Amendment_2_Attachment_5_Q_and_A_0002.pdf
PDF 72 KB Posted
- Attached to
- Environmental Compliance Service, Mt Rainier NP Federal contract opportunity
- Solicitation number
- 140P8324Q0085
About this file
This document is an amendment to a Request for Quotations (RFQ) solicitation for environmental compliance services at Mount Rainier National Park. The solicitation is a 100% small business set-aside with a NAICS code of 541620 Environmental Consulting Services.
The key details are: 1) The National Park Service will be responsible for handling Section 106 consultation, with the contractor incorporating the results into the Environmental Assessment (EA) document. 2) The solicitation includes a revised price schedule with a separate line item for wetland delineation costs, as the final project footprint is not yet known. 3) The solicitation is for tasks including preparation of a draft and final EA, draft and final biological assessments, and a wetland delineation. Quotes are due by September 13, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_2_Attachment_6_REVISED_Price_Schedule_0002.xlsx | XLSX spreadsheet | |
| Sol_140P8324Q0085_Amd_0002.pdf | ||
| Sol_140P8324Q0085_Amd_0001.pdf | ||
| Attachment_4_Quote_Submission_Package_PDF_Portfolio.pdf | ||
| Attachment_2_DOL_Service_Wage_Rates_Pierce_County.pdf | ||
| Attachment_1_Terms_Provisions_Clause.pdf | ||
| Sol_140P8324Q0085.pdf | ||
| Attachment_3_Statement_of_Work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOUNT RAINIER NATIONAL PARK (MORA)
Environmental Compliance Service
Solicitation (RFQ) No. 140P8424Q0085 Amendment no. 2
Attachment 5 - Q and A
NATIONAL PARK SERVICE
PACIFIC WEST REGION
8/28/24
The following two questions received are answered as follows:
(1) QUESTION: The solicitation does not mention Section 106 consultation and we wanted to confirm that NPS will be handling that.
ANSWER: Yes, MORA will be responsible for handling the 106 consultation. The contractor will be responsible for incorporating the results of the 106 consultation into the EA document where appropriate.
(2) QUESTION: Is there a project map or guidance regarding an assumed project corridor that can be provided for reference for the purposes of cost estimation for the wetland delineation and the optional botanical survey? Otherwise, we will identify our supporting assumptions in our response, building off the 4-mile stretch of SR 410 identified.
ANSWER: MORA is refining the footprint of the wetland delineation. Using the current project area is fine. The Price Schedule that was included in Attachment 4, Quote Submission Package, is hereby replaced by new Attachment no. 6, Revised Price Schedule that includes a separate line item for quoters to fill in their estimated cost per acre since MORA does not yet know the final footprint of the area where a wetland delineation will be needed.