This document is a detailed utility service specification for electrical power requirements at multiple locations for the Klamath Basin Area Office (KBAO). The file lists 10 line items specifying electric service details for various pumping stations, dams, and facilities across California and Oregon, including No. 1, 2, and 3 Drainage Pumps, Lower Lake Road Merrill pumps, KBAO & Boat Barn/O&M Office, Wilson Dam, Pumping Plants E, EE, F, FF, A Canal, Keno Dam, Link River Dam, and Station 48. Each location has specific requirements for power type, including underground or overhead service, single or three-phase power, voltage specifications (primarily 240/480 or 2400 volts), and connection types, with most sites requiring underground, 60 cycle/hertz, alternating current electrical service.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2025Q0043.pdf | ||
| C5_5_Attach_3_Meter_Locations_Maps_C-J.pdf | ||
| C5_5_Attach_1_Site_Map_A.pdf | ||
| C5_5_Attach_2_Site_Map_B.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KBAO Pacific Power Utility Service – Updated 4/04/2025
Line Item
Description Account # Address Map Number
The type of electric service required by the Government is:
The normal delivery voltage shall be:
00010 Pumping Power to No.
1,2 and 3- Drainage Pumps, Sump
40470641-005-1, No. 2 Pump, 1.4 Mile S. Township Road, Worden, CA (AREA K)
12-201-5283 Attach 1 Site Map A
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-006-9, No. 3 Pump, 1.4 Mile S. Township Road, Warden, CA (AREA K)
12-201-5283 Attach 1 Site Map A
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-007-7, No. 1 Pump, 1 Mile S.
Township Road, Worden, CA (AREA K)
12-201-5283 Attach 1 Site Map A
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-015-0 Sump 3, Lot 8327 Washrack # 3, County Road 103, Tulelake, CA
12-201-5386 Attach2 Site Map B
[X] overhead [] underground, 60 cycle/hertz, [] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00020 Power to Lower Lake Rd Merrill
40470641-002-8 No. 4 Pump & C-1-1 pump, AREA K, OR
12-201-5283 Attach 1 Site Map A
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00030 Power to
KBAO &
Boat Barn/O&M Office
40470641-011-9, 6600 Washburn Way, Klamath Falls OR, 97603
Attach 3 - Map C (pg 1)
[X- historical meter # 237657730] overhead [X-historical meter # 16488548] underground, 60 cycle/hertz, [X] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[X] 120/240 [] 120/208 [] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-001-0 6600 Washburn Way, Klamath Falls OR, 97603
Attach 3 - Map C (pg 1)
[] overhead [X] underground, 60 cycle/hertz, [X] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[X] 120/240 [] 120/208 [] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
0040 Wilson Dam 40470641-013-5 Wilson Dam at Hill Road, Lost River
Attach 3 - Map H (pg 6)
[] overhead [X] underground, 60 cycle/hertz, [X] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[X] 120/240 [] 120/208 [] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00050 Power to Plant E & EE
40470641-004-4, Pumping Plant E, Klamath Falls, OR Attach 3 -
Map E (pg 3)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [] 240/480 [] 277/480 [X] 2400 [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-008-5 Pumping Plant EE, Hwy 97, Klamath Falls, OR
Attach 3 - Map E (pg 3)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [] 240/480 [] 277/480 [X] 2400 [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00060 Power to Plant F & FF
40470641-009-3, Pumping Plant FF, Ashland Star Rt Attach 3 -
Map F (pg 4)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [] 240/480 [] 277/480 [X] 2400 [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
40470641-010-1 Pumping Plant F, Klamath Falls, OR
Attach 3 - Map F (pg 4)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [] 240/480 [] 277/480 [X] 2400 [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00070 A Canal 40470641-004-4 A Canal Structures at 400 Nevada Street, Klamath Falls, OR
Attach 3 - Map D (pg 2)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00080 Keno Dam 40470641-027-5 Keno Dam on Green Springs Hwy 66, Keno, OR
Attach 3 – Map I (pg 7)
[X] overhead [] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [] 240/480 [X] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00090 Link River Dam
40470641-028-3 Link River Dam structure along the Link River Trail on Lakeshore Drive, Klamath Falls, OR
Attach 3 – Map J (pg 8)
[] overhead [X] underground, 60 cycle/hertz, [] single-phase [X] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta connected [] Wye-connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[X] 120/240 [] 120/208 [] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
00100 Power to Station 48
40470641-012-7 Station 48 at Henley Road, Lost River Attach 3 -
Map C (pg 1)
[X- historical meter # 237657730] overhead [X-historical meter # 16488548] underground, 60 cycle/hertz, [X] single-phase [] 3- phase, [] 2-wire [] 3-wire [] 4-wire, [] Delta-connected [] Wye- connected, alternating current. [Enter requirement for dual-feeder service, if justified.]
[] 120/240 [] 120/208 [X] 240/480 [] 277/480 [] [Enter other secondary and/or primary voltages, as appropriate], with an allowable variation of percent above or below normal. [Enter, if applicable, information on the maximum acceptable frequency and maximum duration of outages.]
File details come from the government source that posted it. Updated .