B08_Attachment_6_Site_Visit_Notes_Q-A_Amendment_2_Summary_0002.pdf

PDF 229 KB Posted

Attached to
Rehabilitate Wolf Creek Water System, NPS-REDW
Solicitation number
140P8424R0005
Issued by

About this file

This document is a summary of a site visit and questions and answers related to a federal contract opportunity for the Rehabilitation of the Wolf Creek Water System at Redwood National and State Parks in California. The key details are:

The solicitation number is 140P8424R0005 and the project is for the Rehabilitation of the Wolf Creek Water System at Redwood National and State Parks in Del Norte County, California. A site visit was held on May 29, 2024 where potential contractors were able to view the project locations and ask questions. The solicitation includes a base bid and bid options. The base bid work involves installing approximately 1,330 linear feet of new 4-inch diameter water main, while the bid options include an additional 1,800 linear feet of new water main and other items. Responses to 33 questions covering topics such as existing conditions, construction methods, disposal of materials, and coordination with the Wolf Creek Education Center are provided. Amendment 0002 includes revisions to the bid schedule, drawings, and specifications.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REDWOOD NATIONAL

AND STATE PARKS

REHAB WOLF CREEK WATER SYSTEM

PMIS No. 309710

AMENDMENT NO. 0002

NATIONAL PARK SERVICE

PACIFIC WEST REGION

Solicitation 140P8424R0005, Attachment 6, Site Visit Notes, Q-A & Amendment 2 Summary

SITE VISIT SUMMARY:

A site visit was conducted on May 29, 2024. Participants met at 1:00 p.m. Pacific Daylight Time (PDT) at the Elk Prairie Campground Entrance Station near Orick, California. The project scope was reviewed at the meeting and potential contractors were given an opportunity to ask questions.

Potential contractors followed NPS and California Department of Parks and Recreation (CDPR) staff to existing points along the water line to observe visible appurtenances and project related infrastructure. Locations visited are listed below. Questions asked during the site visit were recorded and answered below. The site visit concluded at approximately 3:00 p.m.

Project locations visited (reference solicitation plans):

NPS water line “meter box” near connection to campground water line (STN 0+00) Access trail along buried water line STN 0+00 to 6+00, including potential staging areas shown on plans Existing overhead water line cross creek STN 6+00 Access trail along buried water line form Wolf Creek Education Center, to new “elbow” near STN 11+00, including potential staging areas shown on plans Exterior of existing water booster plant at end of water line in Bid Option 1 Existing “Humboldt crossing” where line branches from south of existing water booster plant to NPS staff housing

PROJECT QUESTIONS FROM SITE VISIT:

1. Question: What type and diameter is the existing buried water pipe? Answer: The water pipe is believed to be 4” diameter C900 PVC.

2. Question: Are as-built drawings available for the existing water booster plant plumbing?

Answer: As-built plans are provided as part of this Amendment 2.

3. Question: Is pipe bursting of the existing water line an allowable construction method for installation of the new line? Answer: Due to access and excavation limitations in wetland and stream areas, pipe bursting is not allowed for the base bid water line installation (STN 0+00 to 13+30). Pipe bursting is allowed for Bid Option 1 water line installation from the existing water booster plant building to station 13+30.

4. Question: Does vegetation that’s cut/cleared in staging areas or for construction access require haul and disposal off site? Answer: No. Light vegetation up to 1” diameter can be lopped and scattered in the forest adjacent to the cleared areas. Larger diameter vegetation can be hauled and disposed near the “Elbow” staging area at STN 11+00.

5. Question: What are the general construction hours and are there nesting bird restrictions?

Answer: Per specification 01 11 00, work shall generally be performed during normal business hours 8am to 5pm, Monday to Friday. Weekend work requires prior notification and coordination with NPS. If work is performed during the nesting bird season between March 24 and September 15, noise producing operations must occur between two hours after sunrise and two hours before sunset.

6. Question: Can campgrounds be closed for additional staging near the base bid water line connection to the campground water supply line? Answer: Yes. With prior coordination with NPS and CDPR, campgrounds 62, 63, 64, 65, 66, 67 & 68 can be closed for additional contractor staging such as pipe fusing along the campground paved road.

7. Question: Does the existing water line follow the planned path of the new water line throughout? Answer: Existing water line path varies slightly from new water line path.

Precise as-built information of the existing line is unavailable. Plans show the approximate location of the existing water line. This was reviewed again in preparation of Amendment 2 and the existing water line location has not been modified.

