Att 02_P8418R0006_Project Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8418R0006_Amd_0002.pdf | ||
| Att_13_P8418R0006_Provisions_and_Clauses_revised_2018-Aug-02.pdf | ||
| Att_12_P8418R0006_Spec_Section_230100_revised_2018-Aug-02.pdf | ||
| Att_10_P8418R0006_Site_Visit_Sign_In_Sheet.pdf | ||
| Att_11_P8418R0006_Site_Visit_Notes-Q-A.pdf | ||
| Sol_140P8418R0006_Amd_0001.pdf | ||
| Att_08_P8418R0006_PP-Questionnaire.docx | DOCX document | |
| Att_01_P8418R0006_Bid_Schedule.pdf | ||
| Sol_140P8418R0006.pdf | ||
| Att_07_P8418R0006_Key_Personnel_Form.docx | DOCX document | |
| Att_03_P8418R0006_Construction_Drawings.pdf | ||
| Att_04_P8418R0006_Test-Balance-Report.pdf | ||
| Att_05_P8418R0006_Wage_Rates.pdf | ||
| Att_09_P8418R0006_SF-24_Bid_Bond.pdf | ||
| Att_06_P8418R0006_Relevant_Experience_Form.docx | DOCX document |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
NATIONAL PARK SERVICE – PWR SAN FRANCISCO
SAN FRANCISCO, CALIFORNIA
Bear Valley Visitor Center Heating System Rehabilitation
Point Reyes National Seashore / NPS PMIS #208882 – Point Reyes, California
FINAL SPECIFICATIONS
April 30, 2018
JOSEPH CHOW & ASSOCIATES, INC.
650 Delancey Street, Suite 211 – San Francisco, California 94107 Tel. 415.777.1288 ● Fax. 415.777.2552 ● www.jcaarchitects.com
BEAR VALLEY VISITOR CENTER TABLE OF CONTENTS
HEATING SYSTEM REHABILITATION
Pore #208882 Table of Contents - Page 1 of 2
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS NO. OF PAGES
01 11 00 Summary of Work 01 11 40 Work Restrictions 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 33 23 Submittal Procedures 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities & Controls 01 73 40 Execution 01 77 00 Closeout Procedures
DIVISION 02 - 22
Not used.
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
23 01 00 Mechanical General Site Construction Requirements 23 05 00 Basic Materials and Methods 23 05 13 Motors and Motor Controllers 23 05 29 Support and Anchors 23 05 48 Noise, Vibration, and Seismic Control 23 05 93 Tests and Balancing 23 07 00 Insulation 23 31 00 Ductwork 23 33 19 Sound Attenuators 23 34 00 Fans 23 40 00 Air Filters 23 54 00 Furnaces
DIVISION 25 – CONTROLS
25 00 00 Controls – General Conditions 25 10 00A Building Management System (BMS) 25 30 00 Building Management System Field Devices 25 90 00 Sequence Of Operations
DIVISION 26 – ELECTRICAL
26 05 01 Electrical General Provisions 26 05 02 Equipment Connections and Coordination 26 05 19 600V Wire and Cable
BEAR VALLEY VISITOR CENTER TABLE OF CONTENTS
Pore #208882 Table of Contents - Page 2 of 2
26 05 33 Raceways and Boxes 26 27 26 Wiring Devices
BEAR VALLEY VISITOR CENTER GENERAL REQUIREMENTS
PORE #208882 General Requirements - Page 1 of 13
DIVISION 01
GENERAL REQUIREMENTS
PART 1 - SUMMARY OF WORK - SECTION 01 11 00
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. General: All work outlined below will be performed under a single contract.
B. Project Location: This project is located at Point Reyes National Seashore, Point Reyes Station, California.
C. Project Background: This project will rehabilitate and replace critical components of the Bear
Valley Visitor Center heating system including liquid propane (LP) gas furnaces and related appurtenances. The building, built circa 1983, has the original dual-furnace system designed to heat some (but not all) of the building envelope. This project focuses on the replacement of the furnaces with similar units to provide more efficient and even heating. Currently, the two 50,000-Btu Hastings furnaces are not operating with heat provided by electric space heaters and a wood-burning stove. The system also consists of intake fans at both furnaces as well as two recirculation fans at the upper clerestory. In addition, individual system deficiencies and other components will be replaced as noted later in this document.
D. Project Scope of Work: The Work consists of providing all materials and labor to provide for a complete operating heating and ventilating system per attached drawings and specifications including the following tasks:
1. Replace the existing propane gas furnaces with standard-efficiency, code-compliant LP gas furnaces and all accessory parts and equipment per design.
2. Recommission and rebalance the existing duct system and remove/replace existing ducting as noted.
3. Replace the existing controls with new wireless controls (base bid) direct digital controls (DDC) also known as a building management system (BMS). – Or, as a deductive item, provide Visual-Logic Display (VLD) instead of a wireless equipment controller.
4. Increase positive control of outside air to pressurize the building and balance restroom exhaust quantities, with minimum outside air damper settings.
5. Add two more diffusers to the shortened supply duct in the auditorium and adjust airflow.
6. Replace and install new exhaust fans in the public restrooms.
7. Install new exhaust fan for the projection room to control excess temperatures.
8. Provide acoustically treated transfer air openings to the restrooms for passive heating/make-up air from the exhibit area.
