Summary: RFQ #140P8426Q0046 – Cleaning and Mold Remediation & Interior Restoration

This Request for Quotation (RFQ) solicits services for cleaning, mold remediation, and interior restoration of seven residential units at Crater Lake National Park. The work scope is divided by unit type: three units (24, 28, and 32) require both cleaning and repair activities due to water intrusion and microbial growth affecting ceilings, walls, flooring, and furnishings, while four units (31, 34A, 34B, and 34C) require cleaning only unless additional damage is discovered during inspection. Services include selective demolition of approximately 65 square feet of water-damaged ceiling materials per unit (drywall, plaster, and insulation), two-pass HEPA vacuuming, carpet shampooing and sanitization using HEPA extraction equipment, cleaning and treatment of hard surfaces with EPA-registered antimicrobial agents, furniture sanitization, air purification with HEPA scrubbers (minimum 4 air changes per hour), dehumidification to maintain humidity below 60%, restoration work including insulation replacement and drywall/plaster repair per applicable ASTM standards, air and surface testing to verify clearance criteria, and comprehensive documentation including photo records and final reports with recommendations.

Work must be completed within 30 calendar days, with permitted hours from 7:00 AM to 5:00 PM, seven days per week. The contractor must submit extensive pre-work documentation including payment bond (SF-25A), proof of liability and workers' compensation insurance, accident prevention and quality control plans, waste management plan, unit and room sequencing schedules, and restoration materials specifications. All work areas require containment with negative air pressure, dust control per OSHA standards, and protection of unaffected spaces. Testing personnel must provide credentials and training documentation prior to sampling. Payment is structured as a lump sum per unit upon project completion using the NPS Pay Estimate Form and submitted through www.ipp.gov. A minimum one-year warranty is required, and this is a firm-fixed-price contract with no adjustments for conditions discoverable at the time of quotation. Final inspection and punch list work must be completed within 30 days, weather permitting.

View the file

Other files

File Type Posted
Sol_140P8426Q0046_Amd_0001.pdf PDF
B08_Att_2_140P8426Q0046_Wages_DBA.pdf PDF
Sol_140P8426Q0046.pdf PDF
B08_Att_3_140P8426Q0046_Tech_Info_Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART 1 – GENERAL

ITEM 1 – DESCRIPTION OF WORK

1.1 Unit Overview and Service Requirements:

Crater Lake National Park maintains several historic stone residential buildings. These include six (6) two-story, two-bedroom houses and one (1) two-story structure that contains three (3) two-bedroom units. Collectively, these buildings comprise a total of nine (9) residential units.

Of the nine available units, Crater Lake National Park requires cleaning and/or restoration services for seven (7) specific residential units: units 24, 28, 31, 32, and (within Building 34) units 34A, 34B, and 34C. Unit numbering and locations shall be verified against site map included at the end of this document.

1.2 Scope of Work by Unit Type:

Three (3) of the units – units 24, 28, and 32 – require both cleaning and repair activities.

Water intrusion has resulted in microbial growth affecting ceilings, wall finishes, flooring systems, furnishings, and interior air quality in these units. They require mold cleaning, sanitation, and interior restoration services including demolition and restoration of affected drywall and plaster surfaces to address any identified damage.

The remaining four (4) units – specifically, units 31, 34A, 34B, and 34C – require cleaning only. These units do not show any evidence of water damage or mold at present. They will receive cleaning services exclusively, unless further inspection during execution uncovers damage that necessitates additional intervention.

This project establishes a unit-based remediation and restoration scope, where all work is defined and executed on a per unit basis, with total quantities derived from seven (7) units. Work may occur in any room within each unit where damage or contamination is present.

1.3 Work Covered by the Contract Documents:

Project Location:

Crater Lake National Park Scope Summary (PER UNIT BASIS):

All work shall be performed per individual unit as required. Cleaning (and mold remediation and restoration activities, when required) shall be performed throughout the entirety of each unit, including all accessible enclosed spaces such as closets, cabinets, crawlspaces, and similar areas, while demolition and restoration work may occur in any room (living rooms, bedrooms, hallways, or other interior spaces) as required based on field conditions:

• Selective demolition (per unit): Removal and disposal of approximately 65 square feet of water-damaged ceiling materials, including drywall, plaster, and insulation. Work areas shall be field-verified and may occur in any room within the unit.

Request for Quotation (RFQ) # 140P8426Q0046 - Specifications

CLEANING and/or MOLD REMEDIATION & INTERIOR RESTORATION –

RESIDENTIAL UNITS

CRATER LAKE NATIONAL PARK

PROJECT SPECIFICATIONS

• Interior HEPA vacuuming (per unit): Perform two-pass HEPA vacuuming of all ceilings, walls, floors, furnishings, and contents, including an initial (pre-treatment) cleaning and a secondary (post-antimicrobial application) cleaning, in accordance with IICRC S520 and S100.

