140R3023R0026_0002_Contract_Price_Schedule_0003.pdf
PDF 151 KB Posted
- Attached to
- Yuma Area Office Quarry Project
- Solicitation number
- 140R3023R0026
About this file
This document is a continuation of a price schedule for a federal contract solicitation to provide quarry services at the Ehrenberg Quarry. The contractor will be required to crush 1- to 4-inch material to gravel size totaling 20,800 tons, load, weigh, haul, and stockpile the gravel across 309,375 ton-miles to three designated stockpile sites. Additional services include maintaining access and haul roads, and roads inside the quarry by blading and watering. The contractor must also prepare and submit a Notice of Intent to the EPA. Pricing is provided on a per unit basis for the standard move-in, crushing, hauling and stockpiling, road maintenance, and EPA submittal. The total estimated quantity is provided for the crushing and hauling. The soliciting agency is the Department of the Interior Bureau of Reclamation for the Yuma Area Office Quarry Project under solicitation number 140R3023R0026.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Part B – Continuation of SF
Document No.
140R3023R0026/0002
Document Title Quarry Services for YAO at Ehrenberg Quarry
B-1
Continuation of Section B – Price Schedule
Ehrenberg Quarry
Item
No.
Service
Estimated
Quantity
Unit
Unit Price
Total Price
1-1
Standard move-in to designated quarry.
job $ $
1-2 Crush 1- to 4-inch material to gravel size 20,800 tons $ $
1-3
Load, weigh, haul, & stockpile gravel 529,886
309,375 ton-miles
1-4 Maintain access roads, and haul roads, that need blading, and watering. (Per miles) 1 mi. $ $
1-5 Maintain roads inside the quarry that need routine blading and water. (Per miles) 3 mi. $ $
1-6 Prepare and Submit NOI to EPA 1 Ea. $ $
Total Price $
Contractor will deliver the gravel as indicated in Item number 1-3 to stockpile site A120.8, 139.4 and A144.2.
Stockpile site A120.8 will have a total of 12,300 ton delivered to it, Stockpile site A139.4 will have a total of 4,250 ton delivered to it and Stockpile site A144.2 will have a total of 4,250 ton delivered to it.
Total tons of gravel delivered will be 20,800 tons out of the Ehrenberg Quarry.