Point Reyes National Seashore

Water Well

Questions and Answers

140P8423Q0055

1. Water source – do we have a source on site?

• Spigots are available at the treatment shed at the site. Hydrants are available near the site but will require a water truck.

2. Fluid disposal – can drill and development fluid be discharged on-site?

• All fluids and muds are to be contained by the contractor and removed off-site.

3. Drill cuttings – can drill cuttings be disposed of on-site?

• Drill cuttings are to be contained by the contractor and removed off-site.

4. Timeline – what is the timeline for start and completion?

• We are generally expecting to start the project on 8/7/23 and end it on 11/7/23.