Section_J;_attach_004_-_Sample_Task_SOW.docx

DOCX document 15 KB Posted

Attached to
Alcatraz Island Repair Services IDIQ
Solicitation number
140P8618R0006
Issued by

About this file

Section J; attach 004 - 'Sample Task' SOW

View the file

Other files

File Type Posted
Section_J_attach_002_-_'Sample_Task'_Bid_Schedule_-_140P8618R0006_revised_Amendment_2.xls XLS spreadsheet
Sol_140P8618R0006_Amd_0002.pdf PDF
Revised_Section_J_attach_002_-_'Sample_Task'_Bid_Schedule_-_140P8618R0006.xls XLS spreadsheet
Alcatraz_Energy+Fuel+Expenses_MASTER_(1).xlsx XLSX spreadsheet
Sol_140P8618R0006_Amd_0001.pdf PDF
SCA_Wage_Determination_for_SF_County.pdf PDF
Revised_Section_J_attach_001_-_Bid_Schedule_-140P8618R0006_DCD_Edits.xlsx XLSX spreadsheet
ALCA_IDIQ_Site_Visit_Attendee_List.pdf PDF
Revised_CP.docx DOCX document
QuestionsAnswers.docx DOCX document
Section_J;_attach_010;_Past_Performance.docx DOCX document
Section_J;_attach_003;_SOW_-_140P8618R0006.docx DOCX document
Section_J;_attach_008;_Key_Personnel_Qualifications_140P8618R0006.docx DOCX document
Section_J_attach_001_-_Bid_Schedule_-140P8618R0006.xlsx XLSX spreadsheet
Sol_140P8618R0006.pdf PDF
Section_J,_attach_011;_Exhibits_List_140P8618R0006.pdf PDF
Section_J;_attach_007;_Relevant_prior_Experience.docx DOCX document
Section_J;_attach_009;_Subcontractor_Reference_140P8618R0006.docx DOCX document
Section_J;_attach_006;_SCA_Wage_-_140P8618R0006.pdf PDF
Section_J;_attach_005;_SCA_Wage_-_140P8618R0006.pdf PDF
Section_J;_attach_002_-_Sample_Task_Bid_Schedule.xlsx XLSX spreadsheet
ALCA_IDIQ_PRE-SOL_140P8618R0006.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Alcatraz Repair IDIQ – Sample Task Order SOW

Generator #2 Top End Overhaul and Associated Repairs:

Scope of Work: This project requires a complete in-frame rebuild, sometimes referred to as a "top end overhaul." The work will require the contractor to follow manufacturer’s recommendations for an in-frame rebuild of an MTU Series 60 Prime Mover engine. This engine is attached to a generator but the generator is not part of this scope or rebuild. The contractor will provide all necessary tools, equipment, supervision and technical staff capable of performing the work on-site. The location is Alcatraz Island and more specifically, the engine is located in the generator room located in the historic Powerhouse. During the rebuild, a backup generator will be required to facilitate a safe working environment in the generator room while the rebuild is taking place. This rebuild will also come with a follow up engine check at the 200hr mark, ensuring all parts and labor are holding to manufacturer’s specifications.

Any work found outside the manufacturer’s top end/in-frame rebuild recommendations and work noted below will be diagnosed and addressed as a change order. This bid is for all Onsite Energy parts, supervision and labor required on the MTU’s with Detroit 60 Series Engine from an Onsite Energy Dealer and per MTU guidelines. Parts not replaced will be factory measured, tested to confirm part meets spec with results included in final reporting.

1. Top End Overhaul: Conduct Megger Testing. Provide and Install Gasket Kit, Top End Turbo, Top End Fuel Pump Assembly, Cylinder Head with new studs, Injectors, Belts, Hoses & Filters.

2. Supply replacement oil.

3. Cooling System- Drain coolant from radiator and engine, remove all cooling hoses and clamps including jacket water heater hoses (block heater hoses if fitted), thermostats, all related gasket seals, O-rings, drive belts, radiator cap and replenish with new coolant after top end is completed.

4. Remove radiator, test and recore.

5. Remove after cooler unit, test and recore.

6. Recondition alternator end including cleaning, baking, dip and reinstallation. Return all cores within 30 days.

7. Provide auxiliary generator and all cables necessary for temporary power supply.

8. Unit will be load bank tested after completion of top end overhaul. Provide all cables and equipment to complete load bank testing. Provide daily and final written reporting.

9. Provide a secondary site visit after 200 hours initial run time to confirm valve seating and make any necessary adjustments.

10. Coordinate with contracted Alcatraz Maintenance and Custodial Service provider on all aspects of the work as it pertains to project background, safety, logistics and communication regarding planned power outages necessary to engage/disengage temporary power. See attached “General Requirements for Contractors on Alcatraz Island.”

11. Provide parts/labor warranty for a period of 1 year.

-End of SOW-