• Cleaning, shampooing, and sanitizing (per unit):

o All carpeted areas shall be shampooed and sanitized using HEPA extraction equipment o All hard surfaces shall be cleaned and treated with EPA-registered antimicrobial agents, applied in strict accordance with manufacturer’s instructions, including required dwell/contact time to ensure effectiveness o All furniture and contents shall be cleaned and sanitized, with antimicrobial products applied per manufacturer-specified dwell times

• Air purification (per unit): Provide and operate HEPA air scrubbers achieving a minimum of 4 air changes per hour (ACH) per unit in accordance with ASHRAE 52.2.

• Moisture control (per unit): Deploy dehumidification equipment to maintain relative humidity below 60%. Contractor shall maintain daily moisture logs per unit, including ambient temperature, relative humidity, and material moisture readings using calibrated hygrometers and/or moisture meters in accordance with ASTM F2170 or equivalent standards. All instruments shall be calibrated per manufacturer’s requirements and logs shall be submitted as part of project documentation.

• Restoration (per unit): Restoration work shall be performed on a room-by-room basis within each unit, based on identified damage.

o Replace insulation per ASTM C665 o Install drywall per ASTM C840 where applicable o Repair plaster ceilings and finishes per ASTM C926/C1063 o Tape, finish, texture, and paint to match existing conditions o All repaired and restored finishes shall match existing historic materials, textures, and appearance and shall be performed in accordance with applicable National Park Service (NPS) preservation standards and guidelines, where historic finishes are present

• Testing and reporting (per unit): Conduct air and surface testing and document results.

Acceptable conditions shall be defined as indoor air spore counts and surface sampling results that are equal to or lower than outdoor baseline levels, with no dominance of indicator species (e.g., Stachybotrys, Chaetomium, or Aspergillus/Penicillium) and no visible mold growth or musty odors present. All testing results shall be documented and compared against baseline or control samples to establish clearance and avoid ambiguity at project closeout.

• Closeout (per unit): Provide unit-specific reports and recommendations for further remediation if required.

Total Project Quantity:

7 Units × Per Unit Scope Period of Performance:

• 30 calendar days or less

• Work permitted 7 days per week

• Allowable work hours: 7:00 AM to 5:00 PM daily

Request for Quotation (RFQ) # 140P8426Q0046 - Specifications

ITEM 2 – EXISTING UTILITIES

2.1 Contractor shall verify and protect utilities within each unit and each work area, regardless of room location.

2.2 All systems affected by ceiling demolition (lighting, wiring, HVAC) shall be identified and protected.

2.3 Lockout/tagout procedures shall comply with OSHA 29 CFR 1926 Subpart K.

ITEM 3 – CONTRACTOR’S USE OF PREMISES

3.1 Park Entry: Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.

3.2 Work shall be performed on a room-by-room basis within each unit, as required to address identified damage.

3.3 Contractor shall:

• Establish containment at the room level or unit level, depending on extent of work

• Maintain negative air pressure within each contained work area

• Prevent cross-contamination between rooms and units

3.4 Work Hours:

• Work may occur 7 days per week, 7:00 AM – 5:00 PM.

3.5 Protection Requirements:

• Protect unaffected rooms within each unit

• Protect flooring, furnishings, and adjacent finishes using temporary floor protection

(ASTM D3273 compliant materials)

• Clean tools between rooms and units

ITEM 4 – COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 Work shall be sequenced by unit and by room within each unit.

4.2 Estimated Production Rate (Per Unit):

• Selective demolition: 1 day (2 technicians)

• Cleaning and sanitation: 1 day (2 technicians)

• Air purification/drying: 1–2 days

• Restoration: 1–2 days

4.3 Multiple rooms within a unit may be addressed concurrently.

ITEM 5 – EXAMINATION OF THE SITE

5.1 Contractor shall inspect all rooms within each unit to verify:

• Locations of damage

• Ceiling types (drywall vs. plaster)

• Extent of contamination

ITEM 6 – SITE VERIFICATION RESPONSIBILITY

6.1 All quoters are responsible for field verifying site conditions prior to quote submission. This is a firm-fixed-price type contract; no price adjustments will be made for conditions that were known or discoverable at the time of quoting.

ITEM 7 – ABBREVIATIONS

• OSHA 29 CFR 1926

• IICRC S520 / S100

• EPA Mold Guidance

• ANSI/ASHRAE 52.2

• ASTM C840 / C926 / C1063

• NFPA 241

ITEM 8 – ACCIDENT PREVENTION

8.1 Contractor shall implement and maintain a written respiratory protection program in full compliance with OSHA 29 CFR 1910.134, including medical evaluations, fit testing, training, and proper respirator selection. Documentation of the program, including employee training records and fit test results, shall be submitted to the COR prior to commencement of work and maintained on-site at all times.