9. Provide an electric heat mat behind the visitor center information desk.
10. Replace the stratification fans S-3 and S-4 with new and provide new sound attenuators SA-1 and SA-2, and duct work and support. Paint to match existing ducting. – Or as a deductive item, provide preventive maintenance and repairs to improve sound attenuation of the stratification fans to allow improved operation.
PORE #208882 General Requirements - Page 2 of 13
11. Provide preventive maintenance and repairs to improve operation of motor-controlled clerestory windows.
12. Extend the propane system to a new exhibit area and replace the existing wood-burning stove with new LP gas stove.
1.2 REFERENCE DOCUMENTS / REPORTS
A. General: The following reference documents/reports are attached or available upon request to supplement the information in the specifications:
1. NPS Forms (RFI, CM-16, and QC Daily Report)
2. Design drawings #612-138999
1.3 GOVERNMENT-FURNISHED ITEMS
A. The Government may furnish products and materials for incorporation into the work.
1. The government will arrange and pay for delivery of government furnished items to the project site based on the contractor’s approved construction schedule.
2. After delivery, the government will inspect delivered items for damage. If items are damaged, defective, or missing, the government will arrange for replacement.
3. The contractor is responsible for receiving, unloading, and handling government furnished items at project site for use in the work.
4. The contractor is responsible for protecting government furnished items during storage, handling, and the work, including damage from exposure to the elements.
5. If government furnished items are damaged as a result of the contractor’s operations, the contractor shall repair or replace the items in-kind.
B. Government-Furnished Items: The government will furnish the following products or materials for use on this contract: None
1. Duct Testing and Balance Report by Pacific Test & Balance, Inc. (August 2017)
2. AutoCAD files of original building project will be provided to successful bidder upon request.
1.4 PUBLIC / STAFF USE OF THE SITE
A. General: The project site will be open to the public and staff during construction. The contractor shall at all times conduct his operations to ensure the least inconvenience to the public and staff. Temporary closures may be permitted upon specific written approval of the Contracting Officer.
1.5 CONTRACTOR USE OF SITE
PORE #208882 General Requirements - Page 3 of 13
A. General: Limit use of the site during the construction period to the immediate building area where work is required. The Visitor Center is open every day from 10:00 a.m. to 5:00 p.m.
From November 4, to early March the hours are 10:00 a.m. to 4:30 p.m. Provide schedule of expected “restricted access” (number of days/dates) to the building by the general public for safety reasons. Provide estimated schedule of expected power interruptions.
B. Park Regulations: Ensure all personnel (contractors, subcontractors, and vendors) entering or working in the park are familiar with and obey all park regulations. Law enforcement rangers will intervene if they perceive any unsafe or unlawful activity.
C. Park Entry: Vehicles associated with the Contractor shall be waived the entrance fee upon entering in a marked company vehicle or by providing the names of employees entering in personal vehicle(s). Please note that the entrance fee is waived only for the purpose of reporting directly to a specific work location. Any deviation for recreational purposes is subject to payment of required entrance fees.
1. Provide the Contracting Officer with a listing of all contract personnel and their associated vehicles entering the park on a daily basis.
2. Provide the Contracting Officer with a listing of anticipated deliveries for each week.
D. Site Access: The contractor shall access the project site as outlined on the drawings. Do not drive vehicles off road or access non-project areas without permission from the contracting officer or their representative.
E. Working Hours: Regular work hours shall be limited to daylight hours from 7:00 am until 5:00 pm Monday through Friday, excluding government holidays. Work outside regular hours requires approval from the contracting officer.
F. Staging and Storage: Confine the storage of equipment and materials to the staging / lay-down / storage areas as established at the preconstruction meeting.
G. Property Damage: The Contractor is required to report missing, lost, stolen, or damaged property occurring within the park. This report must be made to a Law Enforcement Ranger or Park Dispatch at the first available opportunity at 415-464-5170.
H. No Smoking Policy: Smoking is prohibited inside or outside within 25 feet of any buildings in the park. This applies to existing buildings and buildings under construction or renovation.
Discarding of tobacco products or debris anywhere other than into designated tobacco receptacles is considered littering and subject to fines.
PART 2 – WORK RESTRICTIONS (SECTION 01 11 40)
2.1 WORK RESTRICTIONS
A. General: The Contractor must comply with the following work restrictions:
B. Vehicles / Heavy Equipment:
PORE #208882 General Requirements - Page 4 of 13
1. Rules of the Road: All vehicles and heavy equipment will comply with posted traffic regulations, including speed limits and double-yellow center lane markings. Vehicles and heavy equipment shall take every safe opportunity to use paved roadside pullouts in order to allow faster moving traffic to pass. Failure to comply with traffic regulations will result in a citation being issued to the driver.
2. Vehicle Parking: The contractor shall park vehicles and heavy equipment in designated areas as established at the preconstruction meeting. Vehicles are not permitted within long-term or overnight parking along park roads or in associated overlooks / pullouts.
3. Driveways and Entrances: The contractor shall keep driveways and entrances serving the premises clear and available to the government, government employees, and emergency vehicles at all times.
4. Vehicle Exhaust: All vehicles will be properly maintained to ensure that the exhaust produced is within legal limits. Effects of excessive vehicle exhaust may be subject to enforcement of State and Federal laws regarding emissions as well as those regarding threatened and endangered species.
