C__Amendment_2_specification_changes_(1)_0002.pdf
PDF 18 MB Posted
- Solicitation number
- 140R1023R0001
About this file
This document provides details for a federal solicitation to modernize turbines and replace turbine runners at the Anderson Ranch Dam. The solicitation number is 140R1023R0001 issued by the Department of the Interior Bureau of Reclamation for the Anderson Ranch Dam Turbine Modernization and Runner Replacement project. Interested offerors are sought to modernize existing turbines and replace turbine runners to improve operational efficiencies at the hydroelectric power plant. The due date for initial proposals was not specified. The document includes specification changes for the project but does not provide pricing, award timing, or other contractual terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Anderson Ranch Powerplant Turbine Modernization and Runner Replacement Boise Project, Idaho Amendment No. 0002
Table of Contents (Revised)
DIVISION 09 - COATINGS
09 96 20 Coatings
DIVISION 22 – PLUMBING
22 10 04 Removal of Bearing Oil Coolers 22 11 86 Bearing Oil Coolers
DIVISION 48 - ELECTRICAL POWER GENERATION
48 13 00 Hydropower Project Information 48 13 01 Hydraulic Design 48 13 02 General Mechanical Evaluations 48 13 03 General Testing Methods 48 13 04 Disassembly and As-found Readings 48 13 05 Onsite Machining 48 13 07 Reassembly and Alignment 48 13 08 Commissioning 48 13 09 Critical Connection Fasteners 48 13 10 Vertical Francis Turbine Runner 48 13 11 Turbine Shaft 48 13 14 Shaft Sleeve 48 13 15 Packing Box Refurbishment 48 13 16 Turbine Guide Bearing 48 13 17 Generator Bearings 48 13 18 Rebabbitt Bearings 48 13 20 Headcover Rehabilitation 48 13 21 Bottom Ring Rehabilitation 48 13 22 Facing Plates and Wicket Gate End Seals 48 13 23 Stationary Wear Rings 48 13 25 Wicket Gates 48 13 26 Wicket Gate Levers and Links 48 13 27 Shear and Linkage Pins 48 13 28 Bushings and Bearings 48 13 29 Operating Ring 48 13 30 Servomotors 48 13 35 Discharge Ring 48 13 43 Brake and Jack System 48 13 44 Bearing Brackets
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Photographs
Table of Contents (Revised)
51 00 20 Assessment Reports 51 02 82 Hazardous Materials Survey and Analytical Results
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
Price Schedule (Revised)
B - 2
PRICE SCHEDULE A - UNIT 2
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
A-1 1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
A-2 01 31 30 Contract Document Management System
For the lump sum of $
A-3 48 13 00 Turbine Modernization and Runner Replacement
For the lump sum of $
TOTAL FOR PRICE SCHEDULE A $_________________
PRICE SCHEDULE B - UNIT 1
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
B-1 2 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
B-2 48 13 00 Turbine Modernization and Runner Replacement
For the lump sum of $
TOTAL FOR PRICE SCHEDULE B $_________________
TOTAL FOR PRICE SCHEDULE A+B $_________________
B.2 WARRANTED CHARACTERISTICS
(a) The Offeror warrants that each turbine with new runner shall:
(1) Meet or exceed the weighted efficiency furnished below.
(2) Meet or exceed the power furnished below.
(b) Weighted efficiency:
(1) A: Guaranteed peak efficiency at net head 260 feet ......................... ______percent
a. Weighting factor for peak efficiency: 30 percent
(2) B: Guaranteed peak efficiency at net head of 300 feet ..................... ______percent
a. Weighting factor for peak efficiency: 50 percent
(3) C: Guaranteed peak efficiency at net head of 330 feet ..................... ______percent
Price Schedule (Revised)
B - 3
a. Weighting factor for peak efficiency: 20 percent
(4) D: Warranted weighted efficiency = A x 0.3 + B x 0.5 + C x 0.2 .... ______percent
a. Minimum warranted weighted efficiency: 93.0 percent
(c) Guaranteed power at B with tailwater at 3866 feet .......................................__________hp
(d) Guaranteed minimum net head for which one turbine will produce 27,500 hp .........................................................................................._________feet
(e) Failure to furnish the required values will result in an incomplete offer, which will not be considered.
(f) The efficiency of turbines with replacement runners installed will be determined from field test data acquired in accordance with the clause in Section E entitled “Performance Tests - Horsepower and Efficiency.”
(g) The contract price will be adjusted in accordance with the clause at WBR 1452.246-81, Failure to Meet Performance Warranties.
