testing performed during this project. In fact, {company name redacted} envisions a representative of the independent testing agency being onsite daily throughout construction.
As a possible cost savings measure, would BOR consider allowing the independent testing agency, in lieu of the contractor, to function as the QC Manager, given their daily presence onsite?
ANSWER: No. Refer to Specification Section 01 46 00 Quality Procedures. The effectiveness of the Contractor’s Quality Control Program will be subject to continued review and approval by the CO.
27. QUESTION: Can water from Harry Strunk Lake be used in and for hydro/water cutting and saw cutting activities?
ANSWER: Yes, provided it meets the water quality standards required of the equipment used.
28. QUESTION: Can the runoff of hydro cutting activities be land applied to the adjacent ground below the Dam?
ANSWER: No. Refer to Specification Sections 01 57 30 Water Pollution Control and 01 74 00 Cleaning and Waste Management.
29. QUESTION: Please identify where, if concrete is mechanically removed, concrete debris is to be disposed of?
ANSWER: Refer to Specification Section 01 74 00 Cleaning and Waste Management paragraph 3.03.
30. QUESTION: There is no way to accurately estimate the amount of rebar replacement that will be required. If rebar/reinforcement is encountered that is rusted, degraded, or not at the stated depth of 3”, is there a CLIN to address rebar replacement on a unit-based quantity? Will the Government QC be on-site to determine if reinforcement is acceptable or determine and approve new rebar replacement? if rebar replacement is required, please provide a repair detail drawing for various scenarios.
ANSWER: Refer to Specification Sections 03 20 00 Concrete Reinforcing, 03 81 10 Concrete Removal and Drawing 40-D-60004.
31. QUESTION: The Government indicated that full-time or part-time onsite QC oversight will occur. Will the COR we able to approve “field adjustments” and “rebar replacement” on-site without delay or stop of work?
ANSWER: Yes.
32. QUESTION: If the contractor would reshape and grade the access road on the east side of the dam, to remove the extensive gulling, would it be allowable to utilize the road to bring materials in from that side of the spillway?
ANSWER: Yes. Refer Specification Section 01 14 00 Use of Site.
33. QUESTION: If a schedule can be developed and implemented to install the culvert area completely, could the remaining portion of the roadway be finished after the April 1 deadline?
ANSWER: Yes. Refer to revised Specification Section 01 14 12 Work Restrictions and Limitations.
34. QUESTION: Please provide the geology and/or reports that indicate the insitu soils and existing rock site conditions are adequate for road construction and soils and existing materials will proctor and compact in compliance with specifications.
ANSWER: All known geology is provided in Attachment 5 Geology Drawings.
35. QUESTION: Can the access road on the East side of the dam be used for concrete pumping and crane operations to access spillway.
ANSWER: Refer to Specification Section 01 14 00 Use of Site.
36. QUESTION: If East access can be used, can the area behind the spillway retaining wall be excavated and leveled up as needed to allow for concrete pump truck and crane operations.
ANSWER: Refer to Specification Section 01 14 00 Use of Site.
37. QUESTION: If the local concrete ready-mix does not have acceptable ASR (Alkaline Silica
Reactivity) test for the ready-mix aggregates mined locally, can admixtures be used to mitigate ASR?
ANSWER: No. Refer to Specification Section 03 30 00.
38. QUESTION: The Controlled Low Strength Material (CLSM) spec, 31 23 70, is not a pumpable material. Based on discussions with one particular supplier, the following mix is recommended to make it more pumpable: 50 lbs of type 1L, 250 lbs of C Ash and 10% air.
Would BOR accept this mix design as an allowable substitution?
ANSWER: Refer to Specification Section 31 23 70 Controlled Low Strength Material (CLSM), paragraph 2.05. The Contractor will be required to submit a mix design showing conformance with specified requirements for compressive strength and spread.
39. QUESTION: To facilitate installation of the culverts, will BOR be completely shutting off water released from the outlet works; or does the contractor need to construct a coffer dam, in conjunction with a pumping system, to pump water away from the work area of the culvert?