PROJECT QUESTIONS RECEIVED VIA EMAIL:

8. Question: Please provide as-built drawings for the booster plant with equipment descriptions? Answer: As-built plans are provided as part of this Amendment 2.

9. Question: On sheet C-004, the pipe to the booster pumps is disconnected at the outlet and the tee end is capped. This occurs on sheet C-009 for option 1. Please provide clarification on how the water system is fed if the booster pump system is taken off-line? Answer: In base bid, the system will be fed through supply line water pressure.

This is connected into the supply line system on C-004 at the 4”x6” increaser adjacent west of the treatment shed.

10. Question: Section 32 16 00 – 3.2 B states, “The furnishing and placing of topsoil shall be in accordance with Section 31 22 00“ Section 31 22 00 is not included in the technical specifications. Please clarify if topsoiling is required. Answer: Topsoiling is expected to be nominal, occurring only at areas of excavation. Section 31 22 00 is provided as part of this Amendment 2.

11. Question: Is the project award based on CLIN No. 1 through 15 or is it based on CLIN’s 1 through 23? Please clarify? Answer: Refer to Section M of the Solicitation which states, “Except when it is determined not to be in the Government’s best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).” See Sections H and M for additional information regarding the exercising of options.

12. Question: Section 31 12 33 - 3.3 A. details minimum trench width and depth if rock is encountered in the excavation. How is rock excavation paid for? Please clarify? Answer:

Excavation shall be paid for under CLIN 3 for the base bid and under CLIN 16 for Bid Option 1.

13. Question: Your attention is directed to sheet C-001. This is the project overview. The termination of the base bid is at station 13+30. Access to this end point is via Wolf Creek Road. Construction equipment and manpower will have to proceed and pass the Wolf Creek Education Center. Will classes be in session during the period of construction?

Answer: The Wolf Creek Education Center may be in use by NPS staff, partners and the public during the period of construction. NPS will coordinate construction access through the site during the period of construction. NPS staff will be present at the Wolf Creek Education Center to assist with this coordination during the period of construction.

14. Question: In reference to previous question #13, if the Wolf Creek Education Center is in session what construction constraints apply? Working hour restrictions? May we excavate around the education center while the center is occupied? There are fire services to be placed at the center. Please clarify. Answer: See answer to site visit question #5 regarding construction hours.These hours and restrictions apply to work around the Education Center. NPS will coordinate occupancy at the Education Center based on the contractor’s construction schedule. NPS will coordinate fire protection of facilities during construction periods when plumbed fire services are taken offline for construction.

15. Question: In the bid schedule, CLIN No. 14 is Water System Pressure Testing. This CLIN is under the base bid. Under the option bid schedule there is no CLIN for Water System Pressure Testing. How is pressure testing paid for under option 1 of the project?

Please clarify? Answer: Pressure testing for the entire project, including Bid Option 1, shall be included under CLIN 14. Specification 01 27 00 incorrectly flip-flopped CLIN 13 & 14. This has been corrected in revised specifications provided with this Amendment 2.

16. Question: Your attention is directed to section 33 11 00 -1.2.3 “Horizontal Directional Drilling Plan.” There it states, Work plans must be stamped and signed by an engineer who is registered as a civil engineer in the State. This requirement is cost prohibitive as prime contractors as well as, directional drilling contractors do NOT have professional Engineers on staff. Please eliminate a plan stamped and signed by an engineer who is registered as a civil engineer in the State? Answer: Utility Horizontal Directional Drilling specifications footer incorrectly numbered for this section. The section footer has been updated to 33 05 23 in this amendment. Engineer stamping requirement of section 1.2.3 has been removed. See specification section 33 05 23 for revisions to section 1.2.3 and subparts. Also see revisions to part 3.2.1.1 and 3.5-A.

17. Question: Your attention is directed to section 33 11 00 – 3.2.8 “Drilling Fluids Disposal.”

There it states, drilling fluids and cuttings must be collected and disposed off-site at an applicable State approved collection facility. Because our drilling fluid is NSF 60 approved and after adequate drying, the soils can be used as trench backfill. Please eliminate off site disposal and allow drilling fluids to remain on site? Answer: Due to the sensitive environment of the park lands on which this project is located, off-site disposal per section 33 11 00 – 3.2.8 is required.

18. Question: If the option is awarded and the contractor selects an open cut method of construction, there will be spoils (excess dirt from trench excavation) due to sand bedding placed in the ditch. Can these spoils remain on-site? Answer: Yes, trench & excavation spoils can be piled in a designated space near the water booster building.