5. Spills: The Contractor shall be responsible for any cleanup efforts required in accordance with 40 CFR and all applicable state environmental quality laws regarding disposal and cleanup of hazardous / industrial wastes. Contractor must immediately notify the Contracting Officer of spills.
6. DOT Compliance: All vehicles are to be compliant with all DOT requirements including but not limited to driver with appropriate license class, medical examiner card as appropriate with license class, carrying three (3) triangles or three (3) flares, mounted fire extinguisher, and valid DOT safety sticker.
7. Slow Vehicles: The Contractor is to notify the Contracting Officer of slow vehicles that may cause traffic delays or extended traffic lines. Vehicles that are slow are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
8. Oversized Vehicles: Oversized vehicles are defined as vehicles where the width of the vehicle or load exceeds one lane (i.e., beyond the center line of the paved road).
Oversized vehicles must not exceed the clearances along the Park road corridor.
Oversized vehicles will require an escort and drivers must avoid driving on the edges of the Park road. The Contractor is to notify the Contracting Officer of oversized vehicles, scheduled dates, and estimated arrival times at the park entrance; and the identity of who is escorting the vehicle (e.g., police, contractor, etc.). Vehicles that are oversized are requested to enter the Park AFTER 2:00 p.m. and exit the Park BEFORE sunset.
9. Road & Weight Restrictions: All vehicle load, weight, and size limitations, as established by State law, apply to vehicles operated on the Park road (36 CFR § 4.11).
No loads heavier than the current load rating for park roads and bridges will be permitted.
C. Resource Protection:
1. General: The Park is committed to protecting natural and cultural resources found within the park and adjacent lands. The Contractor must comply with the following rules and conditions:
PORE #208882 General Requirements - Page 5 of 13
2. Preservation of Natural Features: Prevent damage to natural surroundings. Do not attach ropes, wires, guy lines, cables, or chains to trees or vegetation. Restore damaged areas and replace damaged trees, vegetation, and grass at no expense to the government.
3. Invasive Species: The introduction of non-native invasive species can threaten rare and endangered species or can create new populations of non-native species not traditionally found in the park. The contractor is required to inform personnel, subcontractors, and vendors to thoroughly clean all vehicles (especially the tires), equipment, tools, supplies, and materials prior to packing / loading. The park requires and will perform inspections to prevent transport of non-native species PRIOR to arriving at the park entrance.
Contact the Equipment Inspector David Demko at 415-464-5151 at least (1) one day in advance of park entry to arrange for inspection(s) at the loading dock or point of origin.
4. Endangered Species: Endangered species are protected by Federal law. Obey all park regulations. Drivers must obey all traffic laws and watch for animals on or alongside road or at the jobsite. Contact Park Dispatch at 415-464-5170 immediately if animal is hit or injured or will not move off the road.
The following measures are required to minimize disturbance to endangered wildlife:
a. Work shall be conducted to ensure the work area is cleaned up at the end of each work shift so that loose tools, debris, and materials are not left out in a manner that could present a hazard to a listed species.
b. Noise and vibrations of equipment shall be kept to a minimum when working in the vicinity of a listed species.
c. Hazmat spill prevention protocols shall be employed when using gas-powered equipment.
d. Tarps shall be used to contain all paint chips and building debris from exterior surfaces that may fall to the ground.
e. Ensure loose nails and screws do not make it to the ground when working on exterior surfaces as these can be detrimental to listed species.
5. Archaeological Resources: Archaeological resources are physical evidence of past human activity, including evidence of the effects of that activity on the environment.
Archaeological resources are found above and below ground and underwater. The Contractor’s Project Superintendent, or designee, will observe all ground-disturbing activities in archaeological sensitive areas. If the Contractor discovers resources, the Contractor shall stop work or relocate to a non-sensitive area and contact the Contracting Officer immediately. The Park may also have an Archaeological Monitor at the jobsite who is authorized to stop work upon discovery of archaeological resources.
Archaeological resources typically found in the park or at the project site will be discussed further at the preconstruction meeting.
PORE #208882 General Requirements - Page 6 of 13
6. Soundscape / Noise: The contractor shall minimize noise levels at the project site to protect the soundscape of the park. Perform noise-producing work in less sensitive hours of the day or week or as directed by the contracting officer.
PART 3 – DEFINITION OF CONTRACT LINE ITEMS (SECTION 01 27 00)
3.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
3.2 PRODUCTS (Not Used)
3.3 EXECUTION - LIST OF CONTRACT LINE ITEMS
3.3.1 Contract Line Item No. 1 – Base Bid
3.3.1.1 This bid item consists of the following work:
1. Replace the existing propane gas furnaces with standard-efficiency, code-compliant LP gas furnaces and all accessory parts and equipment per design.
2. Demolish ductwork and provide new ductwork in selected areas as shown on the plans.
3. Recommission and rebalance the existing duct systems per the air flows shown on the plans.
4. Replace the existing controls with new wireless controls (base bid) direct digital controls (DDC) also known as a building management system
(BMS).
5. Increase positive control of outside air to pressurize the building and balance restroom exhaust quantities, with minimum outside air damper settings.
6. At the Auditorium, replace the two existing sidewall supply grilles with new as shown on plan. The existing ductwork in the Auditorium is to remain.