ANSWER: The outlet works will be closed during the non-irrigation season to allow installation of the culvert crossing. See revised Specification Section 01 14 12 – Work Restrictions and Limitations paragraph 1.02, B.
40. QUESTION: According to Section 01 57 30 (1.05.A.1.a): “The Bureau of Reclamation has made application for a permit to discharge dredged or fill material into waters of the United States (including wetlands) as required under section 404 of the Clean Water Act (Public Law 92-500 as amended.” What is the status of the 404 permits?
ANSWER: Reclamation received notice for the Corp of Engineers that this project is covered under the Nationwide Permit 14.
41. QUESTION: According to Section 01 57 30: “Prior to discharging wastewater or other pollutants, secure a permit to discharge pollutants as required under section 402 of the Clean Water Act.” Also, Paragraph 1.05A.1.3.a of the specification states: “Provide monitoring and water treatment, if necessary, to achieve compliance with permit conditions.” Is any of the construction work associated with the concrete repairs considered a source of “wastewater” discharge under an NPDES permit? Has BOR applied for a QUESTION: Section 402 permit, or is that the contractor’s responsibility? Also, does the BOR know if water to be pumped and released during this project requires filtration or other pretreatment methods?
ANSWER: Refer to Specification Section 01 57 30 Water Pollution Control paragraph 1.05 A, Wastewater Discharge Permit. The Contractor is required to obtain the Section 402 Permit.
Conditions of the permit will dictate whether the water will need treated prior to discharge.
42. QUESTION: Please confirm if an Air Quality Permit is required for this contract?
According to Section 01 57 32 Paragraph 3.01, it appears a permit is required. Based on BOR’s experience, how long does it take NDEQ to process an Air Quality Permit application for a construction project such as this one?
ANSWER: Reclamation does not know how long it will take NDEQ to issue this permit.
43. QUESTION: Will the BOR furnish a State of Nebraska Project Exemption Certificate
(PEC) (i.e. sales tax exemption) for this project?
ANSWER: No. Contract price shall include all Federal, State, and Local taxes. Refer to Section I – Contract Clauses, FAR Clause 52.229-3.
44. QUESTION: What is the process for getting construction personnel cleared for site access?
Is full badging required? How much time can we expect for site security requirements?
ANSWER: See revised Section H paragraph H.2 and revised Specification Section 01 33 00 Submittals.
45. QUESTION: What is the existing strength of concrete to be removed?
ANSWER: Strength of the existing concrete is unknown and varies.
46. QUESTION: The local concrete provider has not responded to inquiries on if their mixes can meet the concrete specifications. Therefore, is the BOR amenable to the contractor utilizing a mobile batch plant to mix concrete per the project specifications?
ANSWER: A mobile batch plant would be allowed provided it meets the certification requirements in Specification Section 03 30 00 Cast-In-Place Concrete paragraph 2.07.
47. QUESTION: Will the contractor be allowed to place anchors into the concrete surface of the spillway if the holes are filled once the anchors are removed? If so, can a fast-curing epoxy be used to fill the holes (ex. Hilty HY200).?
ANSWER: Refer to Specification Section 03 30 00 Cast-In-Place Concrete paragraph 3.10.
48. QUESTION: Is there a power source available near the contractor staging area to hard wire the required backup pumps for dewatering? Would contractor be allowed to tap into this power source? Would metering be required?
ANSWER: Refer to Specification Section 01 51 00 Temporary Utilities. There is overhead power located at the outlet works. There is no power at the spillway. Contractors should contact Twin Valleys Public Power District for information on obtaining metered power.
49. QUESTION: Will slurry water from hydro-demolition activities need to be captured and hauled off site?
ANSWER: Refer to Specification Sections 01 57 30 Water Pollution Control and 01 74 00 Cleaning and Waste Management.
50. QUESTION: The specifications mention the use of certified flaggers where trucks and equipment are crossing a public roadway. Is the BOR amenable to removing this requirement from the scope to reduce project costs? Drivers would abide by traffic laws and signage (i.e. stop at stop signs at public road crossings and look both ways before traversing across).
