140R3025Q0115__Work_Statement_Pressure_Vessel_Recertification.pdf
PDF 208 KB Posted
- Attached to
- PRESSURE VESSEL RECERTIFICATION
- Solicitation number
- 140R3025Q0115
About this file
This is a Work Statement for Pressure Vessel Recertification issued by the Bureau of Reclamation (BOR) for the Hoover Dam. The document details the procurement of 62 pressure relief valves (PRVs) from various manufacturers including Anderson Greenwood Crosby, Circle Seal, JAYCO, Kingston, Kunkle, and one unknown manufacturer. The valves range in size from 1/4" to 2 1/2" with varying pressure settings (50-470 psi) and flow rates.
Key contract requirements include delivering all PRVs to the Hoover Dam Central Warehouse within 90 days of award, with strict specifications that all valves must be new, sourced from the original equipment manufacturer (OEM), and match exact size, pressure, and flow rate characteristics. Contractors must submit technical data sheets within 14 days of award for TPOC approval, provide a list of shipped parts, and follow a defined schedule. Payment will be a lump-sum price, with two-thirds paid upon parts purchase and the remainder upon successful delivery. The Technical Point of Contact is Tyrese Smith, and delivery is restricted to Monday-Friday, excluding specific federal holidays.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Statement - Pressure Vessel Recertification 1
Work Statement - Pressure Vessel Recertification
Department of the Interior
Bureau of Reclamation
LCDO - Hoover Dam
Author Note
See Reclamation Facilities, Standards, Instructions & Techniques (FIST) Manual, Volume 2-9 “Inspection of
Unfired Pressure Vessels”, which may be found at: https://www.usbr.gov/power/data/fist/FIST_2-9_(8-2022).pdf, and refer to ASME Code Section I and VIII for valve requirements https://www.usbr.gov/power/data/fist/FIST_2-9_(8-2022).pdf
Pressure Vessel Recertification 2
1. Background
The Hoover Dam utilizes many boilers and pressure vessels that require pressure relief valves (PRVs) to be operated safely. Hoover Dam requests an order of several dozen PRVs of various sizes and specifications to be delivered to the dam so that staff may have them installed throughout the powerplant and connected systems. The Bureau of Reclamation (BOR) is procuring these new PRVs to stay up to
ASME Boiler and Pressure Vessel Code (BPVC) and ensure the safety of all pressurized systems and personnel.
This document will include the size, pressure setting, flow rate, and original manufacturer of the currently installed valves the BOR needs for replacement. The contractors must ensure the specs of any valves they procure match exactly to those defined by the BOR. They are specific to the connected system and any deviations in these characteristics can lead to a failure in the valve or pressure vessel. Any exceptions to procuring an exactly matching characteristic will be discussed in the Part Requirements section.
Contractors will procure and delivery the specified valves to the Hoover Dam Warehouse for the BOR to receive. The BOR requires that all parts delivered by the contractor must be new and sourced from the
OEM (no refurbished parts will be accepted). The delivered PRVs shall be exactly to the specifications following the defined salient characteristics in Table 1 of the appendix.
2. Reference Standards
Refer to AMSE BPVC Section IV, VIII, and XIII when selecting valves.
3. Technical Point of Contact
Contractors will coordinate any technical issues through the Technical Point of Contact (TPOC) Tyrese
Smith via phone or E-mail at the following:
Phone: 702-494-2867
Email: tyresesmith@usbr.gov
4. Government Furnished Information, Assistance, and Facilities
The BOR will supply the following to contractor personnel:
1. A drop off area at the Hoover Dam Central Warehouse to park the delivery truck temporarily while the delivery is being unloaded and received.
2. Central Warehouse will have a forklift and forklift operator to unload bulk totes or pallets from the contractor’s transport vehicle if needed.
3. Cell phone service will be available while at the top of the dam and the Central Warehouse.
4. Restroom and wash-up facilities will be available to all contractor personnel.
Pressure Vessel Recertification 3
5. Part Requirements
The contractor shall obtain and deliver all the requested PRVs and ensure the valves follow the salient characteristics defined in Table 1 as follows:
1. All procured PRVs must have the exact size as listed in Table 1. The size refers to the inlet diameter measurement of the PRV.
2. All delivered PRVs must be new and sourced from the OEM (the BOR will not accept any refurbished or second-hand parts).
3. Contractor must ensure the valves they purchase have an exactly equal set pressure or an adjustable pressure range that includes the pressure specified by the BOR in Table 1.
4. Contractors must ensure the flow rate of the PRVs is at least the value in Table 1, using SCFM as the units unless stated otherwise. Valves with lower flow rates will not be accepted.
5. If there are any issues with sourcing a valve which meets all recommendations, submit inquiry to
Contracting Officer.
6. Delivery
All parts required under this contract for Hoover Dam shall be shipped to the following address:
Hoover Dam Central Warehouse
South U.S. Highway 93, SR 172
Boulder City, Nevada 89005
Deliveries will be accepted between 7:30 a.m. to 3:30 p.m., Pacific Time, Monday through Friday only. The vendor is required to include the cost of travel and delivery to the warehouse in their contract bid. The point of contact for delivery information is Hoover Dam Warehouse, (702) 494-2513. We will not be able to receive deliveries during the following federal holidays:
• New Year's Day (January 1).
