This document is the Section J - Attachment No. 001 Division 1 Specifications for the federal contract opportunity to re-roof the Circle X Quarters 114 and Franklin Canyon Quarters 116.
The project requires removing and replacing the existing roofs on two housing units - a 3,500 sq ft brick structure at Circle X Quarters 114 in Malibu, CA and a 1,400 sq ft historic wooden structure at Franklin Canyon Quarters 116 in Beverly Hills, CA. The roofing materials shall be replaced with in-kind materials, with sample colors to be approved by the National Park Service. The work includes repairing or replacing any rotten sheathing/decking, installing new flashing, gutters, and downspouts, and removing and re-installing any rooftop antennas or equipment.
The contract will be awarded under Solicitation Number 140P8624Q0039 from the Department of the Interior National Park Service Pacific West Region. The contractor shall commence work within 10 calendar days after the date of receipt of the Notice to Proceed. Bidders are required to visit the job sites and examine existing conditions before submitting bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 10 00 - 1
General Requirements
OVERHEAD
SECTIONAL
DOORS
SAMO
RE-ROOF CIRCLE X QTRS. 114
and Franklin Canyon QTRS. 116
DIVISION 1 DOCUMENT
SECTION 01 10 00 GENERAL
REQUIREMENTS
PART 1 - DESCRIPTION OF WORK
1.1 BACKGROUND:
The Circle X (CX) Quarters 114 is located at 12896 Yerba Buena Rd (mile marker 5), Malibu, CA 90265. This is a non-historic brick structure 3500 sf housing unit. This building currently has a rolled asphalt roof and shall be replaced with an in-kind replacement.
The Franklin Canyon (FC) Quarters 116 is located at 2300 Franklin Canyon Drive, Beverly Hills, CA 90210 is a historic wooden structure stucco 1400 sf housing unit.
This building currently has a 3-tab white asphalt shingle roof and shall be replaced with an in-kind replacement.
1.2 The goal of this project is to contract for two re-roofs at said locations as both locations it was determined to replace roofs due to age and condition of existing roofs.
1.3 The roofing materials shall be replaced with in-kind materials, sample materials/color to be approved by NPS.
Circle X Location:
• Remove and dispose of all existing roofing materials, and any rotten sheathing/decking.
• Repair or replace any rotten or damaged sheathing/decking with like material.
• Re-roof with rolled asphalt.
• Furnish and install 50# or recommended felt over the entire roof area including new drip edge flashing.
• Furnish and install new flashing for all roof penetrations, including curb flashings, chimney flashings, valley flashings, roof jacks and vents etc.
• Paint roof jacks and vents to match color of newly installed roofing material.
• Remove existing gutters and downspouts. Install new gutters and new downspouts.
• Remove and re-install any wireless rooftop internet or communication antennas, etc.
Franklin Canyon Location:
• Remove and dispose of all existing roofing materials, and any rotten sheathing/decking.
• Repair or replace any rotten or damaged sheathing/decking with like material.
• Re-roof with in-kind asphalt shingles.
• Furnish and install 50# or recommended felt over the entire roof area including new drip edge flashing.
RFQ 140P8624Q0039
Section J - Att No. 001
01 10 00 - 2
OVERHEAD
SECTIONAL
DOORS
SAMO
CIRCLE X QTRS. 114 RE-ROOF
DIVISION 1 DOCUMENT
• Furnish and install new flashing for all roof penetrations, including curb flashings, chimney flashings, valley flashings, roof jacks and vents etc.
• Paint roof jacks and vents to match color of newly installed roofing material.
• Remove existing gutters and downspouts.
• Install new gutters and new downspouts.
• Remove and re-install any wireless rooftop internet or communication antennas, cameras, or encapsulated ducting etc.
PART 2 - EXISTING UTILITIES
2.1 There should be no need for any excavation during this project or utility location.
PART 3 - CONTRACTOR’S USE OF PREMISES
3.1 ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
3.2 CONSTRUCTION CAMP: N/A
3.3 STORAGE – STAGING AREAS:
A. CX Location - Storage and Staging area is behind the building in the based lot.
B. FC Location - Storage and Staging area at this location has minimal/space and will be restricted to under the carport for materials and any work trucks may stage across from house in dirt turnout.
C. Confine Storage of materials and equipment to the project area. Limits of use and control shall be subject to Contracting Officer’s approval.
D. At FC Location Traffic controls would be limited to 15-minute stops as needed to load and unload materials. Contractor is responsible for traffic control measures and proper signage.
3.4 PRESERVATION OF NATURAL FEATURES: N/A
3.5 HAULING RESTRICTIONS: N/A
3.6 HOUSEKEEPING:
A. Keep project neat, orderly, and in a safe condition always. Store and use equipment, tools, and materials in a manner that does not present a hazard. Do not allow rubbish to accumulate. Provide onsite containers for collection of rubbish and dispose of it at frequent intervals during progress of work.
B. Dispose of waste materials legally. It is the contractor’s responsibility and at their cost to dispose of such debris. Do not use park trash receptacles.
PART 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION
01 10 00 - 3
OVERHEAD
4.1 The Contractor shall commence work within 10 calendar days after the date of receipt of the "Notice to Proceed."
PART 5 - EXAMINATION OF THE SITE
5.1 All bidders are urged to visit the job sites and examine existing conditions before submitting bids. All bidders will be held to have the same knowledge concerning the site and the on-ground conditions as if they had inspected the job site. A pre bid site visit will be scheduled.