ANSWER: Refer to Specification Section 01 55 20 Traffic Control. Flaggers are only needed as required in MUTCD Part 6 Temporary Traffic Control. (i.e. lane closures, construction equipment operating on public roadway, etc.)
51. QUESTION: When do you expect the hydro demolition portion of work to begin?
ANSWER: Refer to revised Specification Section 01 14 12 Work Restrictions and Limitations.
52. QUESTION: Are there any phase requirements for the hydro demolition portion of work?
If yes, what is the timeline between the phases?
53. QUESTION: Will there be a cofferdam constructed to create an area for hydro demolition water to be captured without running into the river water?
ANSWER: Refer to Specification Sections 02 70 10 Removal and Control of Water and 01 57 30 Water Pollution Control.
54. QUESTION: Section 01 31 19, Part 01.04.A.1.a.1 mentioned Project Engineer attendance.
Does this project require a full-time or part-time On-site Project Engineer? If yes, does he/she need to be employed by the Contractor?
ANSWER: There is not a requirement for a Project Engineer.
55. QUESTION: Section 01 35 30 – 4, Part 01.05.D talks about CIH requirement; However, D.1.b states that or as deemed necessary by the COR. Does this project have full time or part time On-Site CIH requirement? If yes, does he/she need to be employed by the Contractor?
ANSWER: Refer to revised Specification Section 01 35 20 Safety and Health paragraph 1.03, B, 8, r, 1, e.
56. QUESTION: Does any work need to be performed in the upstream face of spillway?
ANSWER: No. Refer to revised Specification Section 01 14 12 Work Restrictions and Limitations and revised Drawing 328-600-60077 in revised Specification Section 52 00 00 Drawings.
57. QUESTION: Does any sandblasting and coating need to be performed on this project?
ANSWER: There are no coatings to be performed. Sandblasting may be required as specified in Section 03 30 00 Cast-In-Place Concrete paragraph and revised drawing 328-600-60077.
58. QUESTION: Has the government performed any type of survey for existing contaminants?
On these solicitations, there are typically preliminary assessments/surveys for contaminants that provides the basis for all the environmental, industrial hygiene, and safety/health requirements listed in the project specifications. If a survey or assessment has been performed, can you please provide a copy of it? If a survey is not performed, please let us know the requirements of exposure assessments.
ANSWER: The Government has not performed surveys or testing for existing contaminants.
Exposure assessments are for engineering controls to mitigate exposures to hazardous substances or potential environmental impacts. (i.e. respirable silica, excessive noise, etc.) Refer to Specification Section 01 35 20 Safety and Health.
59. QUESTION: Can the contractor begin spillway repairs with pier 2 and 3 repairs then starting at Panels 1-7 and working from top to bottom? The specs say to complete panels 43
– 56 first but we believe the work will be more efficient and safe proceeding from top to bottom as the hydro demolition debris will always be rolling down to the stilling basin which will make it hazardous to begin performing concrete repairs below the robot.
Starting at panels 43-56 could create a need for the hydro demolition equipment to demobilize and remobilize while waiting for the lower concrete repairs to complete and cure prior to beginning removals at the top.
60. QUESTION: Per Page 379, Factor 2: Company Experience, provide at least three (3) past projects and the following information must be provided for each project:
• Key personnel directly involved in the projects. Provide resumes of key personnel from the projects for personnel currently employed by the offeror/subcontractor.
Please clarify if we submit a project that none of the key personnel remain on our current staff, that the project is still valid to be submitted for past performance. Typically, it is a requirement to provide resumes for planned staff for a proposed project.
ANSWER: Refer to revised Sections L & M removing the requirement for key personnel resumes and evaluations thereof.
61. QUESTION: Per Page 379, Factor 2: Company Experience, for consideration of projects for evaluation, could you please advise if it is acceptable to use the experience and qualifications sister companies and/or related subsidiaries under the same parent company for consideration for this proposal?
ANSWER: No.