8.2 Safety controls shall be implemented per room and per unit.

8.3 PPE required per OSHA 1926 Subpart E, including respirators, gloves, and protective clothing.

ITEM 9 – PRECONSTRUCTION CONFERENCE

Contractor shall present:

• Unit and room-level work plan

• Containment and airflow strategy

• Cleaning and restoration methods

• Accident Prevention Plan/Safety Plan

ITEM 10 – SUBMITTALS

Submit:

• Payment Bond (SF-25A)

• Satisfactory evidence of liability insurance coverage and workman’s compensation for the contractor and all subcontractors

• Letter designating Project Superintendent

• Construction Schedule

• Schedule of Values - breakdown each lump-sum item into component work activities used in the schedule for which progress payments may be requested

• Accident Prevention Plan

• A list of subcontractors for this project

• Written statements from subcontractors certifying compliance with applicable labor standard clauses using Standard Form 1413

• Quality Control Plan

• Waste Management Plan

• Cleaning and sanitation procedures

• Carpet shampoo methods

• Air purification plan

• Restoration materials (drywall/plaster)

• Unit and room sequencing schedule

ITEM 11 – TEMPORARY SERVICES

Provide equipment sized for multi-room and multi-unit operations, including:

• HEPA air scrubbers per work area

• Dehumidifiers per unit

• Temporary power distribution

ITEM 12 – PROJECT CLOSEOUT

12.1 Contractor shall include site maps identifying all building and unit locations (Units 24, 28, 31, 32, 34A, 34B, 34C, and others as applicable) at the end of the closeout documentation. Maps shall clearly indicate work areas, sequencing, and unit identification for record purposes.

12.2 Closeout shall be completed per unit, including all rooms.

12.3 Submit:

• Testing results

• Photo documentation (room-by-room)

• Final report with recommendations

• Release of Claims (form will be provided by the Contracting Officer) upon final acceptance.

12.4 Final Inspection

• At work conclusion, the Contractor shall request a final inspection from CO and COR in writing (via email). Conduct final inspection walkthrough with CO and/or COR. Address all punch list items before project final acceptance by Contracting Officer. Punch list work shall be finalized within 30 days, weather permitting.

12.5 Warranty

• Minimum 1-year warranty

ITEM 13 – PAYMENT

Payment is based on a lump sum per unit, issued upon project completion. Use the NPS Pay Estimate Form and follow the Electronic Invoicing and Payment Requirements outlined in the contract. Email your payment package to the Contracting Officer/COR for review; after approval, submit your request online at www.ipp.gov.

ATTACHMENTS

• Site Map

PART 3 – EXECUTION

Phase 1 – Mobilization & Containment (Per Unit / Per Room)

• Establish containment at affected rooms or full unit.

• Install HEPA air scrubbers and maintain negative pressure.

Phase 2 – Selective Demolition (Per Unit / Any Room)

• Remove approximately 65 SF of ceiling materials per unit, located in any affected room.

• Materials include drywall, plaster, and insulation.

• Implement dust control per OSHA 1926.1153.

• Utilize HEPA-filtered tools or vacuum attachments during demolition activities to capture airborne particulates at the source and minimize dust migration in accordance with IICRC S520 best practices.

Phase 3 – HEPA Vacuuming, Cleaning, and Sanitization (Per Unit)

• Cleaning shall include all accessible enclosed spaces (closets, cabinets, crawlspaces, and similar areas), ensuring full treatment of concealed and confined surfaces.

• Perform cleaning using a top-down sequence (ceiling → walls → floors) to prevent recontamination of previously cleaned surfaces.

• HEPA vacuum all surfaces.

• Shampoo and sanitize all carpeted areas.

• Clean all hard surfaces and furnishings with antimicrobial agents.

Phase 4 – Air Purification & Drying (Per Unit)

• Operate HEPA air scrubbers (minimum 4 ACH) continuously during all active work periods.

• Continue operation of air scrubbers for a minimum 24-hour post-cleaning dwell period prior to final testing to ensure adequate air filtration and contaminant removal.

• Maintain humidity below 60%.

Phase 5 – Restoration (Per Unit / Per Room)

• Replace insulation.

• Install drywall or repair plaster depending on existing conditions.

• Finish and paint to match.

Phase 6 – Testing & Verification (Per Unit)

• Perform air and surface testing for each unit by contractor personnel or a qualified technician trained in mold assessment and sampling procedures.

• Personnel conducting testing shall provide documentation of credentials, training, and relevant experience prior to performing sampling activities.

• Document all results and include technician identification, methods used, and calibration records for equipment.

Phase 7 – Final Reporting & Closeout (Per Unit)

• Provide unit-specific reports using a standardized report format, including a unit-by-unit checklist documenting all completed work activities.

• Include photo documentation (before, during, and after work) for each room within each unit.

• Provide air and surface testing data tables, including baseline comparisons and clearance results.

• Submit recommendations for additional work if required.

• Complete final walkthrough.