AMD_0003_0003.pdf

PDF 1 MB Posted

Attached to
Grand Coulee Luminaires Replacement
Solicitation number
140R1024B0003
Issued by

About this file

This document appears to be technical specifications and related information for a federal contract opportunity to replace interior luminaires at the Nathaniel Washington Powerplant.

The key details are:

  • The work involves removing and replacing existing interior high-bay metal halide fixtures with new LED luminaires, as well as removing, cleaning, and reinstalling T-beam joint spall containment covers and general powerplant cleaning.
  • The contract is amendment 0003 to the Nathaniel Washington Powerplant Luminaire Replacement project under the Columbia Basin Project in Washington.
  • Relevant sections cover the summary of work, work restrictions, submittal requirements, contractor safety personnel, temporary utilities, use of government equipment, and project record documents.
  • Pricing is provided through lump sum items in the Price Schedule.
  • The contracting agency is the Department of the Interior Bureau of Reclamation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SERVICE CENTER

WRITTEN SPECIFICATIONS SIGNATURE SHEET

Specifications Title:

Project Title:

Region:

Prepared: P.E.

Technical Approval: P.E.

Certified: P.E.

AMD/MOD

No.

Technical Approval Signature:

P epared By Signature:

Revised Specifications

LUMINAIRE REPLACEMENT

NATHANIEL WASHINGTON POWER PLANT

NORTHWEST REGION 9

AMD 0003

MICHAEL VON BUHR Digitally signed by MICHAEL VON BUHR Date: 2024.04.26 13:17:34 -06'00'

Digitally signed by DAVID

SALINAS

Date: 2024.04.26 14:54:24 -06'00'

GERALD HORTON Digitally signed by GERALD HORTON Date: 2024.04.29 16:59:47 -06'00'

Price Schedule, 01 11 00, 01 14 12, 01 33 00 01 35 30, 01 51 00, 01 54 00, 01 78 30, 02 41 07, 05 50 00

Nathaniel Washington Powerplant Luminaire Replacement Columbia Basin Project, Washington Amendment No. 0003

Price Schedule (Revised)

B - 2

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

6 05 50 00 Miscellaneous Metalwork (anchors)

For the lump sum of $

7 26 51 10 Interior Luminaires For the lump sum of $

TOTAL FOR PRICE SCHEDULE $_________________

OPTIONAL PRICE SCHEDULE 1

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1-1 26 51 10 Reuse Interior Luminaires Components

For the lump sum of $

TOTAL FOR OPTIONAL PRICE SCHEDULE 1 $_________________

TOTAL FOR PRICE SCHEDULES $_________________

END OF SUPPLIES OR SERVICES AND PRICES/COSTS

Summary of Work (Revised)

01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at Grand Coulee Dam Nathaniel Washington Powerplant, adjacent to the cities of Grand Coulee and Coulee Dam, Washington, approximately 90 miles west of Spokane, Washington, Okanogan County.

1.02 SUMMARY OF WORK

A. Remove and replace existing interior high-bay metal halide fixtures with new light emitting diode luminaries.

1. Remove the existing metal halide fixtures in high bay and below observation bridge.

2. Disassemble metal halide fixtures and dispose of in accordance with Section 01 74 00 – Cleaning and Waste Management and Section 02 41 07 – Removal and Disposal of Debris and Cleaning.

3. Furnish and install new LED luminaires in high bay and below observation bridge.

B. Remove, clean, and reinstall The Powerplant’s roof T-beam joints spall containment covers.

1. Remove 29 gauge. coated steel spall covers between each “T” section joint. After cleaning any debris encountered behind the covers reinstall the covers using new anchors in existing holes. Photographic documentation of any damage to the existing roof T-beams currently concealed by the 29-gauge steel plates.

a. There are 146 locations each with a length of approximately 106 linear feet per location, with 8 of these locations containing a flexible duct seal and an expansion joint material.

b. Replace all plastic anchors.

C. Powerplant cleaning.

1. Remove and dispose of existing debris and cleaning of the identified areas and equipment. See drawings and photographs for reference.

1.03 SPECIFICATION REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

Summary of Work (Revised)

01 11 00 - 2

B. Imperative statements in these specifications are Contractor Requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.

1.04 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Work Restrictions (Revised)

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 WORK RESTRICTIONS

A. Due to security, the Contractor will only be allowed on site when an authorized Government representative, (i.e. Government inspector), is available.