• Birthday of Martin Luther King, Jr. (Third Monday in January).
• Washington's Birthday (Third Monday in February).
• Memorial Day (Last Monday in May).
• Juneteenth (June 19th).
• Independence Day (July 4).
• Labor Day (First Monday in September).
• Columbus Day (Second Monday in October).
• Veterans Day (November 11).
• Thanksgiving Day (Fourth Thursday in November).
• Christmas Day (December 25).
Pressure Vessel Recertification 4
7. Period of Performance
The period of performance for delivering these parts to Hoover Dam is 90 days from date of award.
Contractors must deliver all the required parts and submittals within this period of performance.
8. Submittals
8.1. Technical data of items to be purchased:
BOR requires the contractors to provide cut sheets or shop drawings (whichever is available) of the PRVs they intend to purchase to the TPOC for reviewing. The TPOC at Hoover must approve the selected valves before the contractor can purchase and deliver them. The technical data can be provided to the TPOC (refer to RSN 000 on page 6). A notice to proceed (NTP) to purchase the valves will be issued after approval of the valves.
8.2. List of all shipped parts
Contractors will make a list of all shipped parts, which must contain the ordered quantities, shipped quantities, item number, and description of the parts. Contractors will provide this list to the point of contact at the warehouse upon delivery to confirm if all the requested items are present. Multiple shipments are not allowed, the contractor must deliver all the requested items in a single delivery. This list will be used as the proof of purchase (refer to RSN 001)
8.3. Schedule
Contractors will provide a schedule of expected dates for when they will provide the technical data sheets, purchase the parts, provide a proof of purchase, and when the parts will be delivered to the Hoover Dam Warehouse. The schedule submittal can be referenced in RSN 003.
9. Payment
Payment: Lump-sum price. Payments will be provided as described in Table 2 on page 6, with two thirds off the payment provided once parts have been purchased and the rest of the payment provided upon successful delivery.
Pressure Vessel Recertification 5
10. Appendix
Table 1. Part Characteristics
List of requested parts including their original manufacturer and salient characteristics
Order # Quantity Manufacturer
Salient Characteristics
Size (in) Pressure
(psi)
Flow Rate
(SCFM)
1 4 Anderson Greenwood Crosby 3/4" 150 296
2 4 Anderson Greenwood Crosby 1/2" 357 460
3 2 Anderson Greenwood Crosby 3/4” 357 965
4 17 Anderson Greenwood Crosby 1” 300 567
5 2 Circle Seal 1” 250 1000
6 2 Circle Seal 3/8” 470 355
7 2 Circle Seal 1/2" 350 525
8 2 JAYCO 1” 50 202
9 2 JAYCO 2” 115 1435
10 1 Speedaire* 1/4" 153 71
11 1 Kingston 1/4" 200 162
12 1 Kingston 1/4" 250 358
13 6 Kunkle 1/2" 400 888
14 8 Kunkle 2” 150 4090
15 1 Kunkle 2” 135 6000 lb/hr
16 2 Kunkle 1” 357 2209
17 1 Kunkle 2 ½” 135 3734
18 3 Kunkle 1” 50 341
19 1 unknown 1/4" 125 116
*Speedaire was the manufacturer of the pressure vessel, which appears to have an integral PRV that may or may not be sold separately.
Pressure Vessel Recertification 6
Table 2. Price Schedule
Quan tity
Manufacturer and
Part Number
Salient Characteristics
Size
(in)
Pressure
(psi)
Flow
Rate
(SCFM)
Unit
Price
(ea)
Total
1 4
3/4" 150 296
2 4
1/2" 357 460
3 2
3/4” 357 965
4 17
1” 300 567
5 2
1” 250 1000
6 2
3/8” 470 355
7 2
1/2" 350 525
8 2
1” 50 202
9 2
2” 115 1435
10 1
1/4" 153 71
11 1
1/4" 200 162
12 1
1/4" 250 358
13 6
1/2" 400 888
14 8
2” 150 4090
Pressure Vessel Recertification 7
Quan tity
Manufacturer and
Part Number
Salient Characteristics
Size
(in)
Pressure
(psi)
Flow
Rate
(SCFM)
Unit
Price
(ea)
Total
15 1 2” 135 lb/hr
16 2
1” 357 2209
17 1
2 ½” 135 3734
18 3
1” 50 341
19 1
1/4" 125 116
Total
Table 3. Submittal Table
List of requested submittals with due dates and required recipients.
RSN Submittal Title Due Date
Recipient
CO COR TPOC
000 Technical Data Sheets Within 14 days after receipt of notice of award.
X
Proof of Purchase (List of shipped parts)
Within 14 days of NTP
X X
002 Schedule Within 7 days after receipt of notice of award, and update regularly X X X
File details come from the government source that posted it. Updated .