62. QUESTION: There is a requirement for a part time Safety Professional in 01 35 30. How often does this individual need to come to the site?
ANSWER: See revised Specification Section 01 35 30 Contractor’s On-Site Safety Personnel.
63. QUESTION: 01 14 12 1.02.B.1 (Work Restrictions and Limitations) notes that work on the culverts will be limited to Sept 1st through March 31st. Will the Outlet Works Regulating Gate be closed at this time and that the only flow will be from leakage from the gate, and seepage from the toe-drain outfalls?
64. QUESTION: Can the Government provided an estimate of the amount of leakage for the
Outlet Works Regulating Gate?
ANSWER: Refer to revised Specification Section 02 70 10 Removal and Control of Water.
65. QUESTION: 31 02 10 – Water for dust abatement requires water to be applied twice a day during earthwork activities. Is there a water source that can be utilized from the lake or outlet works or does the contractor have to source water themselves?
ANSWER: Water from the reservoir may be used.
66. QUESTION: 02 70 10 3.02.A notes the requirement to remove any debris in the stilling basin. Does the Government expect there to be existing debris in the basin or does this note refer to debris from construction activities? If there is existing debris, does the Government have an idea as to how much debris that may require removal?
ANSWER: The stilling basin was un-watered and cleaned in 2017. The government expects little to no debris in the stilling basin. Refer to Specification Section 01 74 00 Cleaning and Waste Management.
67. QUESTION: On Sheet 16 (Detail A on Drawing 60077- Pier Profile), there is a note to “Coat
Exposed Portions of Front Face” on the pier. Is there further information on this requirement?
ANSWER: There is no coatings work. Refer to revised Drawing 328-600-60077 in revised Specification Section 52 00 00 Drawings.
C. Revised solicitation sections/pages: The following revised documentation or requirements in the solicitation are hereby identified or provided as attached.
a. SF-1449 - Revised Completion Date: The original completion period of 485 calendar days as shown in SF-1442 – SOLICITATION, OFFER AND AWARD, block 11, is hereby extended by 365 calendar days from 485 calendar days to 850 calendar days.
b. SECTION F – DELIVERIES OR PERFORMANCE: Page F-1, FAR clause 52.211-10 is hereby edited to reflect a completion period of 850 calendar days.
Change page for F-1 attached herein.
c. SECTION H – SPECIAL CONTRACT REQUIREMENTS: Page H-1 is modified to add local clause G-7 SITE SECURITY (Feb 2004) to replace deleted Contract Clause I.14 WBR 1452.237-80 SECURITY REQUIREMENTS – BUREAU OF RECLAMATION ALTERNATE III (MAR 2022). Replacement pages H-1 and H-2 are attached herein.
d. SECTION I – CONTRACT CLAUSES: Contract Clause I.14 WBR 1452.237-80
SECURITY REQUIREMENTS – BUREAU OF RECLAMATION ALTERNATE III
(MAR 2022) is hereby deleted in favor of local clause G-7 SITE SECURITY under Section H. Pages I-20 through I-30 change pages to reflect this deletion are attached herein.
e. SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS: The table on page J-1 is hereby revised to reflect change pages to Attachments 3 and 4, and a complete replacement of Attachment 6. The change pages and replacement Attachment are attached herein.
f. SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO
OFFERORS:
i. Provision L.7 WBR 1452.215-81 – PROPOSAL INSTRUCTIONS –BUREAU OF RECLAMATION (MAR 2021), paragraph (f)(1)(e), Factor 1, Subfactor 1A is revised to reflect a NTP date of approximately November 2024 and work on the culvert crossing beginning September 2025. Change page L-7 is attached herein.
ii. Provision L.7 WBR 1452.215-81 – PROPOSAL INSTRUCTIONS –BUREAU OF RECLAMATION (MAR 2021), paragraph (f)(1)(e), Factor 2, is revised to remove the Key Personnel requirement. Change page L-7 is attached herein.