7. Replace and install new exhaust fans in the public restrooms.
8. Install new exhaust fan in Control Room 105 to control excess temperature.
9. Provide acoustically treated transfer air openings to the public restrooms from the Exhibit Spaces for passive heating/make-up air.
10. Provide custom-fit electric heat mat behind the information desk.
11. Provide new propane service and a new gas stove with remote-control thermostat to replace the existing wood-burning stove.
12. Refurbish the two existing supply fans in the attic and replace their motors with new.
13. Replace the two existing VAV terminals and replace with a new dual-duct
VAV terminal.
14. Replace the stratification fans S-3 and S-4 with new and provide new sound attenuators SA-1 and SA-2, and duct work and support. Paint to match existing ducting.
PORE #208882 General Requirements - Page 7 of 13
15. Clean and lubricate motors that control clerestory windows (14 total windows with 2 motors). Note that this work item is not noted on plans and in Specifications and windows currently operate well. Perform at least the following services to all of the windows: clean both sides of windows (work from interior only); inspect, clean, and lubricate remote sash operator components and related parts driven by motors.
3.3.1.2 No separate measurement will be made.
3.3.1.3 Payment will be made at the contract lump sum price.
3.3.2 Contract Line Item No. 2 – Deductive Item #1
3.3.2.1 This bid item consists of the following work:
1. No upgrade to the existing stratification system (except provide preventive maintenance and repairs to improve sound attenuation of the de-stratification fans to allow improved operation).
2. Delete SA-1, SA-2, VFD-S-3, VFD-S-4 and associated electrical wiring from the scope of work.
3. Controls (refer to Sheets M7.1, M7.2 and M7.3): Delete the BMS wireless main controller.
a. Control all exhaust fans with load-rated programmable electronic timers instead of a BMS.
b. Control S-1/F-1 with an “Alerton” Visual-Logic Display (VLD) instead of a BMS.
c. Control S-2/F-2 with an “Alerton” Visual-Logic Display (VLD) instead of a BMS.
3.3.2.2 No separate measurement will be made.
3.3.2.3 Payment will be made at the contract lump sum price.
3.3.3 Contract Line Item No. 2 – Deductive Item #2
3.3.3.1 This bid item consists of the following work:
1. Controls (refer to Sheets M7.1, M7.2 and M7.3): Delete the BMS wireless main controller.
a. Control all exhaust fans with load-rated programmable electronic timers instead a wireless equipment controller.
b. Control S-1/F-1 with an “Alerton” Visual-Logic Display (VLD) instead of a wireless equipment controller.
c. Control S-2/F-2 with an “Alerton” Visual-Logic Display (VLD) instead of a wireless equipment controller.
3.3.2.4 No separate measurement will be made.
3.3.2.5 Payment will be made at the contract lump sum price.
PART 4 – PROJECT MANAGEMENT (SECTION 01 31 00)
4.1 SUBMITTALS
A. Division 01 Submittal Documents: The following documents shall be submitted a minimum of one week prior to the Preconstruction Meeting. If all of these documents have not been received one week prior to the scheduled Preconstruction Meeting date, the meeting will be
PORE #208882 General Requirements - Page 8 of 13 cancelled and the Notice to Proceed (NTP) will not be issued. Work shall not commence until written Notice to Proceed has been issued.
1. Letter designating the Project Superintendent.
2. Construction Schedule - Submit a baseline schedule with start date, end date, major work activities and durations, estimated pre-final inspection date, and other major milestones.
Provide updates to baseline schedule as needed / requested during construction.
3. Schedule of Values (SOV) – Submit a schedule of values with a breakdown of component work activities for which progress payments will be requested. The total costs for the component work activities shall equal the total contract price.
4. Accident Prevention Plan (APP) – Submit an accident prevention plan with the name of the supervisor responsible for executing the plan, a job hazard analysis for each major work activity, first aid procedures, and planning for potential emergency situations.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
B. Division 02-49 Submittal Documents: The following documents shall be submitted to the Contracting Officer prior to construction start. If these documents have not been received and approved by the NPS prior to construction, the construction start date may be delayed.
1. Product Data – Submit product cut sheets / material data on all products to be used for approval. Indicate the size, model, or type of each recommended product.
2. Samples – When requested, submit a physical sample of a product or an array of color choices for approval.
3. Shop Drawings - Submit shop drawings that embody all major elements of the work.
a. Drawings shall be developed in AutoCAD or similar drafting software.
b. Drawings shall include details, dimensions, notational information and other data to ensure the contractor has a complete understanding of the work.
c. Drawings shall be submitted to the Contracting Officer in PDF format. Allow 2 weeks for the drawings to be reviewed by NPS staff. The Contractor shall incorporate review comments into the shop drawings and resubmit for final approval.