PART 6 - ABBREVIATIONS
6.1 The following list of abbreviations, which may be used in the Construction Specifications or Special Provisions, refer to the organizations and specifications of the organizations listed below:
AASHTO - American Association of State Highway and Transportation Officials
ACI - American Concrete Institute
AISC - American Institute of Steel Construction
AI - Asphalt Institute
ANSI - American National Standards Institute
ASTM - American Society for Testing and Materials
AWWA - American Water Works Association
Caltrans- State of California Department of Transportation
FHWA - Federal Highway Administration
FS - Federal Specifications
MSHA - Mine Safety and Health Administration
MUTCD - Manual on Uniform Traffic Control Devices
NEC - National Electric Code
NEMA - National Electrical Manufacturers Association
NFPA - National Fire Protection Association
NIOSH - National Institute of Occupational Safety and Health
NPS - National Park Service
NSF - National Sanitation Foundation
OSHA - Occupational Safety and Health Administration
PCA _ Portland Cement Association
UBC - Uniform Building Code
UL - Underwriters Laboratories, Inc.
PART 7 - ACCIDENT PREVENTION
7.1 DESCRIPTION: The work of this section consists of establishing and implementing an effective accident prevention program and providing a safe environment for all personnel and visitors.
7.2 SUBMITTALS:
A. ACCIDENT PREVENTION PROGRAM: At the preconstruction conference submit for approval an accident prevention program. The program shall include:
1. Name of responsible supervisor to carry out the program.
01 10 00 - 4
OVERHEAD
2. First aid procedures.
3. Training, both initial and continuing.
4. Planning for possible emergency situations.
5. Contractor to identify nearest location of medical facility for emergencies.
6. Recognition that work will be performed in remote areas with limited communication or cell phone coverage.
B. MEETING AND INSPECTION REPORTS: Submit a report of safety meetings and of inspections.
7.3 QUALIFICATIONS OF EMPLOYEES:
A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner.
B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
C. Operators of vehicles, mobile equipment, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be capable of operating such equipment. Provide operating instructions for all equipment.
D. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
7.4 ACCIDENT REPORTING: The Contractor shall report all accidents to the Contracting
Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
7.5 FIRST AID FACILITIES: Provide adequate facilities for the number of employees and the type of construction at the site.
7.6 PERSONNEL PROTECTIVE EQUIPMENT: Meet requirements of NIOSH and MSHA, where applicable, as well as ANSI.
7.7 EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
7.8 PROTECTIVE EQUIPMENT:
A. Inspect and maintain other protective equipment and devices before use and on a periodic basis to ensure safe operation.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.
7.9 SAFETY MEETINGS: As a minimum, conduct 15 minute "toolbox" safety meetings.
01 10 00 - 5
OVERHEAD
These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite.
7.10 HAZARDOUS MATERIAL ACTION: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials
Business Plan.
A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.
PART 8 - PRECONSTRUCTION CONFERENCE:
8.1 PRECONSTRUCTION CONFERENCE: Before start of construction, Contracting
Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following:
Roles and Responsibilities
Key Personnel
National Park Service regulations
Documents required under the contract
Subcontractors
Labor standards provisions
Modifications
Payments to Contractor
Payroll reports
Technical Issues
Correspondence procedures
Acceptance/Rejection of Work
Construction Meetings
Submittal of shop drawings, project data, and samples
Accident prevention program (including name of responsible supervisor)
Accident reporting
Safety program (compliance with the "Accident Prevention" clause of the General
Provisions)
Spill Response Plan
Saturday, Sunday, holiday and night work
Contract Time
Tentative construction schedule
Notice to Proceed
PART 9 - SUBMITTALS
9.1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
9.2 Sample of roofing and gutter materials/color.
01 10 00 - 6
OVERHEAD
Any work done before approval shall be at Contractor's own risk.
9.3 APPROVED EQUALS: A request for approval constitutes a representation that
Contractor:
A. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
B. Will provide the same warranties for the proposed item as for the item specified.
C. Has determined that the proposed item is compatible with interfacing items.
D. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
E. Waives all claims for additional expenses that may be incurred as a result of the substitution.
9.4 PROGRESS SCHEDULES: As soon as possible after Notice of Award and before beginning any work, submit a Schedule showing estimated starting and completion dates for each part of the work. The first progress payment will not be issued until an acceptable progress schedule is submitted.
PART 10 - TEMPORARY SERVICES
10.1 DESCRIPTION: The work of this section consists of providing temporary services required for Contractor's performance of the work of this Contract.
10.2 FIRE PREVENTION AND PROTECTION:
A. Hazard Control: Take all necessary precautions to prevent fire during construction.
Provide adequate ventilation during use of volatile or noxious substances.
PART 11 - PROJECT CLOSEOUT
11.1 DESCRIPTION: The work of this section consists of final cleanup, closeout submittals, final inspection procedures, and safety precautions.
11.2 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. At time of final inspection, project shall be thoroughly clean and ready for use.
11.3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certification that project is substantially complete, and a final inspection is requested.
Contracting Officer will make an inspection within 10 days of receipt of request.
A. When Contracting Officer determines that the work is substantially complete; he will prepare a list of deficiencies (“Punch List”) to be corrected before final acceptance and issue a Letter of
01 10 00 - 7
OVERHEAD
B. Substantial Completion.
C. If Contracting Officer determines that the work is not substantially complete; he will immediately notify Contractor in writing, stating reasons. After completing work, Contractor shall resubmit certification and request a new final inspection.
11.4 ACCEPTANCE OF THE WORK: After all deficiencies have been corrected, a Letter of
Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.
END OF SECTION