This document contains a pricing schedule for tasks required to develop a temperature modeling system within the CEQUEL W2 Modeling Platform for the Bureau of Reclamation's Central Valley Operations Office. The contractor will be required to complete 17 tasks, including developing a work plan, data management plan, model framework, conducting stakeholder outreach, model selection, data development, model calibration and validation, documentation, uncertainty analysis, and a peer review process. Task deliverables will include technical memorandums, reports, datasets, source code, visualization tools, and trained personnel. Pricing is included on a task-by-task basis, with the total price to be proposed by the bidder. The solicitation is seeking to develop models and tools to help manage reservoir temperatures to meet operational goals.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2020Q0064_Amd_0001.pdf | ||
| Attach 5 Revised PWS Temp Model Development Rev August 2020_0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140R2020Q0064 Amendment 0001
Attachment 4
Item Number Schedule of Services Quantity Unit
Unit Price Total Price
0010 Task 1: Project Work Plan 1 Each $ $
Final Phase I schedule, with technical memorandum on workplan for each task. See Performance Work Statement for specific information.
0020 Task 2: Stakeholder Involvement and Outreach 1 Each $ $
Contractor shall produce and distribute meeting materials and notes for each group meeting, keep a running list of identified action items or issues to be addressed, and document the development of the community participation plan and supporting records of all meetings, training sessions, etc. summarized in the technical memorandum. See Performance Work Statement for specific information.
00030 Task 3: Develop Reclamation’s Institutional Knowledge 1 Each $ $
Contractor shall produce brief and relevant training material to support Reclamation’s development of institutional knowledge for future model development and application. See Performance Work Statement for specific information.
0040 Task 4: Data Management 1 Each $ $
Contractor shall develop a data management plan and data storage system. Contractor shall document the development of the data management plan in a technical memorandum. See Performance
0050 Task 5: Model Framework Design & Refinement 1 Each $ $
Contractor shall document in a technical memorandum the description of the modeling framework of reservoir models, including network, inputs, selective withdrawal, temperature curtains, etc. and facility representations necessary to achieve temperature management goals. See Performance Work Statement for specific information.
0060 Task 6: Model Selection Design 1 Each $ $
After consultation and agreement with Reclamation, model selection shall be documented by contractor in a technical memorandum See Performance Work Statement for specific
0070 Task 7: Data Development 1 Each $ $
For each model, contractor shall deliver a description of the model input requirements. For each model input requirement, contractor shall deliver datasets, data sources, data retrieval mechanisms, and metadata/documentation. Contractor shall document the data collection process for all data sources, metadata, and automated mechanisms for data retrieval and/or quality control in a technical memorandum. Contractor shall provide a data package of all data collected. Contractor shall provide a recommendation for additional data monitoring which would improve modeling performance. See Performance Work Statement for specific
0080 Task 8: Model Development 1 Each $ $
Records on iterative improvements, interim model products with version control, final calibrated models, and final calibration document shall be summarized and documented in a technical memorandum by the contractor. See Performance Work Statement for specific information.
0090 Task 9: Calibration, Validation and Sensitivity 1 Each $ $
Calibrated models, source code, documentation of results of calibration and validation tasks, and potential inclusion of results of tasks into uncertainty estimation procedures for framework shall be provided, summarized, and documented by contractor in a technical memorandum. Updates on calibration shall be provided in Modeling Technical Committee meetings. See Performance
0100 Task 10: Documentation Phase I 1 Each $ $
Contractor shall produce Phase I report, in a consistent format, of each component of system, to be included in overall documentation of the framework.
Total Price Proposed $
0110 Task 11: Phase II Workplan 1 Each $ $
Contractor shall produce final Phase II schedule, with a technical memorandum on the workplan.
0120 Task 12: Implementation 1 Each $ $
Contractor shall provide reservoir models developed to application stage and model documentation including a User’s Guide, as well as a technical memorandum outlining procedures for model comparison, data utilized, linkage of models (modeling framework), results of comparison among models, and recommendations for future activities. Contractor shall provide source code of application models.
0130 Task 13: Estimation of Uncertainty – Sources 1 Each $ $
Contractor shall document potential sources of uncertainty in individual datasets/modeling components in a technical memorandum.
0140 Task 14: Estimation of Uncertainty – Protocols 1 Each $ $
Contractor shall document estimates/estimation procedures for estimating uncertainty in individual datasets/modeling components and mechanisms for translating uncertainty to model results in a technical memorandum.
0150 Task 15: Output Communication 1 Each $ $
Communication/visualization tools and presentation methods/venues shall be produced and documented by the contractor.
0160 Task 16: Documentation Phase II 1 Each $ $
Contractor shall produce Phase II report, in a consistent format, of each component of system, to be included in overall documentation of the framework.
0170 Task 17: Peer Review 1 Each $ $
Contractor shall make documentation available for peer review and shall provide summary/documentation of peer review on model components/datasets to Reclamation.