END OF SUPPLIES OR SERVICES AND PRICES
Project Management and Coordination (Revised)
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 PROJECT COORDINATION
A. The following meetings are considered significant, but do not relieve the Contractor from the responsibility of other meetings required by the specifications.
1. Progress Review Meetings:
a. Meeting shall be held weekly at the work site project office or remotely.
Prepare agenda and distribute 24 hours before the meeting.
b. Prepare and distribute meeting minutes.
c. Attendees: Responsible representatives who have been fully informed of specifications with respect to technical requirements, and coordination necessary to complete construction. Representatives shall be determined on an as needed basis and typically should include:
1) Project Manager from Contractor.
2) Field Superintendent from Contractor.
3) COR and other Representatives from Reclamation.
4) Representatives may attend by telephone or video conference.
d. Purpose:
1) Review, schedule, construction progress, and coordination.
a) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.
b) Review safety, security, environmental, schedule, project issues and concerns, submittals, contractor Requests for Information (RFI), Requests for Proposals (RFP), pending Contract Modifications, and other project related items.
c) Provide 3-week look-ahead schedule at least 24 hours before start of meeting.
d) Review as-built drawings.
Submittals (Revised)
01 33 00 - 8
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
1 Release of claims (1452.204-70)
Release of claims (DI-137) against United States
After completion of work and prior to final payment
A CO CDMS
2 Payroll and Basic Records (52.222-8)
Certified payrolls Weekly for each week any contract work is performed on site
I COR CDMS
3 Subcontracts (52.222-11)
(1) List of subcontractors
(2) Statement and Acknowledgment Form (SF-1413) for each subcontract
Within 21 days after Notice to Proceed, and within 14 days after award of any subcontract
I COR CDMS
4 Equal opportunity (52.222-26)
Information required by Executive Order
11246 (SF-100)
Within 30 days following Notice to Proceed
I COR CDMS
5 Performance and Payment Bonds (52.228-15)
Performance and payment bonds
Within 10 calendar days after award
A CO 1 0 0
6 Estimate of Percentage of Recovered Material Content of
EPA-
Designated Items (52.223-9)
Estimate the percentage of the total recovered material content for EPA designated item(s) delivered and/or used in contract performance
On completion of the contract (no later than with submittal of final voucher)
I COR CDMS
7 Safety and Health (WBR 1452.223-81)
Safety Program Submitted and approved before starting onsite work.
See Section 3 of
RSHS.
A Y COR CDMS
8 Safety and Health (WBR 1452.223-81)
Monthly Accident Summary Report
First day of month.
See paragraph 3.5.8 of RSHS
I COR CDMS
9 Security Requirements
(WBR
1452.237-80)
Security Program Submitted and approved before mobilization
A COR CDMS
01 33 00 - 9
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
10 Liability Insurance (1452.228-70)
Acceptable evidence showing that insurance has been obtained
Within 10 calendar days after award
I CO 1 0 0
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
At least 28 days before use of Government land
A COR CDMS
01 14 30-1 Interruption of Service
Interruption of Service Request
At least 60 days before interruption of service
A COR CDMS
01 31 30-1 Contract Document Management System
Approval Data Within 21 days of Notice to Proceed
A COR 1 1 1
01 31 30-2 Contract Document Management System
Final Data Within 14 days of completion of work
I COR CDMS
01 32 10-1 Construction Program
Representative Information
Within 21 days after receipt of Notice of Proceed
A COR CDMS
01 32 10-2 Construction Program
Baseline Schedule
Within 21 days after receipt of Notice to Proceed
A De let ed
COR CDMS
01 32 10-3 Construction Program
Updated Schedule
Monthly
When invoice for progress payments will be submitted, submit at least 7 days before invoice.
