This document is an Amendment that contains Questions and Answers related to Solicitation 140P8324Q0069 for the Supply and Delivery of Culvert Pipe to Olympic National Park.
The key details are:
- The solicitation is for 30' lengths of culvert pipe to be delivered to Olympic National Park.
- Vendors inquired about the availability of 48" pipe in 30' lengths, and were informed that 20' lengths with bell and spigot ends and couplers would be acceptable.
- Vendors asked if ASTM-F2648 specification pipe would be accepted, and the agency confirmed this specification is acceptable per the Statement of Work.
- Vendors asked about the acceptable method for off-loading pipe, and were informed they can leave the metal bands intact and push the pipe off the trailer onto the ground.
- The solicitation is being issued by the Department of the Interior National Park Service Pacific West Region.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140P8324Q0069_Amd_0001.pdf | ||
| A06_Attachment_1_OLYM_Culvert_Specifications.pdf | ||
| Sol_140P8324Q0069.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 140P8324Q0069 Supply and Delivery of Culvert Pipe Attachment 2: Question(s) and Answer(s) Olympic National Park
Question and Answer for Solicitation 140P8324Q0069
Q1: When attempting to source the various sizes of pipe required, we ran into an issue regarding the 48” pipe… this large of a diameter pipe does not get manufactured in 30’ lengths or with plain ends… we can provide 20’ lengths with bell and spigot WT and can include 48” couplers if this would suffice as an alternative? If acceptable we would just adjust the LF on the 48” 20’ sticks to get to your overall requested length in 30’ sticks."
Due to several responses for 30' sections, we believe they are out there. However, if the vendor can couple 2-20' sections, and cut bell ends off to make them plain ended 30' sections, and they can deliver completed 30' sections of 48" plain-ended pipe, that will work for us. We do not want to have the crew cutting and coupling pipe during installation.
Q2: Will NPS accept ASTM-F2648 spec’d pipe?
Yes, ASTM-F2648 is listed in the applicable standards as acceptable in the SOW.
Q3: The call for bids states supply and delivery of culvert pipe of 30' lengths "including off-loading to the ground" on a day to day basis we off load pipe by cutting the metal banding and rolling the pipe off of our trailer onto the ground into a neat pile, my question is, would that be acceptable practice to unload your pipe if we are awarded the bid?
Vendors are allowed to leave metal bands intact and push culvert stacks off of the trailer onto the ground. Or supply their own forklift for removal.
File details come from the government source that posted it. Updated .