D. Attachments to Amendment 0004:
Document(s) Page Number(s) # Pages Date Section F change page (change in yellow highlight) F-1 1 8/30/2024 Section H change pages (title of new clause in yellow highlight)
H-1, H-2 2 8/30/2024
Section I change pages I-20 thru I-30 11 8/30/2024 Section J change page J-1 1 8/30/2024
Section J, change pages for Attachment 3 – Print-Ready Specifications for Medicine Creek Dam Concrete Repairs
Pages for Sections:
01 14 12, 01 33 00, 01 35 30, 02 70 10, 52 00 00, Pages for Drawings:
328-600-60077-RD-1
27 8/30/2024
Section J, complete replacement of Attachment 6 – Submittals for Medicine Creek Dam Concrete Repairs All 10 8/30/2024
Section L change page L-7 11 8/30/2024
E. Proposals Due: The due date for proposals remains unchanged on September 13, 2024, as described in Amendment 0002.
F. Acknowledgement Requirement: See Block 11 on the Standard Form 30 form above regarding how to acknowledge this amendment. The Government must receive acknowledgment of each amendment issued under this solicitation within Block 19 of the Standard Form 1442 at time of your proposal submission.
Medicine Creek Dam Concrete Repairs and Access Improvement Cambridge Unit, Nebraska Solicitation Number: 140R6024R0020
F-1
SECTION F -- DELIVERIES OR PERFORMANCE
F.1 52.252-2 - CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at the following addresses:
FAR Clauses - https://www.acquisition.gov/far/
The following clauses have been incorporated by reference:
CLAUSE TITLE DATE
52.211-10
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
fill-in: (a)…within 10 calendar days… fill-in: (c)…not later than 850 calendar days…
SEP 2000
52.211-12 LIQUIDATED DAMAGES-CONSTRUCTION
fill-in: (a) …$3,200.00 per day… SEP 2000
52.211-13 TIME EXTENSIONS SEP 2000
52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984
52.242-14 SUSPENSION OF WORK APR 1984
Amendment 0004 dtd 08/30/2024 https://www.acquisition.gov/far/ KMunro Highlight
Cambridge Unit, Nebraska Solicitation Number: 140R6024R0020
H-1
SECTION H -- SPECIAL CONTRACT REQUIREMENTS
H.1 GP-1 - SCHEDULE OF VALUES (JUL 2019)
(a) Definitions.
“Schedule of Values” means the clearly definable tasks, and the cost associated with each of those tasks, which comprise the total work effort required to complete a lump sum contract line item.
Except for the Mobilization and Preparatory Work line item, the Contractor shall submit a Schedule of Values for review and acceptance for all lump-sum Contract Line Item Numbers listed in Section B.
The Schedule of Values will be used to assess the intermediate value of work completed for the purpose of making progress payments.
H.2 GP-2 - PAYMENT FOR TECHNICAL DATA (JUL 2019)
The Contracting Officer shall retain five percent (5%) from all progress, or other payments made under this contract (excluding any payment for mobilization and preparatory work) until the Contractor receives final acceptance of the contract.
H.3 GP-7 SITE SECURITY FEB 2004
(a) At least 10 days prior to arriving at the worksite, the contractor shall submit a list to the Contracting Officer (CO) of the names of all contractor employees that will be on-site initially. Additional employee names must be provided to CO prior to additional employees arriving on-site. The list(s) must include a legible photocopy of each employee's driver's license. In the absence of a driver's license, provide an alternate source of official identification that includes: First, Middle, Last Name; date and place of birth; and place of residence. All contractor employees must be U.S. citizens or have a valid Immigrant Visa Number, Permanent Resident Card or Resident Alien Card authorizing them to work in the U.S.
(b) The contractor is hereby notified of the following:
The Government may perform background checks on any or all workers. If the Government performs background checks, workers shall be required to submit additional personal and work history information. The Government may deny access to any worker at any time, based on information discovered during the background check. Information related to criminal matters (e.g., outstanding arrest warrants) that is discovered during a background check will be reported to the appropriate authorities.
