This is an Amendment 001 to Solicitation 140R2026R0007 issued by the Bureau of Reclamation, Mid-Pacific Region for the Stampede Power Plant Switchgear Replacement project. The amendment incorporates a site visit agenda and sign-in sheet dated June 9, 2026, at 10:00 AM PDT and confirms that the proposal due date of 1700 PDT on June 27, 2026, remains unchanged. Offerors must acknowledge receipt of this amendment prior to the deadline by completing required forms, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers.
The solicitation is restricted to Total Small Business concerns under FAR Clause 52.219-6. The estimated project cost ranges between $250,000 and $500,000, and the Government intends to award a firm-fixed price construction contract without discussions. Principal work involves removing and replacing three existing switchgear enclosures and distribution panels: the DCA draw-out breaker enclosure with five breakers and associated equipment, the DCB molded case circuit breaker distribution panel, and panels D1A and DCC. Contractors must provide their own mobile generators and restroom facilities during the scheduled outage. The contract requires work to commence within 7 calendar days of Notice to Proceed and be completed within 150 calendar days thereafter. A post-award conference will be conducted via MS Teams. Davis-Bacon wage rates apply, and all questions must be submitted in writing by five days after the site visit with answers provided in writing to become part of the contract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Roxana Ahola
See continuation page
Bureau of Reclamation Mid-Pacific Region Regional Office Division of Acquisition Services 2800 Cottage Way, Room E-1815 Sacramento CA 95825-1898
R20
140R2026R0007
05/28/2026
05/28/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140R2026R0007/0001
A. TITLE: Stampede Power Plant Switchgear
Replacement
B. PURPOSE: The purpose of this amendment is to incorporate the attached site visit agenda and sign in sheet.
C. DESCRIPTION: This amendment hereby incorporates the following:
1) Site visit agenda and sign in sheet.
2) The proposal due date of 1700 PDT on June
27, 2026, remains unchanged.
| 140R2026R0007 (3) |
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
140R2026R0007 Site Visit Docs
File details come from the government source that posted it. Updated .