This document is an Amendment (Amendment 0001) to Solicitation 140R2025Q0007 for Endeavor Boat Repairs & Modifications issued by the Bureau of Reclamation's Mid-Pacific Region. The amendment extends the quote submission deadline from March 25, 2025, to April 1, 2025, at 3:00 PM PST, and provides detailed answers to 16 contractor questions about specific repair and modification requirements for the RV Endeavor vessel.
Key clarifications include specifications for propeller replacement (Michigan Wheel Dyna Quad or equivalent), roof access ladder materials and design (removable aluminum bottom half), painting instructions (cabin door and trim white, radar/anchor mast dark blue), and confirmation that propellers are to be a replacement set requiring installation. The amendment also indicates flexibility on contractor location if 2-way transport is included in the quote, and provides additional details about boat specifications such as beam width (16 feet), displacement (16 tons), and various repair/modification expectations for different boat components.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2025Q0007.pdf | ||
| C5_5_DOL_Wage_Determination_2015-5623_Rev_23.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2025Q0007 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
03/03/20250001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/03/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The purpose of this Amendment is to extend the quote due date by one (1) week from March
25, 2025 to 3:00 PM (PST) on April 1, 2025 and answer questions that have been asked about the requirement.
B. Q&As:
1. OBSOLETE THRU-HULLS - Can you clarify if these thru-hulls are in the hull bottom or hull sides?
Answer: These are on the hull sides.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Sherry L. Heibeck
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2025Q0007/0001
2. ROOF ACCESS LADDER -
A. Can you clarify whether the ladder should be built out of aluminum or stainless steel?
B. Based on my understanding, I fear that the bottom of the tread will be very high, making it hard to get on and off the ladder. Should the ladder not be built a little longer towards the deck to facilitate using it?
Answer: The intent is that the bottom half of the ladder be removable to save access to the life ring when the ladder is not in use. Aluminum would save weight being that it is removable.
3. The RFQ specifies using a Michigan Wheel Dyna
Quad propeller. I would like to know if we are able to supply a substitute propeller. ZF offers a comparable replacement that is a better-quality propeller than the Dyna Quad, at a better price point.
Answer: A substitute would be appropriate if you identify the material, so we can compare to the material used on the Dyna-Quad.
4. Can you provide clarify as to whether these
(propeller) are being supplied as a spare set, or if they are supposed to be installed, replacing the currently installed props. The RFQ does not specify.
Answer: The propellers are to be a replacement set and need to be installed.
5. Would you consider awarding the contract outside of the 60-mile radius if our price (with
2-way transport included in our proposal) beats the local offers? The USCG small Boats division has this written into their RFQs, so it is done elsewhere.
Answer: Reclamation is open to considering a contractor outside the 60-mile radius if the contractor includes 2-way transport in their quote.
6. What is the beam or width of the boat? Answer:
16 feet
7. What is the displacement or weight of the
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2025Q0007/0001 boat? Answer: 16 tons
8. What is the fixed height of the boat from keel to highest point on the cabin after removing any radars or masts. Answer: Reclamation does not currently have this information.
9. Starboard bulkhead-8 screws and cap to be removed?
Answer: Remove and fill holes. Black Cap is pass thru that scientists probably use. It will remain.
10. Handrail hardware-switch all to 316 stainless steel?
Answer: Remove roof handrail for painting and do not reinstall. Fill and fair holes. (The rail is a left over from when the boat was a fishing boat, does not really serve a purpose now. I should have specified that in the package)
11. Aft overhang - "painted masonry board with battens" to be replaced with marine grade head liner?
Answer: Yes, replace with marine grade material.
If teak strips are re-used, paint them white.
12. Radar/Anchor mast- to be painted? Blue? White?
Answer: Paint Dark Blue to match the hull color.
13. Non-skid both roof top levels-repainted to match the deck?
Answer: Nonskid on roof can be white to match cabin paint. Better for heat from sun.
14. New decals to be supplied?
Answer: Reclamation will have decals made and supplied.
15. Starboard cabin door-paint to match? Teak wood frame, paint or varnish?
Answer: Paint cabin door and teak trim white to match cabin.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2025Q0007/0001
16. Expectation of fairing on the cabin? Is textured right now.
Answer: Some fairing would be nice, but not
"Yacht Quality", perhaps one pass of fairing to take out deep valleys.