B. Allowable constructions periods.

1. Work hours are 6:00 am to 7:00 pm Monday through Friday, unless otherwise approved by COR.

2. Night work shall be approved by COR with a 72-hour advance notice.

C. Restrict material deliveries and removal of materials from jobsite to 6:30 am to 2:30 pm, Monday through Thursday unless approved by COR.

1. Material deliveries and removal of materials from jobsite not allowed on weekends and holidays.

2. Material deliveries require inspections by the Government before being allowed onsite. Coordinate deliveries with COR 48-hours in advance to avoid unanticipated delays during deliveries.

D. Alternate work schedules including weekends and holidays may be allowed as approved by COR. Provide COR a written notice 72 hours in advance of proposed alternate work schedule for review and approval.

E. No construction or other onsite work during Federal Holidays shall be allowed.

F. Contractor to schedule work around annual Grand Coulee Dam Laser Light Show.

1. Coordinate work hours with COR to avoid disrupting the laser light show.

2. Show dates and Times:

a. Saturday of Memorial Day Weekend to July 31st at 10:00 P.M.

b. August 1st to August 31st at 9:30 P.M.

c. September 1st to September 30th at 8:30 P.M.

Submittals (Revised)

01 33 00 - 2

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement Units: US Customary Units.

C. Drawings:

1. Minimum Identification in Title Block:

a. Contract number and title.

b. Contractor or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Final Drawings:

a. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

6. Final Electronic Drawings: Final electronic drawings are required:

a. Drawing format: AUTOCAD, Version 2021 or later, or as approved by the

COR.

b. Compile using ‘eTransmit’ utility in AutoCAD.

c. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

d. Electronic files: On CD, DVD discs or other Government approved electronic media.

e. Original plots: D size (22 inches by 34 inches).

f. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

01 33 00 - 8

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

1 Release of claims (1452.204-70)

Release of claims (DI-137) against United States

After completion of work and prior to final payment

I CO 1

1 0

2 Payroll and Basic Records (52.222-8)

Certified payrolls Weekly for each week any contract work is performed on site

I COR CDMS

3 Labor standards data (52.222- 11)

(1) List of subcontractors

(2) Statement and Acknowledgment Form (SF-1413) for each subcontract

Within 14 days after Notice to Proceed (NTP), and within 14 days after award of any subcontract

I COR 1 1 0

4 Equal opportunity (52.222-26)

Information required by Executive Order

11246 (SF-100)

Within 30 days after

NTP

I COR 1 0 0

5 Bonds / Insurance (52.222-15)

Performance and payment bonds

Within 10 calendar days after award

I CO 1 0 0

6 Liability Insurance (1452.228-70)

Acceptable evidence showing that insurance has been obtained

Within 10 calendar days after award

A CO 1 0 0

7 Estimate of Percentage of Recovered Material Content of

EPA-

Designated Items (52.223-9)

Estimate the percentage of the total recovered material content for EPA designated item(s) delivered and/or used in contract performance

On completion of the contract (no later than with submittal of final voucher)

I COR CDMS

8 Security Requirements

(WBR

1452.237-80)

Security Program Submitted and approved at least 28 days before mobilization

A COR CDMS

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

At least 28 days before use of Government land

A COR CDMS

01 33 00 - 9

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 14 30-1 Interruption of Service

Interruption of Service Request

At least 14 days before interruption of service

I COR CDMS

01 31 19-1 Project Management and Coordination

Weekly Progress Meeting Minutes

Weekly I COR CDMS

01 31 30-1 Contract Document Management System

Approval Data Within 14 days after issuance of the NTP

A Y COR 1 1 1

Via email

01 31 30 -2 Contract Document Management System

Final Data Within 21 days after completing the work

A COR 1 1 1

Via email

01 32 10-1 Construction Program

Representative Information

Within 7 days after receipt of NTP

A COR Via email

01 32 10-2 Construction Program

Baseline Schedule Within 10 days after receipt of NTP

A COR Via email

01 32 10-3 Construction Program

Updated Schedule:

(1) Blackline prints

(2) Reports

With monthly requests for progress payments

A COR CDMS

01 32 10-4 Construction Program

Time Impact Analysis

(1) Blackline prints

(2) Reports

Within 28 days after the Contracting Officer directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract

A COR CDMS

01 35 10-1 Safety Data Sheets

Complete LHM and

SDS

At least 28 days before starting on site work

I COR CDMS

01 33 00 - 10

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 35 10-2 Safety Data Sheets

Updated LHM and

SDS

At least 14 days before jobsite delivery of each hazardous material

I COR CDMS

01 35 20-1 Safety and Health

Emergency Action Plans Written Program and Training Records

Submitted and accepted before starting onsite work.

