Rehabilitate Two Digesters at El Portal Wastewater Treatmetn Plant for YOSE (140P8518R0002)
Solicitation number
140P8518Q0049
Issued by

About this file

140P8518Q0049 - 01_Price_Schedule

View the file

Other files

File Type Posted
Award_Notice_140P8518P0061.pdf PDF
04_SCA_Wage_Determination.pdf PDF
03_Drawings.pdf PDF
01_Price_Schedule.pdf PDF
02_Specifications.pdf PDF
06_Experience_and_Past_Performance_Form.pdf PDF
02_Specifications.pdf PDF
04_SCA_Wage_Determination.pdf PDF
03_Drawings.pdf PDF
05_FAR_52.212-3_Form.pdf PDF
140P8518Q0049_Terms_and_Conditions.docx DOCX document
140P8518Q0049_SF1449.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT PRICE SCHEDULE

SOLICITATION NUMBER: 140P8518Q0049

PARK - PMIS: YOSE 185130

DEVELOPED AREA: EL PORTAL, CA

PROJECT TITLE: REHABILITATE TWO DIGESTERS AT EL PORTAL WASTEWATER TREATMENT FACILITY

Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the quote unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific l ine item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs.

In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.

CONTRACT

LINE ITEM

NUMBER

(CLIN)

CONTRACT LINE ITEM (CLI) TITLE QUANTITY

UNIT OF

MEASURE

UNIT PRICE

TOTAL

PRICE

1 Mobilization 1 Lump Sum

2 Cleaning and Dewatering of Primary Digester 1 Lump Sum

3 Cleaning and Dewatering of Secondary Digester 1 Lump Sum

4 Demobilization 1 Lump Sum

TOTAL PROPOSED BASE PRICE (Contract Line Item Number 1 through 4) ------------------------------------

All measurement and payment information is included in the project specifications, Section 01 27 00.