4.2 PRE-CONSTRUCTION MEETING
A. Preconstruction Meeting: Before the start of construction, the Contracting Officer will arrange for a preconstruction meeting either on site or via teleconference. The meeting agenda will include the following topics:
1. NPS Roles & Responsibilities
PORE #208882 General Requirements - Page 9 of 13
2. Key Contractor Personnel
3. Coordination with Subcontractors
4. Correspondence & Submittal Procedures
5. Submittals
a. Status of Division 01 Submittals
b. Schedule & SOV
c. Safety & Accident Prevention Plan
d. Storm Water Pollution Prevention Plan
e. Status of Division 02-49 Submittals
6. Park Rules & Regulations
7. Work Hours and Weekend, Holiday, and Night Work
8. Project Information
a. Park Access & Vehicle Reporting
b. Jobsite Access & Parking
c. Staging, Storage, and Lay Down Area(s)
d. Temporary Facilities & Controls
e. Jobsite Restrictions
f. Resource Protection
g. Weather, Climate, Environmental Conditions
h. Reference Documents
i. Other Contracts / Ongoing Work
9. Labor Standards Provisions
10. Labor Interviews
11. Payroll Reports
12. Payments to the Contractor
13. Change Orders / Modifications
14. Progress Meetings
15. QC Daily Reports
16. Inspections
17. Acceptance and Rejection of Work
18. Closeout Procedures & Submittals
19. Contract Period of Performance
20. Notice to Proceed
4.3 REQUESTS FOR INFORMATION (RFIs)
A. General: On discovery of the need for additional information or interpretation of the Contract Documents, the Contractor shall prepare and submit a RFI utilizing the form attached.
1. Contracting Officer will only respond to RFIs submitted by the Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. RFI Form: Include a detailed, legible description of the subject or item needing information or interpretation on the RFI Form with:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, if applicable.
6. Photographs or sketches if applicable.
PORE #208882 General Requirements - Page 10 of 13
7. Contractor's suggested resolution. If the Contractor's suggested resolution impacts the contract time or the contract sum, Contractor shall state impact in the RFI.
C. Response to the RFI: The Contracting Officer will review each RFI, determine the action required, and respond accordingly.
PART 5 – SUBMITTAL PROCEDURES (SECTION 01 33 23)
5.1 SUBMITTAL PROCEDURES
A. CM-16 Transmittal Form: All submittals shall be transmitted using National Park Service CM- 16 form attached to the end of this specification section. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Complete all applicable fields, sign the form, and attach all supporting documentation.
PART 6 – SAFETY REQUIREMENTS (SECTION 01 35 23)
6.1 SAFETY REQUIREMENTS
1. First Aid Equipment: Provide adequate first aid equipment for all contract employees and the hazards associated with the types of ongoing construction work at the site.
2. First Aid Training: Provide adequate training to all Contractor personnel to ensure prompt and efficient application of first aid.
3. Personal Protective Equipment (PPE): Provide personal protective equipment (PPE) that meets applicable OSHA and ANSI standards for all contract employees.
4. Hazardous Materials: Hazardous materials are defined as explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury. Store hazardous materials in accordance with manufacturer’s and OSHA recommendations. Maintain MSDS onsite for each chemical used on the jobsite.
Immediately report all spills of hazardous materials to the contracting officer.
5. Safety Meetings: At a minimum, conduct weekly "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the week.
6. Emergency Contacts: Post telephone numbers and reporting instructions for ambulance, hospital, fire department, police, and park dispatch in conspicuous locations at the site.
7. Emergency Reporting: In the event of an emergency medical incident, the Contractor shall Dial 911 as needed. The Contractor shall also contact Park Dispatch at 415-464-5170 for any medical emergency, traffic accident, or personal injury occurring within the Park. Park Dispatch is called so that the entrance station will be prepared should any emergency vehicles need to enter the Park and so that any available Emergency Medical Services personnel in the Park might respond until such time as the ambulance arrives.
PART 7 – QUALITY REQUIREMENTS (SECTION 01 40 00)
PORE #208882 General Requirements - Page 11 of 13
7.1 QUALITY REQUIREMENTS
C. General: The Contractor is responsible for all quality control to guard against defects and deficiencies in the work. Inspect and test work as needed to ensure that the quality of materials, workmanship, construction, finishes, and functional performance are in compliance with applicable specifications, drawings, building codes and standards.
D. Quality Control (QC) Daily Reports: Submit quality control daily reports documenting the progress and quality of the work. The Contractor’s Quality Control Supervisor shall utilize the forms attached at the end of this Section. The submission frequency of the QC Daily Report to the contracting officer will be determined at the preconstruction meeting.
PART 8 – TEMPORARY FACILITIES & CONTROLS (SECTION 01 50 00)
8.1 TEMPORARY FACILITIES & CONTROLS
A. General: The contractor will be allowed to set up temporary facilities and controls as outlined. All temporary facilities and controls shall be removed from the site before final acceptance of the work.
B. Temporary Utilities: The following utilities / services are available for use at the project site:
1. Electrical Power Service: Electrical power service is available from facilities at or near the project site for use on the contract without charge. Provide all connections and extensions of services in a safe manner in compliance with NEC, NEMA, and UL standards and regulations.
2. Water Service: Potable water service is available from facilities at or near the project site for use on the contract without charge.
Provide all connections and extensions of services with proper backflow prevention devices in compliance with AWWA standards and local regulations.
3. Sanitary Facilities: Restrooms are available at or near the project site for use of the contract without charge.
4. Telephone Cellular Service: The project site does have limited cellular service.
E. Temporary Office: The construction of temporary office buildings or installation of trailers will not be allowed in the park. If the contractor requires office space, the park will attempt to accommodate the contractor with an existing space for administrative work.
F. Temporary Enclosures: For uncontrolled sites, the contractor shall construct an enclosure fence, barrier, or partition to prevent people and animals from entering the project site except by gates / doors.