A De let ed
COR CDMS
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after the CO directs a contract change, requests proposal for a future modification, value engineering proposal, or request for equitable adjustment
01 33 00 - 10
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 35 10-1 Safety Data Sheets
Complete LHM and
SDS
At least 14-days before hazardous materials are delivered to jobsite
A COR CDMS
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 14-days before hazardous materials are delivered to jobsite
A COR CDMS
01 35 30-1 Contractor’s Onsite Safety and Health Personnel
Qualifications Submitted and approved before development of RSN 7. See Section 3 of RSHS
A COR CDMS
01 35 30-2 Contractor’s Onsite Safety and Health Personnel
Safety Inspection Reports
Within 7 days of inspection
I COR CDMS
01 35 30-3 Contractor’s Onsite Safety and Health Personnel
CIH Exposure Assessment Reports
Within 7 days of inspection
I COR CDMS
01 46 00-1 Quality Procedures
Contractor Quality Control Plan (QC)
At least 28 days before start of construction or onsite activities
A COR CDMS
01 46 00-2 Quality Procedures
Contractor’s Daily Report
At the end of following workday
I COR CDMS
01 46 00-3 Quality Procedures
Quality Control Supervisor (QCS) Resume
At least 28 days before start of construction or onsite activities
A COR CDMS
01 46 00-4 Quality Procedures
Contractor’s Quality Testing Plan
At least 28 days before start of construction or onsite activities
A Y COR CDMS
01 46 00-5 Quality Procedures
Summary of Test Results
Monthly I COR CDMS
01 54 20-1 Use of Government Crane
Crane Operator Qualifications
At least 28 days before start of construction or onsite activities
01 33 00 - 11
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
01 54 20-2 Use of Government Crane
Crane Use Schedule Weekly A COR CDMS
01 55 20-1 Traffic Control Traffic Control Plan At least 28 days before start of construction or onsite activities
A Y COR CDMS
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28 days before start of construction activities
A Y COR CDMS
01 57 30-1 Water Pollution Control
Water Management Plan
At least 28 days before start of construction activities
A COR CDMS
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 28 days before start of construction activities
A COR CDMS
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
At least 28 days before start of construction activities
A COR CDMS
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
At least once each week
A COR CDMS
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 28 days before start of construction activities
A COR CDMS
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
I COR CDMS
01 78 30-1 Project Record Documents
Final As-Built Drawings
Within 14 days of completion of each unit overhaul
A Y COR CDMS
01 78 30-2 Project Record Documents
Combined Final Drawings in Government Format
Within 21 days of completion of each unit overhaul
A Y COR CDMS
01 78 30-3 Project Record Documents
Extra Materials Within 14 days of completion of work
I COR CDMS
01 33 00 - 12
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
02 80 10-1 General Requirements for Coatings Containing Hazardous Materials Abatement
Resumes and Qualifications
At least 28 days before beginning onsite work
A Y COR CDMS
02 80 10-2 General Requirements for Coatings Containing Hazardous Materials Abatement
Worker Protection Program
At least 28 days before beginning onsite work
A COR CDMS
02 80 10-3 General Requirements for Coatings Containing Hazardous Materials Abatement
Area Baseline Test Results
Within 7 days of collecting samples
A COR CDMS
02 80 10-4 General Requirements for Coatings Containing Hazardous Materials Abatement
Working Level Test Results
Within 1 day of collecting samples
A COR CDMS
02 80 10-5 General Requirements for Coatings Containing Hazardous Materials Abatement
Post Test Results for Cleaning Verification
Within 3 days of collecting samples
A COR CDMS
02 83 35-1 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Qualifications At least 28 days before beginning onsite work
01 33 00 - 13
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
02 83 35-2 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Coatings Removal Debris Abatement Plan
At least 28 days before beginning onsite work
A Y COR CDMS
02 83 35-3 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Waste Characterization Report
Within 28 days of collecting samples
A COR CDMS
02 83 35-4 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Waste Handling and Disposal Plan
Within 21 days of Waste Characterization Report approval. Do not submit prior to Waste Characterization Report approval
A COR CDMS
02 83 35-5 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Manifest for Reclamation Signature
Within 14 days of shipping hazardous waste. Only required when accepted Waste Characterization Report indicates the presence of hazardous waste
A COR CDMS
02 83 35-6 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Final Manifests, Recycling Report, Bills of Lading, Disposal Certificates
Within 21 days of shipping waste
A COR CDMS
02 87 20-1 Removal and Disposal of Used Oil
Qualifications At least 28 days before beginning
01 33 00 - 14
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
02 87 20-2 Removal and Disposal of Used Oil
Oil Handling and Disposal Plan
At least 28 days before beginning onsite work
A Y COR CDMS
02 87 20-3 Removal and Disposal of Used Oil
Manifest for Reclamation Signature
Within 14 days of shipping hazardous waste
A COR CDMS
02 87 20-4 Removal and Disposal of Used Oil
Final Manifests and Disposal Certificates
Within 21 days of shipping waste.