(c) At least 10 days prior to arriving at the worksite, the contractor shall submit an initial list to CO of all contractor vehicles to be brought to the worksite. A supplemental list shall be provided to CO before additional vehicles are brought on-site. For each vehicle the list shall include the year, make, model and color; and license plate numbers and state of issuance when applicable.
(d) Reclamation will provide keys and/or locks to gates and doors, etc. as necessary for contractor personnel to access points within the scope of this project. Any duplication of keys or substitution of locks is strictly
Amendment 0004 dtd 08/30/2024
Cambridge Unit, Nebraska Solicitation Number: 140R6024R0020
H-2 prohibited. Contractor shall be accountable to secure and return all keys and/or locks provided by the Government and shall immediately notify the CO of the loss or misplacement of any provided key and/or lock.
(e) All drawings, plans, and other sensitive documents issued to the contractor shall remain under their direct control at all times. These sensitive documents shall not be reproduced or copied or further distributed without approval from CO.
(f) All firearms and dangerous weapons are prohibited in Federal facilities for all persons not specifically authorized by Title 18, United States Code, Section 930. A license to carry a concealed firearm issued under state law is not an exception to this prohibition. This prohibition shall apply to all areas within the construction worksite and contractor use area.
(g) In case of an emergency situation, the contractor shall follow emergency instructions provided by CO.
(h) Unless exempted by CO, the contractor shall comply with all security requirements already in place at the site, i.e., those security requirements that have been adopted as standard operating procedures at the site.
(i) The contractor shall report to the CO all incidents of criminal and/or suspicious activity observed by their employees on or adjacent to the construction site.
(j) Reclamation reserves the right to change or modify security requirements as mandated by the Office of Homeland Security and/or as deemed necessary by Reclamation security staff.
(k) Any violations of Reclamation security requirements and/or restrictions may result in Reclamation denying the contractor personnel access to the worksite.
(l) Cost - Include cost incurred for General Security Requirements in prices offered in the schedule for other items of work. In the event Reclamation changes of modifies these requirements after the contract is in place, increased Contractor costs will be paid for under the Contract Change Clause.
(m) Contractor shall notify the CO at least 24 hours in advance of any material delivery to worksite. Material may only be delivered to areas approved by CO.
Cambridge Unit, Nebraska Solicitation Number: 140R6024R0020
I-20
(f) Subcontractors. The Contractor shall insert this clause in all subcontracts that involve performance of work on job site terrain.
(g) Cost. Except as provided in subsection (e) above, the cost of complying with this contract clause shall be included in the prices offered in the schedule for other items of work.
(h) Government Access. The Contractor's arrangement with landowners shall permit the Government or its representatives access to the land to identify cultural resources and conduct appropriate inspections during the Contractor's use of the area or during material procurement.
I.14 WBR 1452.237-80 - SECURITY REQUIREMENTS – BUREAU OF RECLAMATION –
ALTERNATE III (MAR 2022)
(a) General Security Requirements:
(1) This clause addresses security requirements, including general procedural requirements, information security requirements, contractor employee suitability requirements, identification card requirements, site security requirements, vessel exclusion barriers, and information technology security requirements. Within this clause, COR means Contracting Officer's Representative. If there is no COR appointed and identified to the Contractor, the term instead will mean the Program Manager or any other authorized individual responsible for technical oversight under the contract. “Work site” means the Government facility, office, construction site, and any other area within the Government office or facility that the Contractor must access to accomplish work under this contract.
(2) The work performed under this contract shall only be accomplished by individuals (in the employment of the Contractor or any subcontractors) whose conduct and behavior is consistent with the efficiency of the Federal Service and the requirements of this contract, and who are acceptable to the contracting officer. If Reclamation finds a Contractor employee to be unsuitable or unfit for his or her assigned duties, the contracting officer will direct the Contractor to remove the individual from the contract and access to the Federal facility at which the contract activities are occurring.
(3) The Contractor’s employees governed by this contract may need access to sensitive information and/or sensitive areas. The Federal Government (Government) reserves the right, in its sole discretion, to determine suitability of Contractor personnel and deny access to any sensitive information or project specific area to any personnel for any cause.