See Section 3 of

RSHS.

A Y COR CDMS

01 35 20-2 Safety and Health

Proposed Job Hazard Analysis (JHA) Template

At least 28 days before beginning on site work.

A COR CDMS

01 35 20-3 Safety and Health

Job Hazard Analyses (JHAs) and Exposure Assessments (EAs)

At least 14 days before performing work

I COR CDMS

01 35 20-4 Safety and Health

Safety Inspection Records

Daily I COR CDMS

01 35 30-1 Contractor’s Onsite Safety Personnel

Qualifications Within 14 days after receipt of Notice to Proceed

A COR Via email

01 35 30-2 Contractor’s Onsite Safety Personnel

Safety Inspection Reports

At least once each week

I COR CDMS

01 46 00-1 Quality Procedures

Contractor Quality Control Plan (QC)

At least 28 days before starting onsite work

A COR CDMS

01 46 00-2 Quality Procedures

Contractor’s Daily Report

Weekly when onsite A COR CDMS

01 46 00-3 Quality Procedures

Quality Control Supervisor (QCS) Resume

At least 35 days before starting onsite work and prior to submission of RSN 01 46 00-1

A COR CDMS

01 46 00-4 Quality Procedures

Contractor’s Quality Testing Plan

At least 28 days before starting onsite work

A Y COR CDMS

01 46 00-5 Quality Procedures

Summary of Monthly Test Results

Monthly A COR CDMS

01 33 00 - 11

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 54 00-1 Use of Government Cranes and Tools

Crane Operator Qualifications

At least 28 days before beginning onsite work

A COR CDMS

01 54 00-2 Use of Government Cranes and Tools

Crane Use Schedule Monthly I COR CDMS

01 55 00-1 Vehicular Access and Parking

Temporary Site Access and Parking Plan

At least 28 days before starting onsite work

A COR CDMS

01 56 10-1 Protection of Existing Installations

Plan for Protecting Existing Installations and Terrazzo Flooring

At least 28 days before starting onsite work

A Y COR CDMS

01 56-10-2 Protection of Existing Installations

Survey of Existing Concrete and Terrazzo Flooring

At least 28 days before starting onsite work

A COR CDMS

01 57 30-1 Water Pollution Control

Water Management Plan

At least 28 days before starting onsite work

A COR CDMS

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

At least 28 days before starting onsite work

A COR CDMS

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Within 5 days of waste disposal

I COR CDMS

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume

At least 28 days before beginning environmental assessment

I COR CDMS

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment

Within 14 days of completion of work

I COR CDMS

01 78 30-1 Project Record Documents

As-built Drawings Within 7 days of completion of work.

A Y COR 0 1 0

01 78 30-2 Project Record Documents

Shop Drawings At least 28 days before beginning work

A Y COR 0 1 1

01 33 00 - 12

Table 01 33 00A - List of Submittals

* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -

Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates

Technical Service Center

RSN

Clause or

Section Title

Submittals required

Due date or Delivery time

Type

CP

Respon-sible code

No. of sets to be sent to: ***

CO COR TSC

01 78 30-3 Project Record Documents

Final Drawings Within 14 days following approval of RSN 01 78 30-1, As-built Drawings

A Y COR 0 1 1

01 78 30-4 Project Record Documents

O&M Manuals Within 7 days of completion of work

A Y COR CDMS

0 1 1

01 78 30-5 Project Record Document

Extra Materials Within 7 days of completion of work

A COR CDMS

0 1 1

01 78 30-6 Project Record Document

Electronic Media Release Form

Within 7 days of

NTP

I CDMS

02 41 07-1 Removal and Disposal of Debris, and Cleaning

Removal and Disposal of Debris, and Cleaning Plan

At least 42 days before removal of debris and cleaning starts

A COR CDMS

26 51 10-1 Interior Lighting

Approval Data At least 28 days prior to purchasing components

A Y COR CDMS

26 51 10-2 Interior Lighting

Measurement and Verification (M&V) Plan

At least 28 days before starting onsite work

A Y COR CDMS

26 51 10-3 Interior Lighting

Measurement Report

Within 7 days of completion of test

A Y COR CDMS

26 51 10-4 Interior Lighting

Verification Report Within 7 days of completion of test

I Y COR CDMS

Contractor’s Onsite Safety Personnel (Revised)

