This is a Statement of Work for RFQ No. 140R3026Q0054 issued by the Bureau of Reclamation for the purchase of two replacement HydroFlo vertical turbine sump pump assemblies for Hoover Dam. The contractor must supply 2 interchangeable pump assemblies that are compatible with the currently installed systems to facilitate maintenance and reduce the need for expanded spare parts inventory. The pumps must be 16HH single stage vertical turbine assemblies with specific technical specifications including 1.5" head shaft assembly (416 stainless steel), coated steel motor stand with 16" 150# flat face discharge flange, approximately 630" of 16" oil lube/water flush column assembly, 16HH oil lube/water flush bowl assembly, 304 stainless steel basket strainer, Tnemec N140 coating (6-8 mils dry film thickness), 316 stainless steel impeller and collet, and a 2300V, 3-phase, 60 Hz, 150 HP motor rated for 5000 GPM flow, 60 ft head, and 18.6 ft maximum NPSHr.
The contractor must submit five documents for review/approval with a 14-calendar-day review period per submittal, including general pump arrangement drawing, pump datasheet with performance curves, motor nameplate datasheet, motor dimensions drawing, and coatings material datasheet. Reference documents must include equipment operation and maintenance manuals with instruction leaflets for all components, overhaul/refresh parts and materials lists for motor and pump, motor wiring diagram, and equipment lubrication recommendations. Delivery must occur within 9 months of contract award to Hoover Dam Central Warehouse in Boulder City, Nevada, on an FOB Destination basis. The contractor must comply with manufacturer's instructions for rigging, transporting, and storing units, protect equipment from physical damage, and coordinate delivery with the Contracting Officer Representative. All costs for submittals are included in the quoted price.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R3026Q0054.pdf | ||
| 140R3026Q0054_CSS.pdf | ||
| Brand_Name_Justification_Sump_Pumps_REDACTED.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ No.
140R3026Q0054
Project Title Central Section Sump Pump Replacement
Statement of Work
Replacement Central Section Sump Pumps for Hoover Dam
Background:
Hoover Dam is in need of two replacement HydroFlo Vertical Turbine pumps. Hoover dam currently has 3 locations for these pumps to be installed, two of which require replacement.
Scope:
The scope of this supply is the purchase of 2 sump pump assemblies that are interchangeable, in whole or in part, with the currently installed sump pumps. Interchangeability of the pumps is essential to ease of maintenance of the entire sump pumps system and eliminates the need to maintain larger stock of wear parts while also removing the risk of incorrect part installation during maintenance. These two pumps will be installed by government personnel.
Requirements:
The contractor shall supply 2 pump assemblies with the following characteristics (reference Hydroflo drawing number 36-346-16HH01WF-SBM as previously purchased by Hoover Dam, also may reference HydroFlo serial number TX36346-2 or TX36346-1):
• 16HH Single stage vertical turbine pump assembly
• 1.5” Head shaft assembly, 416 stainless steel, with 10TPI, Left Hand, bronze adjusting nut and key
• Coated steel motor stand; 16” 150# Flat Face Discharge Flange connection and separate base plate
• ~630” of 16” oil lube/water flush column assembly with 2.5”-12LH x 1.5” shaft water flush tube and shaft assembly; connections of column sections to be 16” 150# Flat Face flanges
• Underground style discharge
• 16HH oil lube/water flush bowl assembly with bell suction and flanged to discharge column
• External oil lube line for bowl assembly feed oil
• 304 stainless steel bolt on basket strainer
• All steel components coated with Tnemec N140, dry film thickness 6-8 mils
• 16HH impeller, impeller and collet made from 316 stainless steel
• 2300 V, 3 phase, 60 Hz, 150 HP, 1800 RPM 4 pole, continuous duty motor with
Wye-Delta start function and 447TPA frame size
Pump rated performance as follows:
• Flow: 5000 GPM (US)
• Head: 60 ft
• NPSHr: 18.6 ft max
Project Title Central Section Sump Pump
Submittals:
Contractor shall submit for Review/Approval the following documents:
1. General Pump Arrangement/Specifications Drawing
2. Pump datasheet with performance curves
3. Motor nameplate datasheet with motor performance data
4. Motor dimensions drawing
5. Coatings material datasheet
Submittal Requirements
1. Reclamation will have 14 calendar days to review each submittal.
2. Submittal documents shall include Purchase Order number and title, and submittal number and title.
3. The Contractor shall furnish all submittals to the COR electronically. Names and emails will be provided after award. Hard copies of drawings shall be submitted to the COR.
4. Reclamation will provide an electronic response to the Contractor for each submittal.
Submittals required for approval or acceptance will be returned either “approved” or “accepted” or “approved, subject to identified changes” or “accepted, subject to identified changes” or “not approved” or “not accepted”. Submittals not approved or accepted shall be revised and resubmitted. Any resubmittal will require another 14 calendar days of Reclamation review time.
5. All costs of furnishing the submittals shall be at the Contractor’s expense and shall be included in the quote.
Delivery:
Contractor shall provide the following for Shipping, Storage, & Protection:
1. Comply with manufacturer's installation instructions for rigging, unloading, and transporting units. Unit shall be stored and handled per manufacturer’s instructions.
2. Protect units from physical damage.
3. Shipped to:
Hoover Dam Central Warehouse Hwy 93 / St. Rte. 172 Boulder City, NV 89005
4. FOB Destination
Contractor shall submit for reference the following documents:
1. Equipment operation and maintenance manuals; provided with each assembly including instruction leaflets and instruction bulletins for the complete assembly and each major component
2. Overhaul/refresh parts and materials list for both motor and pump
3. Motor wiring diagram
Project Title Central Section Sump Pump
4. Equipment lubrication recommendations and specifications
Contractor shall deliver 2 pump assemblies with motors and discharge columns to the Hoover Dam central Warehouse within 9 months of contract award. Contractor shall coordinate delivery with the COR.