(4) The Contractor is responsible for informing and ensuring compliance by its employees with any applicable security procedures of the Government facility where work may be performed under this contract.
(5) Any Contractor employee that will have access to a Federally-controlled facility or information system will be required to have a Government-issued identification card, consisting of a Personal Identity Verification (PIV) Card, a temporary identification card, or a visitor badge.
(Note: within the Department of the Interior this card is known as a DOI Access Card.) During performance of the contract, the Contractor shall keep the COR apprised of any changes in personnel, or changes in personnel access or duration, to ensure that performance is not delayed by compliance with credentialing processes.
Amendment 0004 dtd 08/30/2024
I-21
(6) A Contractor employee will not be provided access to a Government facility or information system until a Government PIV Card, temporary identification card, or visitor identification badge has been issued to the Contractor employee. For those individuals that will be receiving a PIV Card, the Government may, at its discretion, issue a temporary identification card or visitor identification badge after the electronic background investigation forms have been received and the investigation is initiated.
(7) All Contractor employees shall access the facility via the facility’s entry screening system and visibly display the Government-issued PIV Card, temporary identification card, or visitor identification badge at all times. Contractor employees must visibly wear the Government-issued identification card at all times they are on Government facilities. Contractor employees are responsible for the safekeeping of all Government-issued identification cards, whether on-site or off-site. Cards that have been lost, damaged, or stolen must be reported to the COR and DOI Access Sponsor immediately, but not later than within 24 hours. The Contractor shall return all identification cards and card keys and any other Government property and information upon completion of performance or when personnel depart permanently or for a period of 7 days or more. The Contractor may be required to turn in access control cards or identification cards on a daily basis.
(8) Misuse or loss of access control or identification cards, or failure to comply with required surrender of such cards may, at Government discretion, result in Contractor personnel being denied access to the work site, at no cost to Government. The Contractor may be charged up to $500 for each occurrence for any required replacement of Government-issued access control or identification cards due to loss or misuse. At the end of contract performance, or when a Contractor employee is no longer working under this contract, the Contractor shall ensure that all access control and identification cards are returned to the COR.
(9) All Contractor personnel, including subcontractor personnel, with access to the work site shall be U.S. citizens or foreign individuals legally residing in, or legally admitted to, the U.S. For all non-U.S. citizens working under this contract, irrespective of length of time working on the contract, the Contractor shall provide to the COR, legible and valid copies of the individual’s passport and visa (unless individual is on the Visa Waiver Program) a minimum of 14 calendar days prior to beginning work or arriving at the facility. A driver’s license is not acceptable identification. In addition, a completed form I-94 shall be submitted to the COR upon the individual’s arrival at the work facility and prior to beginning work.
(10) The Contractor shall report all contacts with entities, individuals, and counsel/representatives (including foreign entities and foreign nationals) who seek in any way to obtain unauthorized access to sensitive information or areas. The Contractor shall report any violations of contract provisions, laws, executive orders, regulations, and guidance to the contracting officer. The Contractor shall report any information raising a doubt as to whether an individual’s eligibility for continued employment or access to sensitive information is consistent with the interests of National Security and the Public Trust.
(11) Unsanctioned, negligent, or willful inappropriate action on the part of the Contractor (or its employees) may result in termination of the contract or removal of some Contractor employees from Reclamation facilities at no cost to the Government. These actions include, but are not limited to, exploration of a sensitive system and/or information, introduction of
I-22 unauthorized and/or malicious software, inappropriate release of sensitive information, or failure to follow prescribed access control policies and/or security procedures. Failure to comply with Reclamation policies, procedures, or other published security requirements may result in termination of the contract or removal of some contracted employees from Reclamation buildings and/or facilities at no cost to the Government.
(12) All provisions of this clause shall equally apply to all subcontractors. The Contractor shall incorporate the substance of this clause in all subcontracts.
(13) These security requirements apply to all sections of this Contract including Contract Drawings and other Contract Specifications as applicable. Related documents include other general provisions of Construction or Operations and Maintenance type Contracts, including FAR clauses by reference or as amended by related documents.