01 35 30 - 1

SECTION 01 35 30

CONTRACTOR’S ONSITE SAFETY PERSONNEL

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/safety/rshs/index.html

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 35 30-1, Qualifications:

1. Contractor’s Part-time Onsite Safety Representative.

C. RSN 01 35 30-2, Safety Inspection Reports:

1. Prepare detailed monthly safety inspection reports listing noted deficiencies, digital photos, abatement dates and follow-up action for all jobsite activities.

2. Inspection report shall include findings of jobsite walk-through with Government representative.

1.04 QUALIFICATIONS

A. Contractor’s Part-time Onsite Safety Representative:

1. Competent supervisory employee with current safety and health related training, experience and duties on at least three projects of similar nature, size, complexity, and work to be performed as the current project

2. OSHA Construction 30-Hour Training Course including applicable elective subjects, for example Confined Space Entry; Cranes, Derricks, Hoists, Elevators, and Conveyors; Ergonomics; Fire Protection and Prevention; Materials Handling, Storage, Use and Disposal; Signs; Signals and Barricades; Powered Industrial Vehicles; Safety and Health Programs; Scaffolds; Steel Erection; Tools - Hand and Power; Welding and Cutting. Current first aid CPR certification.

01 35 30 - 2

3. Include resume with current telephone numbers of references, description of safety representative responsibilities, and copies of training certifications.

1.05 APPLICATION

A. Designate an employee as the Contractor’s Part-time Onsite Safety Representative prior to start of construction.

1. Safety requirements may be met by retaining appropriate level of services of an acceptable safety consultant.

B. Contractor’s Part-time Onsite Safety Representative Authorities, Duties, and Responsibilities:

1. Responsible for effectively implementing the Contractor’s Safety Program.

2. The Safety Representative shall coordinate all emergency response activities.

3. Recommend controls for observed hazards or predicted hazards.

4. Full authorization to correct unsafe acts on the spot, including the authority to stop work to correct safety and health problems.

5. Lead weekly safety meetings at the jobsite.

6. Onsite, during any and all construction activities.

7. Assemble, review, and sign each Job Hazard Analysis (JHA).

a. Review of JHA with employees.

8. Verify the correct use of respiratory protection and personal protective equipment.

9. Conduct and prepare weekly safety inspections in conjunction with the onsite government representative listing noted deficiencies, their abatement dates, follow up action. The report shall be available for review onsite.

10. Provide direct oversight and assemble a detailed report of all incident reviews, near-misses, accidents, and emergency response or rescue actions.

11. The Onsite Safety Representative may have other non-safety duties not to exceed 50% of their time.

1.06 QUALITY ASSURANCE

A. Contractor’s Part-time Onsite Safety Representative:

1. The effectiveness of the Contractor’s Part-time Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the COR.

2. Should the Contractor’s onsite safety representative’s effort be deemed insufficient the Contractor may be required to provide the services of a qualified, full-time safety and health representative at no additional cost to the Government.

01 35 30 - 3

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Temporary Utilities (Revised)

01 51 00 - 1

SECTION 01 51 00

TEMPORARY UTILITIES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Institute of Electrical and Electronics Engineers (IEEE)

1. IEEE C2-2023 National Electrical Safety Code (NESC)

B. National Fire Protection Association (NFPA)

1. NFPA 70-2020 National Electrical Code (NEC)

1.03 TEMPORARY ELECTRICITY

A. Electric power of limited capacity will be available for work to be performed under these specifications.

1. Single-phase 120-volt power is available at existing receptacles.

a. Verify locations with COR.

B. Provide required electric power for construction other than 120-volt power.

C. Comply with IEEE C2 clearances and spacing for temporary communications and supply lines and NFPA 70.

D. Remove temporary equipment and facilities upon completion of work under this contract.

1.04 TEMPORARY WATER

A. Government can provide water from its service water system within the Plant. It will be available for construction purposes.