G. Temporary Traffic Controls: The contractor shall erect and maintain barricades, danger signals, and warning signs in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition. The contractor shall provide adequate traffic control, PORE #208882 General Requirements - Page 12 of 13 including flaggers on either side of any work performed in the road. Any workers on or near the road must wear highly visible, bright clothing.
PART 9 – EXECUTION (SECTION 01 73 40)
9.1 EXECUTION
A. Examination: Examine the project area and site facilities and verify compatibility between existing conditions and the scope of work.
B. Preparation: Take field measurements or conduct surveys to verify dimensions before fabrication or installation.
C. Installation: Install all systems or components according to the specifications, manufacturer’s recommendations, permit conditions (where applicable), and local, State, and Federal codes, standards, and regulations.
D. Correction of the Work: Upon discovery of defects or damage of new work or to existing facilities damaged by new work, repair or replace damaged systems or components and restore substrates and finishes.
E. Progress Cleaning: Clean the project site and work area on a daily basis. Keep site free of waste and debris in proper containment. Properly dispose of all waste and debris offsite.
F. Final Cleaning & Waste Disposal: At the completion of the work, clean all surfaces and remove all waste materials, trash, tools, equipment, machinery, and surplus items from the project site and legally dispose of all waste items.
PART 10 – CLOSEOUT PROCEDURES (SECTION 01 77 00)
10.1 SUBSTANTIAL COMPLETION AND FINAL INSPECTION
A. When the project, or a designated portion of the project, is substantially complete, the Contractor shall request a final inspection in writing. Upon receipt of the written request that the project is substantially complete, the Contracting Officer will proceed with a final inspection within ten (10) days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.
B. If the work is determined to be substantially complete at the final inspection, the Contracting Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final acceptance. The Contractor shall complete the work described in the Punch List within thirty (30) calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.
C. If the work is determined to be not substantially complete, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new final inspection. All re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
PORE #208882 General Requirements - Page 13 of 13
D. After all deficiencies have been corrected and the project is complete, a Letter of Final Acceptance will be issued by the Contracting Officer.
10.2 CLOSEOUT SUBMITTALS
A. Operation & Maintenance (O&M) Manual: Submit two (2) hard copies (in D-ring binders) and two (2) compact disks (CDs) with all operation and maintenance information including but not limited to a preventative maintenance schedule, operating instructions, product / material cut sheets, system diagrams, as-built drawings, progress photos, product warranties, and a one-(1) year Contractor-issued warranty on all workmanship starting from the date of final acceptance.
10.3 DEMONSTRATION & TRAINING
A. Demonstration & Training: Provide onsite demonstration and training to NPS operators and staff on the proper, safe operation of all new systems and components.
END OF DIVISION 01 -
BEAR VALLEY VISITOR CENTER MECHANICAL GENERAL REQUIREMENTS
PORE #208882 Section 230100 – Page 1 of 17
SECTION 23 01 00
MECHANICAL GENERAL REQUIREMENTS
PART 1 – GENERAL
1.1 DESCRIPTION
A. Comply with the requirements of DIVISION 1.
B. The requirements of this SECTION apply to all work of this DIVISION.
C. Provide a complete working installation with all equipment called for in proper operating condition. Documents do not undertake to show or list every item to be provided. When an item not shown or listed is clearly necessary for proper operation of equipment, which is shown or listed, provide an item which will allow the system to function properly at no increase in the Contract Amount.
1.2 QUALITY ASSURANCE
A. Related Work Specified Elsewhere:
1. Refer to DIVISION 26 for all electrical wiring (except that specifically indicated on Control Drawings) for motor starters (except pre-wired packaged systems, in which case they must conform to DIVISION 26).
B. Examination of the Site:
1. Visit the site prior to bidding. Take measurements and such other information as to locations, depths, capacities and sizes of existing piping and ductwork to which connections may be made or which may be abandoned or which require rerouting. If any of the above requires extra work due to discrepancies or omissions on the drawings, and if such omissions or discrepancies have been revealed by examination before bidding, the Contractor should report the discrepancy to the Contracting Officer a minimum of three days prior to receipt of bids. If additional work is required due to omissions and discrepancies after the contract for the work is signed and if such omissions or discrepancies would have been revealed by a visit to the site before receipt of bids, then the corrective additional work shall be performed at no additional cost to the Owner.
C. Requirements of Regulatory Agencies:
Standards Compliance: When materials or equipment must conform to the standards of organizations such as the American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), National Electrical Manufacturers Association (NEMA), American Society of Mechanical Engineers (ASME), American Gas Association (AGA), American Refrigeration Institute (ARI), and Underwriters' Laboratories (UL), proof of such conformance shall be submitted to the Contracting Officer for approval.
PORE #208882 Section 230100 – Page 2 of 17
If an organization uses a label or listing to indicate compliance with a particular standard, the label or listing will be acceptable evidence, unless otherwise specified in the individual sections. In lieu of the label or listing, the Contractor shall submit a certificate from an independent testing organization, which is competent to perform acceptable testing and is approved by the Contracting Officer. The certificate shall state that the item has been tested in accordance with the specified organization's test methods and that the item conforms to the specified organization's standard.