(b) Information Security Requirements.
(1) Sensitive Information. The term “sensitive information” means any information which warrants a degree of protection and administrative control as defined by Reclamation or that meets the criteria for exemption from public disclosure set forth under Sections 552 and 552a of Title 5, United States Code: the Freedom of Information Act and the Privacy Act. Sensitive information is generally categorized as CONTROLLED UNCLASSIFIED INFORMATION (CUI), but in some cases may include other unclassified information. (The protection of National Security information is beyond the scope of this clause. If any work on National Security information is required under this contract, it is addressed under other contract clauses.) The Contractor shall protect this type of information from unauthorized release into public domain, or to unauthorized persons, organizations, or subcontractors. Information which, either alone or in aggregate, is deemed sensitive by Reclamation shall be handled and protected in accordance with Reclamation Directives and Standards SLE 02-01 Identifying and Safeguarding Controlled Unclassified Information (CUI), which is available from the COR or at http://www.usbr.gov/recman/DandS.html#sle.
(i) Any Government-furnished information or material does not become the property of the Contractor and may be withdrawn at any time. Upon expiration or termination of the contract, all documents released to the Contractor and any material created using data from such documents shall be returned to the COR for final disposition. Government-furnished information residing on any electronic systems (laptops, servers, desktops, media) shall be deleted from those systems using a COR-approved data erasure solution. Only with prior authorization from the contracting officer may the Contractor retain the material. The Contractor or subcontractor shall not disclose or release the materials provided to the Contractor to any individuals of the Contractor's organization not directly engaged in providing services under the contract or that do not have a valid need-to-know. All technical data provided to the Contractor by the Government shall be protected from public or private disclosure in accordance with the markings printed on them. All other information relating to the items to be delivered or the services to be performed under this contract shall not be disclosed by any means without prior approval of the contracting officer. Prohibited dissemination or disclosure includes, but is not limited to: permitting access to such information by foreign nationals or by immigrant aliens who may be employed by the Contractor, publication of technical or scientific papers, advertising, disclosure to Contractor staff not investigated and deemed acceptable at the appropriate information sensitivity level, I-23 and any other public release. The Contractor shall maintain, and furnish upon request of the contracting officer, records of the names of individuals who have access to sensitive material in its custody and the sensitive material to which the individuals had access. All questions regarding information security, access, and control shall be referred to the COR.
(ii) The Contractor shall not release to anyone outside the Contractor’s organization any sensitive, or otherwise protected information, regardless of medium in which it is contained (for example, film, tape, document, electronic), pertaining to any part of this contract or any Reclamation program or activity, unless the contracting officer has given prior written approval. This includes, but is not limited to, news releases, marketing promotions, articles, interviews, reports, social media posts, and any other media releases. Requests for approval shall identify the specific information to be released, the medium to be used, the purpose for the release, and a description of the need-to-know. The Contractor shall submit its request to the contracting officer ten business days before the proposed date for release. Subcontractors shall submit requests for authorization to release through the prime Contractor to the contracting officer.
(iii) The Contractor shall notify the COR immediately when known or suspected loss/compromise of sensitive information or other documents, notes, drawings, sketches, reports, photographs, exposed film or similar information which may affect the security interests of Government has occurred. This requirement extends to employees and other personnel working on behalf of the Contractor, and expands responsibility to include prompt reporting of security issues, including observed or subsequently discovered efforts by unauthorized persons to gain unauthorized access to sensitive information.
(2) Classified Information.
(i) The disclosure of U.S. Government documents by third parties can result in damage to our national security. While this contract may not deal directly with classified information, each contractor is obligated to protect classified information pursuant to all applicable laws and to use Government information technology systems in accordance with agency procedures so that the integrity of such systems is not compromised.
(ii) Unauthorized disclosures of classified documents (whether in print, on a blog, or on websites, or other electronic or non-electronic media) do not alter the documents' classified status or automatically result in declassification of the documents.