A COR CDMS
03 81 12-1 Concrete Removal and Replacement
Concrete Removal Plan
At least 28 days before beginning onsite work
A Y COR CDMS
03 81 12-2 Concrete Removal and Replacement
Changes to Removal Equipment Settings (if changes are made)
Within 24 hours of change
A COR CDMS
03 81 12-3 Concrete Removal and Replacement
Approval Data At least 28 days before beginning onsite work
A Y COR CDMS
03 81 12-4 Concrete Removal and Replacement
Applicator’s Reference and Qualifications
At least 28 days before beginning onsite work
A COR CDMS
03 81 12-5 Concrete Removal and Replacement
Backfill Grouting Plan
At least 28 days before beginning onsite work
A COR CDMS
09 96 20-1 Coatings Approval Data At least 28 days before beginning onsite work
A Y COR CDMS
09 96 20-2 Coatings Final Approval Data At least 14 days before beginning onsite work
A COR CDMS
09 96 20-3 Coatings Qualifications At least 28 days before beginning onsite work
A COR CDMS
09 96 20-4 Coatings Quality Control Plan At least 28 days before beginning onsite work
A COR CDMS
09 96 20-5 Coatings Contractor Quality Testing Final Report
At least 28 days before beginning
01 33 00 - 15
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
09 96 20-6 Coatings Protection of Mating Surfaces
At least 28 days before beginning onsite work
A COR CDMS
22 11 86-1 Bearing Oil Coolers
Approval Data and Drawings
At least 42 days before procurement of equipment
A COR CDMS
22 11 86-2 Bearing Oil Coolers
Contractor Source Test Plan and Schedule
At least 28 days before testing
A COR CDMS
22 11 86-3 Bearing Oil Coolers
Test Reports Within 14 days of test completion
A COR CDMS
22 11 86-4 Bearing Oil Coolers
Qualifications At least 42 days before beginning onsite work
A COR CDMS
22 11 86-5 Bearing Oil Coolers
Field Quality Test Plan and Schedule
At least 42 days before beginning onsite work
A Y COR CDMS
22 11 86-6 Bearing Oil Coolers
Field Quality Test Reports
Within 14 days of test completion
A COR CDMS
22 11 86-7 Bearing Oil Coolers
Final Drawings and Data
Within 28 days of completion of work
A COR CDMS
48 13 01-1 Hydraulic Design
Initial Report At least 180 days prior to mobilization
A Y COR CDMS
48 13 01-2 Hydraulic Design
Hydraulic Transient Analysis Report
At least 56 days prior before beginning onsite work
A Y COR CDMS
48 13 01-3 Hydraulic Design
Final Report At least 28 days prior to procurement of runner components
A Y COR CDMS
48 13 04-1 Disassembly and As-Found Readings
Approval Documentation
At least 28 days before beginning onsite work
A Y COR CDMS
48 13 04-2 Disassembly and As-Found Readings
As-Found Reading Documentation
Within 21 days after completing readings
I COR CDMS
48 13 04-3 Disassembly and As-Found Readings
Disassembly Documentation
Within 21 days after inspections
I COR CDMS
48 13 04-4 Disassembly and As-Found Readings
Embedded Component Documentation
Within 21 days after completing readings
01 33 00 - 16
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
48 13 05-1 Onsite Machining
Approval Documentation
At least 28 days before beginning onsite work
A Y COR CDMS
48 13 05-2 Onsite Machining
Machining Equipment Details
At least 28 days before beginning onsite work
A COR CDMS
48 13 05-3 Onsite Machining
As-Found Report Within 21 days after completion of examination
I Y COR CDMS
48 13 05-4 Onsite Machining
Final Documentation
Within 21 days after completion of machining
A COR CDMS
48 13 07-1 Reassembly and Alignment
Reassembly Procedures
At least 100 days prior to reassembly at site
A Y COR CDMS
48 13 07-2 Reassembly and Alignment
Pipe Cleaning and Flushing Procedure
At least 100 days prior to reassembly at site
A Y COR CDMS
48 13 07-3 Reassembly and Alignment
Bill of Materials At least 100 days prior to reassembly at site
A COR CDMS
48 13 07-4 Reassembly and Alignment
As-left Protocol Sheets, Draft
At least 28 days before beginning onsite work
A COR CDMS
48 13 07-5 Reassembly and Alignment
As-left Protocol Sheets, Recorded
Within 21 days after completing readings
A COR CDMS
48 13 07-6 Reassembly and Alignment
Alignment Protocol Sheets, Recorded
Within 21 days after completion of task
A COR CDMS
48 13 07-7 Reassembly and Alignment
Critical Connection Torque Values
Within 21 days after completion of task
A COR CDMS
48 13 09-1 Critical Connection Fasteners
Approval Documentation
At least 28 days before ordering materials
A Y COR CDMS
48 13 09-2 Critical Connection Fasteners
Material Certifications
Within 21 days of procurement of materials.