1. Contractor shall provide their own potable water.

2. Service water shall be provided to the contractor for cleaning purposes. Service water minimum pressure: Typically 70 to 125 pounds per square inch.

3. Make arrangements with the COR for use of water.

4. The COR will designate locations from which water may be obtained.

5. No charge will be made for water obtained from this source.

Use of Government Crane and Tools (Revised)

01 54 00 - 3

Category and Type of Cranes

Number of Hours of Actual Crane Operating

Experience

Number of Hours of Crane Related Experience

Overhead Cranes:

(a) Cab Operated 40 Hours 40 Hours

(b) Pendant/Remote 40 Hours 40 Hours

Hours of actual crane operating experience: Time while the operator is at the controls of the crane; and/or has direct control of that crane; and/or a combination of operating hours within the same crane type.

Note: Additional actual crane operator experience may account for crane related experience.

Hours of crane related experience: Time as a signalman/bellman, oiler, crane mechanic, crane inspector, formal classroom training, crane simulator operation, and a combination of operating hours on other categories of cranes.

3. Drug Testing: Crane operators shall be subject to drug testing. Within 7 days after Government requests random test, submit documentation for each crane operator of a substance abuse test. In the event of a crane operating incident involving personnel injury or death, or damage to the crane or equipment; submit a substance abuse test immediately. Substance abuse testing shall be conducted by a recognized laboratory.

4. Orientation: Contractor crane operators shall participate in orientation of each crane with the Government before operating. Expected length of orientation is 4 hours.

B. Before use of a crane on each shift, the Contractor’s crane operator shall inspect the crane and complete Government’s crane inspection form. The crane inspection shall be entered in the crane’s logbook and the completed crane inspection form shall be provided to the

COR.

C. Crane use shall comply with ASME B30.2 and 29 CFR 1910.

D. Except for special tools provided, the Contractor shall provide slings, shackles, and rigging required for use with the crane.

1.08 SCHEDULING

A. Make written request for each use of Government crane to COR at least 5 days before crane is required.

Project Record Documents (Revised)

01 78 30 - 2

1. Drawings shall be provided in Adobe Acrobat (.pdf) format.

D. RSN 01 78 30-3, Final Drawings:

1. Final Drawings prepared from certified as-built drawings.

E. RSN 01 78 30-4, O&M Manuals

1. Provide O&M manual for the lighting fixtures.

a. Provide in both hardcopy and electronic form.

b. Number of hard copies as indicated in Section 01 33 00 – Submittals.

F. RSN 01 78 30-5, Extra Materials:

1. List of extra materials.

G. RSN 01 78 30-6, Electronic Media Release Form, Upon Request.

1. Refer to Article 1.04 Electronic Drawings below.

1.04 ELECTRONIC DRAWINGS

A. CADD Files, including template, will be distributed upon request, after:

1. Notice to Proceed.

2. Contractor signs form in Section 51 00 50 – Electronic Media Release.

1.05 AS-BUILT DRAWINGS

A. Provide and maintain 1 set of full-size prints of Government informational contract drawings marked to show accurate and complete records of as-built conditions. Keep drawings at the jobsite and mark as work progresses.

B. Use standard drafting practice to represent changes and include supplementary notes, legends, and details necessary to clearly portray as-built construction.

C. Mark as-built drawings in the following colors:

1. Red - Additions to original drawings.

2. Green - Deletions to original drawings.

3. Blue - Notations necessary for explanation of as-built markings.

D. Allow the Government to review the drawings at all times.

E. At the completion of work:

1. Submit As-built Drawings to COR for review and acceptance.

a. One set will be maintained by Government.

Removal and Disposal of Debris and Cleaning (Revised)

02 41 07 - 7

Photo 8: Bridge Crane Photo 9: Rahco Crane

8. (Photos 8 and 9) Bridge Cranes and Rahco Crane: There are three powerplant bridge cranes; two 275-ton capacity cranes, see informational drawings 1222-D-1323 and 1222-M-D-19-526, -527, -528, and one 50-ton capacity crane, see informational drawings 1222-D-1322 and 1222-M-D-19-428. The cranes span the entire width of the powerplant. Additionally, there is a 2000-ton capacity Rahco crane, below the bridge cranes, that spans the width of the powerplant. The top surfaces of these cranes have accumulated debris and stains from water and hydraulic oil leaks. The tops of the cranes shall be thoroughly vacuumed to remove all dust, dirt, foam, and other debris. The cranes and trolley catwalks shall then be cleaned using a water and soap solution to remove all stains. The cleaning is limited to the tops of all surfaces and does not include any vertical or bottom surfaces unless cleaning solution runs down any vertical surface. Those areas shall than be wiped down to ensure a uniform appearance is restored. Final surface appearance shall be uniformly clean.