Final location will be coordinated by NPS. Approximate location has been added to sheet C-007 of this amendment.

19. Question: The new water system connects to existing on sheet C-002. What size is the existing water main there? Please provide a connection detail on the construction drawings? Answer: Existing water main is believed to be 4” C900. Connection to be in conformance with specification 33 11 00.

20. Question: There are two new future fire water services as shown on sheet C-007. How do these two future fire service water lines connect to the housing units? For example, in a fire riser or are they capped for future connection? Answer: Water service branch towards south NPS facilities on C-007 has been removed from project scope. See revised sheet C-007 as part of Amendment 2.

21. Question: In the solicitation, liquidated damages for not completing the project within the period of performance is not given. What are liquidated damages for not completing on time? Answer: Liquidated damages do not apply to this project.

22. Question: For the bid bond, can this be covered by my subcontractor if they can prove they are capable? Answer: No, all bonds must be supplied by the prime contractor.

23. Question: For Volume I, Technical Proposal, Factor 2, is a copy of our subcontractor's California Contractor State License alone sufficient to fulfill this requirement? Answer:

Please review the Solicitation, specifically Section L instructions and corresponding Section M evaluation factors. Section L instructs offerors to submit a copy of the current California Contractor State License classification such as “A” (General Engineering Contractor), “C-34” (Pipeline Contractor), or other classification that is applicable to the work the Offeror, and any proposed subcontractor(s), will be performing on this project (describe in detail in your proposal). Any prime contractor and/or subcontractor that will be performing horizontal directional drilling work shall be required to possess a current C-34 license classification. There is no preprinted form for this submittal. Section M states, among other things, that offerors who possess a current and valid State License applicable to the work they will be performing on this project will be more favorably rated.

24. Question: There is a stream crossing that was discovered during the site visit that is not shown on sheet C-007. Please advise what is to be done at the “Humbolt Stream Crossing”? Answer: Water service branch towards south NPS facilities on C-007 has been removed from project scope. See revised sheet C-007 as part of Amendment 2.

25. Question: There are two fire hydrants south of the classroom building that are not shown on the drawings. Please clarify what is to be done with the two existing fire hydrants not shown Answer: Hydrants are to be connected into new system as part of Bid Option 1.

See revised sheet C-008 now showing these two hydrants in lieu of new hydrants in the area.

26. Question: During the site visit, it was mentioned that the existing 4” line from stations 6+00 to 12+00 is potentially not shown in the correct location. Please provide location of existing piping in the above-mentioned locations. Answer: See response to site visit question #7.

27. Question: Clearing operations will be required to gain access to staging areas from station 0+00 to 13+13. Will slash and debris from clearing operations be allowed to broadcast into the forest or will they need to be hauled off site? Answer: Light vegetation up to 1” diameter can be lopped and scattered in the forest adjacent to the cleared areas. Larger diameter vegetation can be hauled and disposed near the “Elbow” staging area at STN 11+00.

28. Question: In order to set up for pipe bursting and HDD operations, long lengths of piping will need to be pre-fused which will impede into several campsites near station 0+00 and block the roadway from visitors. Will it be possible to close down the campground loop closest to station 0+00 during the construction period? Answer: Yes. With prior coordination with NPS and CDPR, campgrounds 62, 63, 64, 65, 66, 67 & 68 can be closed for additional contractor staging such as pipe fusing along the campground paved road.

29. Question: Note 1 on sheet C-002 states that HDD is required from station 3+30 to station 13+13. During the site visit it was mentioned that a portion of that could be completed utilizing pipe bursting methods. Please clarify what areas, if any, are allowed to be pipe burst between stations 3+30 and 13+13? Answer: See response to site visit question #3.

30. Question: Can clarification be provided on question 2 of the Project Experience Questionnaire: Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses. Section L doesn’t appear to address project elements. Is this the correct reference section? Answer: Question 2 of the Project Experience Questionnaire is addressing the bulleted elements listed in the Solicitation Section L, specifically E.3, Factor 1.

31. Question: Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? Answer: No, the positions do not have to be separate individuals.

32. Question: Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? Answer: Refer to FAR clause 52.211-10 within the solicitation which states that the firm end date for performance is October 31, 2025. This completion date is based on the assumption that the successful offeror will receive the notice to proceed by September 1, 2024.