A COR CDMS
48 13 09-3 Critical Connection Fasteners
Final Documentation
Prior to delivery to site
01 33 00 - 17
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
48 13 10-1 Vertical Francis Turbine Runner
Runner Mechanical Analysis
At least 180 days prior to mobilization
A Y COR CDMS
48 13 10-2 Vertical Francis Turbine Runner
Approval Documentation
At least 180 days prior to mobilization
A Y COR CDMS
48 13 10-3 Vertical Francis Turbine Runner
Material Certification
Within 21 days of casting or procurement of material
A COR CDMS
48 13 10-4 Vertical Francis Turbine Runner
Initial Inspection Reports
At least 56 days prior to shipment to site
A COR CDMS
48 13 10-5 Vertical Francis Turbine Runner
Runner Fabrication Logistics
Within 240 days after receipt of Notice to Proceed
A Y COR CDMS
48 13 10-6 Vertical Francis Turbine Runner
Final Report Within 14 days after final inspection
A COR CDMS
48 13 10-7 Vertical Francis Turbine Runner
Final Drawings Prior to delivery to site
A COR CDMS
48 13 11-1 Turbine Shaft Approval Documentation
At least 28 days prior to mobilization
A Y COR CDMS
48 13 11-2 Turbine Shaft As-Found Report Within 7 days of inspection
I COR CDMS
48 13 11-3 Turbine Shaft Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 14-1 Shaft Sleeve Approval Documentation
At least 28 days prior to mobilization
A Y COR CDMS
48 13 14-2 Shaft Sleeve Material Certification
Within 14 days after procurement
A COR CDMS
48 13 14-3 Shaft Sleeve Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 15-1 Packing Box Refurbishment
Approval Documentation
At least 28 days prior to mobilization
A Y COR CDMS
48 13 15-2 Packing Box Refurbishment
As-Found Report Within 14 days after inspection
I COR CDMS
48 13 15-3 Packing Box Refurbishment
Material Certification
Within 14 days after procurement
01 33 00 - 18
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
48 13 15-4 Packing Box Refurbishment
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 16-1 Turbine Guide Bearing
Approval Documentation
At least 28 days prior to mobilization
A Y COR CDMS
48 13 16-2 Turbine Guide Bearing
As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 16-3 Turbine Guide Bearing
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 16-4 Turbine Guide Bearing
Final Documentation
At least 28 days prior to shipment to site
A COR CDMS
48 13 17-1 Generator Bearings
Approval Documentation
At least 28 days prior to mobilization
A Y COR CDMS
48 13 17-2 Generator Bearings
As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 17-3 Generator Bearings
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 17-4 Generator Bearings
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 20-1 Headcover Rehabilitation
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 20-2 Headcover Rehabilitation
As-Found Reports Within 14 days after inspection
I Y COR CDMS
48 13 20-3 Headcover Rehabilitation
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 21-1 Bottom Ring Rehabilitation
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 21-2 Bottom Ring Rehabilitation
As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 21-3 Bottom Ring Rehabilitation
Final Inspection Documentation
Within 14 days after final inspection
A COR CDMS
48 13 22-1 Facing Plates and Wicket Gate End Seals
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 22-2 Facing Plates and Wicket Gate End Seals
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 22-3 Facing Plates and Wicket Gate End Seals
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 23-1 Stationary Wear Rings
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
01 33 00 - 19
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
48 13 23-2 Stationary Wear Rings
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 23-3 Stationary Wear Rings
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 25-1 Wicket Gates Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 25-2 Wicket Gates Rough Machining Report
Within 14 days after inspection
A COR CDMS
48 13 25-3 Wicket Gates Material Certification
Within 14 days after procurement
A COR CDMS
48 13 25-4 Wicket Gates Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 26-1 Wicket Gate Levers and Links
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 26-2 Wicket Gate Levers and Links
As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 26-3 Wicket Gate Levers and Links
Final Inspection Documentation
Within 14 days after final inspection
A COR CDMS
48 13 27-1 Shear and Linkage Pins
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 27-2 Shear and Linkage Pins
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 27-3 Shear and Linkage Pins
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 28-1 Bushing and Bearings
Approval Documentation
At least 28 days before mobilization
A COR CDMS
48 13 28-2 Bushing and Bearings
Material Certification
Within 14 days after procurement
A COR CDMS
48 13 28-3 Bushing and Bearings
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 29-1 Operating Ring Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 29-2 Operating Ring As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 29-3 Operating Ring Final Inspection Documentation
Within 14 days after final inspection
A COR CDMS
48 13 30-1 Servomotors Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
01 33 00 - 20
Table 01 33 00A - List of Submittals
* Submittal Types: A - Approval, I - Information ** Y indicates Yes, the submittal is required to be shown on the Construction Schedule - see Section 01 32 10 -
Construction Program *** CO indicates Contracting Officer, COR indicates Contracting Officer Representative, and TSC indicates
Technical Service Center. CDMS indicates Contract Document Management System.
