This document is a Statement of Work (SOW) for the replacement of perimeter fencing surrounding pastures in the Ash Mountain area of Sequoia and Kings Canyon National Parks (SEKI). The Contractor shall provide all materials, equipment, and labor needed to replace approximately 7,100 feet of fencing, with priority given to the southern and western fences. The fence posts shall be pressure-treated wood with specific dimensions and installation requirements. The wire shall be a combination of smooth and barbed wire, attached using appropriate fasteners. The existing fence material must be removed from the park by the Contractor.

The related federal contract opportunity is a Request for Quotes (RFQ) for this fencing replacement project, which is set-aside for Small Business (SB) concerns only. The North American Industry Classification System (NAICS) code is 238990 with a $19.0 million small business size standard. The construction magnitude is $25,000 to $100,000. Proposals are due by 12:00 P.M. Pacific Standard Time on August 5, 2024, and must be submitted via email. The Department of the Interior, National Park Service is the procuring agency.

View the file

Other files for this federal contract opportunity

Other files attached to SEKI ASH MT PASTURE FENCE REPLACEMENT, newest first.
File Type Posted
Sol_140P8524Q0080_Amd_0002.pdf PDF
B08_Attachment_5_Questions_and_Answers_Vol_2_0002.docx DOCX document
B08_Amendment_0001_Attachment_4_Questions_and_Answers_0001.docx DOCX document
Sol_140P8524Q0080_Amd_0001.pdf PDF
Sol_140P8524Q0080.pdf PDF
B08_Attachment_1_SOW.docx DOCX document
B08_Attachment_2_Fencing_Map.pdf PDF
B03_Attachment_3_Wage_Determination_CA20240016.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW: Ash Mountain Pasture Fence Replacement

Background

Sequoia and Kings Canyon National Parks (SEKI) staff maintains miles of fencing in the parks. These fences serve a multitude of purposes, but among them is establishing a perimeter for the pastures used by government owned stock. For a several months a year, government owned horses and mules (stock) live in corrals and pastures within SEKI. Competent fences are critical to preventing stock from damaging resources or potentially injuring themselves by reaching areas outside of designated areas.

SEKI has a need to replace fencing at the end of its life cycle surrounding portions of its pastures in the Ash Mountain area of SEKI.

Statement of Work (responsibilities)

1. Contractor shall supply provide all materials, equipment and labor needed to replace pasture fencing.

2. A map of the area is included. Contractor shall replace all pasture fencing denoted with a red outline (existing fences shown in yellow). Contractor will be responsible for doing their own linear takeoffs – approximately 7,100-feet of fences will be replaced. Priority will be given to completing the southern and western fences. There is one Tubed gate to be replaced and one water crossing on Sycamore creek.

3. Fence posts shall be pressure treated wood with a minimum size of 4-inches by 4-inches. Perimeter posts will be set every ten feet. Posts will be embedded at least two feet into the ground. Posts will be encased with concrete measuring 12-inches diameter x 12-inches deep at the bottom of the post – concrete will not extend below the post. Posts will extend at least 66-inches above the ground. Wire shall be stapled to the interior, pasture side of the wood posts. Wood post "H" braces should be replaced in locations where they currently exist, and 4x4 angle bracing is required on all corner posts.

4. Metal T-Posts may be used on straight fence segments to a maximum length of 40-feet. Wood posts will be used at all angle points, hill crests, and valleys. Metal posts spaced at 10-feet intervals will have wood posts on either side – wood post, three metal posts maximum, wood post. There shall be 1 wood post to every 3 steel posts. Metal T-Posts do not require a concrete footing but shall be driven in to the ground to the top of the T-post chevron plate. Wire shall be clipped to the interior, pasture side of metal T- posts. (Estimated wood posts 213/metal posts 533)

5. Wire shall be used between posts. The lower three wires shall be 12.5 gauge high-tensile, smooth wire. The upper two wires shall be barbed wire of the same gauge. Five wires shall be installed with the bottom wire falling 12-18 inches above the ground. The top wire shall be 60-inches above the ground. Other wires will be equally spaced. (Estimated Barbed Wire- 14,200 ft./Smooth Wire- 21,300 ft.)

6. All wires shall be attached using T-post clips (metal posts) or 1-3/4-inch fence staples (wood posts) as appropriate.

7. Existing fence wire shall be removed. Any existing fence posts shall be removed. All existing fence material is to be removed from the park by contractor. The park has no salvage need for this material.

8. The new fence shall be constructed in the same alignment as the original fence. Any deviation in alignment must be approved by the NPS.

9. A road does not follow the existing fence – a suitable UTV may be used to move materials through the pasture to the fence where truck access is not possible. There will be locations where walking of materials to the fence line will be required. Most of the fence line is accessible by UHV "side by side" or "quad" directly or within approximately a tenth to a quarter of a mile of mechanized access. Contractors pack animals can be used.

NPS Responsibilities

1. The Facility Manager or acting will inspect and monitor progress.

2. NPS will review any Contractor request to deviate from the original alignment and respond within 14-days.

Performance Period:

Contract Award, to September 30, 2024 There is no camping allowed on site. There is camping allowed at Potwisha campground, approximately 4 miles from project site, it is reservation only through Recreation.Gov, there may be other camping available outside the park on Recreation.gov also. The town of Three Rivers is nearby and should have Hotel and Air B&B accommodations available.

Billing and Invoicing:

Price will be billed by the length of fence (in feet) installed per month.

Quality Assurance:

A physical inspection of installed fence will be performed by an NPS representative and contractor before payment. All specifications shall be met and agreed to by contractor and NPS Contracting Officer.

NPS Contacts:

The following authorized NPS employees will coordinate installation activities:

Nathaniel Aldrich, Facility Manager (559) 565-4360 Rick Hall, Chief of Facilities (559) 565-3737