9. (Photo 9): Rahco Crane.

02 41 07 - 10

Photo 14: Architectural Ledge

14. (Photo 14): Architectural Ledge (Photo 14). There are 34 sloping architectural ledges throughout the powerplant, see Informational drawings 1222-D-381, -382 and -384. These ledges are within easy reach from the main floor. Vacuum all 34 locations to removal all dust, foam, and debris.

Photo 15: Debris example on Top side of Sheet metal Cover

15. (Photo 14): Precast tee roof beam joints and behind the 29ga Sheet Metal Covers.

There are 146 Locations with a 29 ga Sheet Metal Covers. Cleaning behind the additional 8 locations at expansion joints will only occur where failed anchors are replaced per specification Section 05 50 00 – Metal Fabrications. Removal and re-installation of the covers per specification Section 05 50 00 – Metal Fabrications. After removal of covers vacuum up loose debris between where the concrete T-beams meet. Any damage found to the concrete T-beams shall be documented with photos to show the extent of the existing damage (if any).

Those photographs shall be numbered to indicate which plate (south to north starting with 1) and distance in linear feet from the west wall. These photos shall be turned over to the Government for use in future monitoring of the condition

02 41 07 - 11 discovered. Before re-installation of covers also clean, contain, and dispose of any debris behind cover. Covers are located where each T-beam joins to another as seen on informational drawings 1222-D-1126 and 1222-D-1127. Accessibility to the covers is outlined in article 1.04 B of this specification.

Photo 16: Scissor Lift and Scissor Lift Fabricated Platform

16. (Photo 16): Scissor lift and scissor lift fabricated platform.

17. Once surfaces are cleaned with the soap and water solution, rinse clear with clean water.

B. Accessibility:

1. The parapet ledge, drain lines, air handling units, precast tee roof beam sheet metal covers, and high bay lights are accessible using the two scissor lifts mounted upon bridge crane 1 or the scissor lift mounted upon crane 4, (see Photo 16). However, the NE, NW, and SE corners are only accessible with the use of a 125-foot boom lift. The SW corner and areas adjacent to the observation deck are accessible via the observation deck. The 125-foot boom lift must be equipped with exhaust scrubbers (MSHA compliant) to be used in the powerhouse.

a. Previous contractors have hoisted an electric scissor lift onto the Eagles nest (exterior viewpoint on west face of the powerplant) for use to access the parapet wall ledges in that portion of the powerplant.

Metal Fabrications (Revised)

05 50 00 - 1

SECTION 05 50 00

METAL FABRICATIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Miscellaneous Metalwork (spall containment covers):

1. Payment: Lump sum price offered in the Price Schedule.

a. Includes: Removal of coated steel 29 ga. sheet metal spall containment covers, oversizing holes on one side along covers length, and re-installation of the spall containment covers utilizing new anchors and hardware.

1) Removing existing plastic anchors from concrete and installing a new anchor in existing hole.

b. Exclude removal of the sheet metal covers at expansion joints consisting of 8 locations each at 106 liner feet in length. These locations can be identified where the sheet metal covers also include a flexible duct seal tape. The covers at these 8 locations will not be removed.

B. Miscellaneous Metalwork (anchors):

1. Deleted

2. Payment: Lump sum price offered in the Price Schedule.

a. Includes: Removal and reinstallation of a failed anchor anywhere along the 8 expansion joint locations.

b. Include inspecting the expansion joint covers to identify failed anchors to identified to be replaced.

C. Cost:

1. Include cost of cleaning loose debris while replacing the failed anchors in price offered in the Price Schedule for Removal and Disposal of Debris, and Cleaning.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME B1.1-2019 Unified Inch Screw Threads (UN and UNR Thread Form)

B. ASTM International (ASTM)

1. ASTM A 385-22 Providing High-Quality Zinc Coatings (Hot-

Dip)

2024-10-24T09:20:40-0600
DAVID SALINAS
2024-10-24T10:41:23-0600
BYRON VAN ORDEN

File details come from the government source that posted it. Updated .