RSN
Clause or
Section Title
Submittals required
Due date or Delivery time
Type
CP
Respon-sible code
No. of sets to be sent to: ***
CO COR TSC
48 13 30-2 Servomotors As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 30-3 Servomotors Material Certification
Within 14 days after procurement
A COR CDMS
48 13 30-4 Servomotors Final Inspection Documentation
Within 14 days after final inspection
A COR CDMS
48 13 35-1 Discharge Ring Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 35-2 Discharge Ring As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 35-3 Discharge Ring Material Certification
Within 14 days after procurement
A COR CDMS
48 13 35-4 Discharge Ring Final Inspection Documentation
Within 14 days after final inspection
A COR CDMS
48 13 43-1 Brake and Jacking System
Approval Documentation
At least 28 days before mobilization
A Y COR CDMS
48 13 43-2 Brake and Jacking System
As-Found Reports Within 14 days after inspection
I COR CDMS
48 13 43-3 Brake and Jacking System
Final Documentation
Within 14 days after final inspection
A COR CDMS
48 13 44-1 Bearing Brackets
Approval Documentation
At least 28 days before mobilization
A COR CDMS
48 13 44-2 Bearing Brackets
As-Found Reports Within 14 days after inspection
END OF SECTION
Hydropower Project Information (Revised)
48 13 00 - 3
1.06 TURBINE INFORMATION
A. Original Manufacturer: The James Leffel & Company.
B. Type: Vertical Francis
1. Cavitation on existing runners is repaired annually and requires a one week outage per unit.
a. Refer to Section 51 00 10 – Photographs.
b. Refer to Section 51 00 20 – Inspection Reports.
C. Years Installed: 1950 (Unit 1), 1951 (Unit 2).
D. Approximate Component Weights:
1. Runner: 10,500 pounds.
2. Nose Cone: 600 pounds.
E. Weight of components, including hydraulic thrust at twice runner design wearing ring clearance, carried by the generator thrust bearing: 134,000 pounds.
F. Vacuum Breaker:
1. Existing system is functional and has not been modified from original design.
2. Existing units do not have issues with noise, stability, and vibration.
G. Casing Baffle Vane, Draft Tube Baffle, Waterway Condition: Refer to Section 51 00 10 – Photographs for photographs of existing condition.
1.07 GENERATOR INFORMATION
A. Generator Output: 20.0 MVA at 1.0 power factor.
B. Losses in kilowatts. Refer to Table 48 13 00B – Generator Losses.
Table 48 13 00B – Generator Losses
Full Load 0.75 Load 0.50 Load 0.25 Load
Loss 441 340 270 226
PART 2 PRODUCTS
Not Used
Hydropower Project Information (Revised)
48 13 00 - 4
PART 3 EXECUTION
Not Used
Packing Box Refurbishment (Revised)
48 13 15 - 5
4. Electronic photos of findings.
D. Final Report:
1. Verified measurements and inspection sheets.
a. Material temperature when measurements were taken.
2.05 NON-DESTRUCTIVE TESTING
A. General:
1. See Section 48 13 03 – General Testing Methods.
2. Perform before and after refurbishment.
B. VT Testing:
1. Perform 100 percent VT.
2. Test the following components:
a. Packing box.
b. Lantern Ring.
c. Gland.
d. Yokes and eye bolts.
C. MT and PT Testing:
1. Perform 100 percent MT or 100 percent PT.
2. Test the following components:
a. Packing box.
b. Lantern Ring (new component only).
c. Gland (new component only).
D. As-found Report:
1. Written and mapped description of the results from the non-destructive examination for retained components.
2. Recommended Repairs:
a. Identification and description of defects.
b. Proposed methods of repair.
3. Personnel qualification records per ASTM A903 S1.
E. Final Report:
1. Written and mapped description of the results from the non-destructive examination for retained and new components.
Brake and Jacking System (Revised)
48 13 43 - 2
a. Deleted
b. Brake and Jack Assemblies.
2. Inspection test plan.
3. Drawing.
C. RSN 48 13 43-2, As-Found Reports:
1. Dimensional Report.
2. Non-Destructive Examination Report.
3. Disposition Report.
4. Testing Report.
D. RSN 48 13 43-3, Final Documentation:
1. Bill of Materials.
2. Final Non-Destructive Examination report.
3. Final Dimensional Check Sheets.
4. Final Drawings.
5. Final Testing Reports.
1.05 QUALIFICATIONS
A. Non-destructive examination personnel:
1. See Section 48 13 03 – General Testing Methods.
1.06 EXISTING CONDITIONS
A. Brake and Jack Assemblies:
1. Air operated pistons to engage brake ring on rotor to bring rotating parts to a stop from one half operating speed in five (5) minutes, without field excitation.