33. Question: Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions. Answer: Soil boring reports are not available.

Excavations and HDD paths could encounter obstructions. Reference specifications for additional information on obstructions including 31 05 33 and 33 05 23.

SUMMARY OF AMENDMENT 0002 ITEMS:

The offeror shall make the following changes, modifications and additions to the pertinent sheets, pages and paragraphs of the specifications and drawings, and shall take the same into consideration in the proposed prices:

1. Revised Bid Schedule (see Section B of the updated provisions and clauses document and/or updated Microsoft Excel Bid Schedule form)

a. Adjusted Base Bid CLIN 4, 4” Gate Valve, down to 2 EA

b. Adjusted Option CLIN 16, 4” HDPE Water Main, down to 1800 LF

c. Adjusted Option CLIN 17, 4” Gate Valve, up to 3 EA

d. Adjusted Option CLIN 20, 4” x 6” Increaser, up to 2 EA

e. Adjusted Option CLIN 21, Fire Service Connection, up to 4 EA

f. Removed Option CLIN 22

2. Revised project drawings, see clouded items:

a. C-002

b. C-003

c. C-007

d. C-008

3. Revised specification sections

a. 01 27 00:

3.1.C, CLIN 0003, clarified includes excavation and backfill 3.1.M & 3.1.N, reversed order to match bid schedule Bid Option 1, G, CLIN 0022 removed

b. 31 22 00: Topsoiling and Finished Grading, section added

c. 33 05 23: Utility Horizontal Directional Drilling

Footer numbering corrected 1.2.3, engineering stamping requirement removed 1.2.3, section revised, including subparts 3.2.1.1, revised 3.2.5, Guidance Systems, revised 3.5-A, revised

4. As-built plans

a. 1997 As-built Plans

5. Updated provisions and clauses

a. Section B (Bid Schedule) is revised as described above in 1.

b. Section G is updated as follows:

Update date of IPP Clause (FEB 2021)

c. Section I is updated as follows:

Remove FAR 52.204-4, Printed or Copied Double Sided on Postconsumer Fiber Content Paper (MAY 2011)

Add full-text version of FAR 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (NOV 2021)

Update date of FAR 52.219-6, Notice of Total Small Business Set-Aside

(NOV 2020)

Update date of FAR 52.219-8, Utilization of Small Business Concerns

(SEP 2023)

Update date of FAR 52.219-28, Post Award Small Business Program Rerepresentation (SEP 2023)

Moved from full text to Incorporate by Reference (IBR): FAR 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020)

Update date of FAR 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2024)

Delete 52.223-6, Drug-Free Workplace (MAY 2001) and replace with 52.226-7, Drug-Free Workplace (MAY 2024)

Delete 52.223-15, Energy Efficiency in Energy-Consuming Products

(MAY 2020)

Delete 52.223-17, Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (Aug 2018)

Delete 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) and replace with 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While Driving

(MAY 2024)

Update date of 52.223-21, Foams (MAY 2024) Delete 52.228-11, Individual Surety—Pledges of Assets (FEB 2021) from

IBR and replace with full-text version of 52.228-11, Individual Surety— Pledges of Assets (FEB 2021) (DEVIATION MAY 2023)

Delete 52.228-15, Performance and Payment Bonds-Construction (JUN 2020) from IBR and replace with full-text version of 52.228-15, Performance and Payment Bonds-Construction (JUN 2020)

(DEVIATION MAY 2023)

Update FAR 52.244-6, Subcontracts for Commercial Products and Commercial Services (FEB 2024)

Add full-text FAR 52.252-6, Authorized Deviations in Clauses (NOV 2020)

d. Section J is updated to include the following new attachments:

B08_Attachment_1_Specifications_Amendment_2.pdf

B08_Attachment_2_Drawings_Amendment_2.pdf B08_Attachment_3_Wage_Determination_24May2024.pdf B08_Attachment_5_Site Visit Sign-In Sheet.pdf B08_Attachment_6_Site Visit Notes_Q-A_Amendment_2_Summary.pdf B08_Attachment_7_1997 Wolf Creek As-Built.pdf B08_Attachment_8_Vol_II_CBS_Amendment_2.xlsx B08_Attachment_9_140P8424R0005_Provisions_and_Clauses_Rev_1

8Jun2024.pdf

e. Section K is updated as follows:

Update FAR 52.204-8, Annual Representations and Certifications (MAY 2024)

f. Section L is updated as follows:

Minor language updated for clarity Add full-text version of FAR 52.201-1, Acquisition 360: Voluntary Survey

(SEP 2023)