140P8422Q0130_Attach_06_Q_A_0002.docx

DOCX document 15 KB Posted

Attached to
Remove & Replace Decking at Channel Islands NP
Solicitation number
140P8422Q0130
Issued by

View the file

Other files

File Type Posted
Sol_140P8422Q0130_Amd_0002.pdf PDF
140P8422Q0130_Attach_05_Site_Visit_Sign_In_Sheet_0002.docx DOCX document
Sol_140P8422Q0130_Amd_0001.pdf PDF
Attach_04_Technical_Information_Form.pdf PDF
Attach_03_Wage_Determination.pdf PDF
Attach_02_Site_Map.pdf PDF
Sol_140P8422Q0130.pdf PDF
Attach_01_Specifications.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P8422Q0130 Replace Decking at Headquarters and Visitor Center Channel Islands National Park

Attachment 06: Questions & Answers

Q1: Can one Supervisor administer all three hats? (Superintendent, Site Safety Health Officer, and Quality Control Manager?)

A1: Yes, provided all contract requirements are met

Q2: Will the project be phased? If so, how many phases? KTR recommends entire outdoor area in 1 phase and indoor area 2 phases. Will this phase plan be acceptable?

A2: Preference is for the project be phased, as this will allow for parts of the Visitors Center to remain open while work continues with minimal interruption to visitor services.

Q3: What will be hours for KTR to work? KTR suggests 4 10-hour shifts Monday-Thursday from 0600-1400. Will this be acceptable?

A3: 10hr days Mon- Thurs pare permissible, however 0600-1400 is an 8hr day. The start time is suggested to be 0700-17:30 as the will be no NPS on site prior to this time.