2. Hydraulically operated pistons to jack (lift) unit to provide removal or adjustment of the thrust bearing and during unit disassembly/reassembly.
3. Same system is used for braking and jacking by changing the working fluid.
PART 2 PRODUCTS
2.01 REFURBISHMENT
A. General:
1. Plug holes and ports.
48 13 43 - 3
2. Protect machined surfaces from cleaning, media blasting, and coating operations.
3. Develop and provide an inspection test plan.
4. Clean, perform dimensional checks and non-destructive examination:
a. Provide disposition report.
5. Surfaces machined for restoration per OEM finish unless otherwise stated.
6. Minimize material removal, maximum material removal 0.010-inches. Additional removal requires approval.
7. Provide bill of materials for new items.
B. Deleted
C. Brake and Jack Cylinder Assembly Rehabilitation:
1. Provide rehabilitation procedure.
2. Shop Testing:
a. Bench test each cylinder assembly prior to and after rehabilitation. Test both pneumatically and hydraulically.
b. Record test pressure and results.
1) Post rehabilitation acceptance pressure test is no leaks.
c. Test for reliable and free movement, smooth return, a minimum of 6 cycles. Record results.
1) Post rehabilitation acceptance is proper operation without binding.
d. Provide testing reports with completed data sheets.
3. Rehabilitation:
a. Fully disassemble cylinder assemblies and inspect.
b. Hone cylinder bores to restore cylindricity and sealing tolerances.
c. Replace:
1) Wear parts, seals, gaskets, and packing.
2) Hardware, 1-inch in diameter or less.
3) Return springs.
4) Brake pads.
2.02 PREPARATION
1. Photo-document as-found condition.
48 13 43 - 4
2. Coatings contain regulated metals. Refer to Section 02 83 35 - Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals.
B. Clean and prepare entire component for examination:
1. Machined and journal surfaces: SSPC-SP 1
2. All other surfaces, including coupling bores: SSPC-SP 2
3. For surfaces contaminants that cannot be removed by SSPC-SP 2, first power tool surfaces to SSPC-SP 3. If still not removed blast surfaces to SSPC-SP 6.
4. No metal removal is allowed during the cleaning process.
5. Protect machined and journal surfaces during blasting of other surfaces.
2.03 DIMENSIONAL AND GEOMETRIC INSPECTIONS
A. Perform as-found and final inspections.
1. Record material temperature when measurements were taken.
2. Record measurement device used and calibration certificate.
B. 100 percent dimensional and geometric inspection of all components, including but not limited to:
a. Brake and Jacking Cylinder Assemblies.
b. Brake Pads.
c. Deleted
C. As-found Report:
1. Dimensional and geometric condition:
a. Material temperature when measurements were taken.
2. Verified measurements and inspection sheets.
3. Recommended Repairs:
a. Identification and description of defects.
b. Proposed methods of repair.
4. Electronic photos of findings.
D. Final Report:
1. Verified measurements and inspection sheets.
a. Material temperature when measurements were taken.
2.04 NON-DESTRUCTIVE EXAMINATION
48 13 43 - 5
1. See Section 48 13 03 – General Testing Methods.
2. Perform before and after refurbishment.
B. VT Testing:
1. Perform 100 percent VT.
2. Test the following components:
a. Brake and Jack Cylinder Assemblies.
b. Deleted
C. MT and PT Testing:
1. Perform 100 percent MT or 100 percent PT.
2. Test the following components:
a. Brake and Jack Cylinder Assemblies.
b. Deleted
D. As-found Report:
1. Written and mapped description of the results from the non-destructive examination.
2. Recommended Repairs:
a. Identification and description of defects.
b. Proposed methods of repair.
3. Personnel qualification records per ASTM A903 S1.
E. Final Report:
1. Written and mapped description of the results from the non-destructive examination.
2. Personnel qualification records per ASTM A903 S1.
2.05 DRAWINGS
A. General:
1. Include material designations and weight of individual components.
B. Approval Drawings:
1. Refurbishment Drawings:
a. Provide a separate drawing for:
1) Brake Assemblies.
2) Deleted
48 13 43 - 6
C. Final Drawings:
1. Updated versions of approval drawings:
a. Government format.
b. Changes made in the field or shop.
c. Verified dimensions:
1) Specific to individual unit, labeled.
d. Torque values.