1. Any specific reference in these Specifications to codes, rules, regulations, standards, manufacturer's instructions or requirements of regulatory agencies shall mean the latest printed edition of each in effect at date of submission of Bid, unless the Document is shown dated.
2. Perform the work in conformance with the applicable requirements of all regulatory agencies, including, but not limited to the following:
a. National Electrical Code.
b. Uniform Plumbing Code.
c. International Building Code
d. California Code of Regulations (CCR).
(1) Title 8, Division 1, Chapter 3.2 - California Occupational Safety and Health Regulations (CAL/OSHA).
(2) Title 8, Division 1, Chapter 4 - Safety Orders.
(3) Title 24, Building Standards.
(a) Part 2 - California Building Code
(b) Part 3 - California Electrical Code
(c) Part 4 - California Mechanical Code
(d) Part 5 - California Plumbing Code
(e) Part 6 - California Energy Code
(f) Part 9 - California Fire Code
(4) Acceptance Requirements of California Energy Code: Perform work necessary to complete the Acceptance Requirements of the California Energy Code, including but not limited to:
(a) Testing of minimum ventilation controls, zone temperature and scheduling controls, duct leakage, Air-side economizer controls, demand control ventilation systems, fan volume controls and variable frequency drive fan systems.
PORE #208882 Section 230100 – Page 3 of 17
(b) Reviewing plans and specifications to ensure conform to the Acceptance Requirements
(c) Perform construction inspection prior to testing to ensure that the equipment installed is capable of complying with the requirements of the Standards, the equipment is installed correctly and calibrated.
(d) Undertake all required Acceptance Requirement procedures and identify all performance deficiencies, ensuring that they are corrected. Document the results of the Acceptance Requirement procedures on the Acceptance Test forms and indicate satisfactory completion by signing the Certificate of Acceptance.
3. Nothing in the Drawings or Specifications shall be construed to permit Work not conforming to applicable laws, ordinances, rules, regulations.
4. When Drawings or Specifications exceed requirements of applicable laws, ordinances, rules, regulations, Drawings and Specifications take precedence.
5. It is not the intent of Drawings or Specifications to repeat requirements of codes except where necessary for completeness or clarity.
6. Work herein shall comply with all applicable requirements of CCR Title 8, Division 1, as they apply to this project, both in reference to Contractor's operations in performing his work and also in construction result to be accomplished. Where an omission or a conflict appears between OSHA requirements and the Drawings and Specifications, OSHA requirements shall take precedence.
D. When there is an ambiguity or discrepancy between Drawings and Specifications the more stringent requirement of the two shall be provided.
E. Licenses, Permits and Fees
1. Provide, procure and pay for all permits, licenses, fees, etc., required to carry on and complete the Mechanical Work. Contact all applicable utility authorities and include in bid all fees, charged by any such authorities.
F. Operating and Maintenance Instruction:
1. Furnish the services of competent instructors who will give full instruction to the designated personnel in the adjustment, operation, and maintenance, including pertinent safety requirements, of the equipment or system specified. Each instructor shall be thoroughly familiar with all parts of the installation and shall be trained in operating theory as well as practical operation and maintenance work. Instruction shall be given during the first regular work week after the equipment or system has been accepted and turned over to the Owner for regular operation. The number of man days (8 hours) of instruction furnished shall be 1 (one).
PORE #208882 Section 230100 – Page 4 of 17
1.3 SUBMITTALS
A. General
1. Submit shop drawings, catalog data, supplemental data, for all materials, equipment in all Sections of this DIVISION in accordance with the requirements of SECTION 013323, "SUBMITTAL PROCEDURES," and as specified hereinafter.
2. Four weeks after award of the Contract, or earlier, if deemed appropriate by the Contracting Officer, submit a schedule of all submittals with the date of each equipment submittal or shop drawing submittal clearly indicated.
3. Forward all submittals to Contracting Officer, together, at one time. Individual or incomplete submittals are not acceptable. Electronic copies are required.
4. Submittals shall have been reviewed and stamped by the General Contractor in accordance with the requirements of the GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION. Submittals not so stamped will be returned without review.
5. The contractor shall allow for adequate time for submittal review by the Contracting Officer. In general, the contractor shall allow for a minimum of 15 working days from the day the general contractor sends the submittal to the Contracting Officer to the day the Contracting Officer returns the submittal to the general contractor. Additional time shall be allowed for large or complex submittals.
6. Identify each item by manufacturer, brand, trade name, number, size, rating, or whatever other data is necessary to properly identify and check materials and equipment. Words "as specified" are not sufficient identification.
7. Identify each submittal item by reference to Specification SECTION Paragraph in which item is specified or drawing and detail number.
8. Organize submittals in same sequence as they appear in specification sections, articles, or paragraphs.
9. Submit signed Acceptance Test forms indicating completion of California Energy Code Acceptance Test requirements.
B. Electronic Submittals: Electronic submittals is the preferred method of review. Follow these procedures:
1. Provide one pdf file for each submittal. PDF file must be unlocked, editable and printable to accommodate electronic mark-ups or printing a hard copy from markup.
2. Electronic submittals are to be complete and self-contained with each item requiring Contracting Officer’s action highlighted.
3. Web links or other electronic submittals requiring the Contracting Officer to surf
PORE #208882 Section 230100 – Page 5 of 17 websites or navigate to find documents on websites or posting services are not acceptable.
4. The use of construction phase file hosting services or programs such as BIM 360 or Prolog or Primavera may not be used before prior approval from the Contracting Officer.
5. Any electronic submittal procedures should not require the Contracting Officer to search for submittals but should follow procedures that are the electronic equivalent of hard copy submittals sent by Contractor to the Contracting Officer in a manner acceptable to the Contracting Officer including indexing requirements mentioned below.
6. No electronic submittals for samples (if needed) will be permitted.
7. Contracting Officer will return one marked up electronic submittal for Contractor to process and distribute to subcontractors and for Owner according to agreed procedure.
8. On each electronic submittal, provide Contractor review and approval stamp.
C. Indexing:
1. Submittals shall be indexed according to specification DIVISION and SECTION number and paragraph to identify each item. Sporadic submittals, incomplete data, or unidentified data, or data not showing features to coordinate item with other work will not be accepted.
D. Submittal literature, Drawings and wiring diagrams shall be specifically applicable to this project and shall not contain extraneous material. The literature shall be clearly marked to indicate the proposed item and any accessories or options to be furnished. Submittals shall include, but not be limited to the following:
a. Motors * Drives and Guards
b. Hangers and Seismic Bracing, Insulation, Vibration Isolators
c. Duct Trim, Filters, Sound Attenuators,
d. Temperature Controls, Air Handling Equipment, Air Inlets and Outlets +
Notes:
* Include a family of rating curves. See applicable specification section.
+ With a detailed list including Room Nos., neck sizes, throws and NC levels.
E. Resubmittals shall respond to comments made on the original submittal and shall be marked with a resubmittal number and dated. Resubmittals not in conformance with these requirements will be returned without review.
F. Shop Drawings:
1. Submit shop drawings for ductwork and equipment. Do not begin fabrication
PORE #208882 Section 230100 – Page 6 of 17 until shop drawings have been coordinated with all trades and have been reviewed and accepted by the Contracting Officer.
2. Contractor shall prepare and submit coordinated shop drawings for Contracting Officer’s review prior to installation of work. Shop drawings shall show mechanical (including plumbing), electrical, lighting, low-voltage, and fire protection systems including piping, ducting, equipment, devices, fixtures, supports, drains, panels, connections, etc. to show that all equipment/systems can be constructed without interference between components. Equipment access as required by code or as recommended by the manufacturer shall be accounted for and shown.
3. Drawings shall be a minimum of 8-1/2 inches by 14 inches in size, with a minimum scale of 1/8 inch per foot, except as specified otherwise. Drawings shall include floor plans, sectional views, wiring diagrams, and installation details of equipment; and equipment spaces identifying and indicating proposed location, layout and arrangement of items of equipment, control panels, accessories, ductwork, and other items that must be shown to assure a coordinated installation. Ductwork layouts and Mechanical Room layouts shall be drawn at a minimum scale of 1/4 inch per foot. Drawings shall indicate adequate clearance for operation, maintenance, and replacement of operating equipment and devices.
4. Submit wiring diagrams for packaged equipment and controls. Wiring diagrams shall identify circuit terminals, and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment.
5. The Contracting Officer's review of Shop Drawings is not intended to verify dimensions or quantities, nor to coordinate items shown on these Drawings. He will review them for general conformance with design concept of the project and general compliance with the information given in the contract requirements of the plans and Specifications. Contractor is responsible for dimensions, which shall be confirmed and correlated at the job site, for fabrication processes and techniques of construction, for coordination of his work with that of all other trades and the satisfactory performance of his work.
G. Record Drawings
1. Installation drawings shall be drawn at the site by the Contractor on reproducible paper and shall be fully coordinated for interferences by all trades. The Contractor shall maintain at the jobsite a complete set of prints of the installation drawings for all mechanical work. These prints shall be kept up to date by recording all changes daily. The progress of the work shall be clearly, neatly and accurately designated, coloring in the various pipes, ducts and equipments as they are erected. This process shall incorporate all changes to the original drawings including formal change orders or other instructions issued by the Contracting Officer. Principal dimensions of all concealed work shall be recorded including inverts of buried piping and height to underside of ducts.
2. These marked up prints will be used as a guide for determining the progress of the work installed. They will be inspected monthly by the Contracting Officer
PORE #208882 Section 230100 – Page 7 of 17 and shall be corrected immediately if found either inaccurate or incomplete.
3. Prior to final acceptance of the Work of this Division, submit properly certified Record Drawings to the Contracting Officer for review and make changes, corrections, or additions as the Contracting Officer may require. After the Contracting Officer's review and any required Contractor revisions, deliver the Record Drawings to the Owner on electronic media in AutoCAD .DWG format.
The Architect and Engineer do not assume any responsibility for the accuracy or completeness of the Record Drawings.
H. Operating & Maintenance Manuals:
1. Manuals shall conform to SECTION 017700, “CLOSEOUT PROCEDURES”.
2. Furnish an operation and maintenance manual for each item of equipment.
Furnish three (3) copies of the manual bound in hardback binders or an approved equivalent. Furnish one complete manual prior to the time that equipment tests are performed, and furnish the remaining manuals before the contract is completed. Inscribe the following identification on the cover: the words OPERATION AND MAINTENANCE MANUAL, the name and location of the equipment or the building, the name of the Contractor, and the contract number.