2.06 MATERIALS
A. Brake Cylinder Assembly Components:
1. Brake Pads: In-kind replacement. Low-dust, asbestos-free.
2. Return Springs: In-kind replacement.
B. Hardware:
1. Bolts and studs: ASTM A193, B7.
2. Nuts: ASTM A194, 2H.
3. Washers: Hardened steel compatible with brake ring and hardware.
2.07 COATINGS
A. Coat in accordance with Section 09 96 20 – Coatings.
PART 3 EXECUTION
A. Reference Section 48 13 07 - Reassembly and Alignment.
Photographs (Added)
51 00 10 - 1
SECTION 51 00 10
PHOTOGRPAHS
51 00 10 - 2
1.01 CASING BAFFLE VANE
51 00 10 - 3
51 00 10 - 4
51 00 10 - 5
51 00 10 - 6
51 00 10 - 7
51 00 10 - 8
51 00 10 - 9
51 00 10 - 10
51 00 10 - 11
51 00 10 - 12
1.01 DRAFT TUBE BAFFLE
51 00 10 - 13
51 00 10 - 14
51 00 10 - 15
51 00 10 - 16
51 00 10 - 17
1.02 RUNNER CONDTION
51 00 10 - 18
51 00 10 - 19
51 00 10 - 20
51 00 10 - 21
51 00 10 - 22
51 00 10 - 23
51 00 10 - 24
51 00 10 - 25
1.03 WATERWAY CONDITION
51 00 10 - 26
51 00 10 - 27
51 00 10 - 28
51 00 10 - 29
51 00 10 - 30
51 00 10 - 31
51 00 10 - 32
51 00 10 - 33
51 00 10 - 34
51 00 10 - 35
51 00 10 - 36
51 00 10 - 37
51 00 10 - 38
51 00 10 - 39
51 00 10 - 40
51 00 10 - 41
51 00 10 - 42
51 00 10 - 43
51 00 10 - 44
51 00 10 - 45
51 00 10 - 46
51 00 10 - 47
51 00 10 - 48
51 00 10 - 49
51 00 10 - 50
51 00 10 - 51
51 00 10 - 52
This page intentionally left blank.
Inspection Reports (Added)
51 00 20 - 1
SECTION 51 00 20
INSPECTION REPORTS
51 00 20 - 2
1.01 RUNNER U1
51 00 20 - 3
51 00 20 - 4
51 00 20 - 5
51 00 20 - 6
51 00 20 - 7
51 00 20 - 8
51 00 20 - 9
51 00 20 - 10
51 00 20 - 11
51 00 20 - 12
51 00 20 - 13
51 00 20 - 14
51 00 20 - 15
51 00 20 - 16
51 00 20 - 17
51 00 20 - 18
51 00 20 - 19
51 00 20 - 20
51 00 20 - 21
51 00 20 - 22
51 00 20 - 23
1.02 RUNNER U2
51 00 20 - 24
51 00 20 - 25
51 00 20 - 26
51 00 20 - 27
51 00 20 - 28
51 00 20 - 29
51 00 20 - 30
51 00 20 - 31
51 00 20 - 32
51 00 20 - 33
51 00 20 - 34
51 00 20 - 35
51 00 20 - 36
51 00 20 - 37
51 00 20 - 38
51 00 20 - 39
51 00 20 - 40
51 00 20 - 41
51 00 20 - 42
Drawings (Revised)
52 00 00 - 4
Table 52 00 00A - List of Drawings
Sheet No.
Drawing No. Title
46 14-B-5878 Vert. W.W. Generator - Thrust Bearing Assembly (36 Dia.)
47 16-B-1445 Vertical W.W. Generator Fr. 26-167-29 - Lower Guide Bearing Assembly (24 ½ Dia.)
48 16-B-1450 Vertical W.W. Generator Fr. 26-167-29 – Cooling Coil (Lower Guide Brg.)
49 19-A-3346 Vertical W.W. Generator Fr. 26 – Main Shaft
50 9710D24 Hydro Generator 26-167-29 – General Assembly
51 9710D25 Hydro Generator 15,000 KVA Outline
51a 47002 Baffle
51b 47003 Baffles and Piping Installed in One Draft Tube
Standard Drawings:
52 40-D-7102 Government Drawing Format - Drawing Border, Sample Title Block and Signature Lines
| Table of Contents |
| Section B- Price Schedule |
| 01 31 19 |
| 01 33 00A- Submittal Table |
| 48 13 00 |
| 48 13 15 |
| 48 13 43 |
| 51 00 10 |
| 51 00 20 |
| 52 00 00A |