Attachment_E_Site_Visit_Clarifications_0001.pdf

PDF 146 KB Posted

Attached to
Replace Well System, Peck Residence, Olympic NP Federal contract opportunity
Solicitation number
140P8324Q0064
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a set of clarifications for Solicitation #140P8324Q0064 to rehabilitate the well system at the Peck Residence in Olympic National Park. Key details include:

The existing 61-foot-deep well has run dry in recent years, requiring the installation of a deeper replacement well. The new well should be capable of producing 5-10 gallons per minute. The existing 100-amp electrical panel in the pump house is sufficient, but the contractor should verify sizing based on the final pump house components. The new well will be located approximately 35 feet north-northeast of the existing well, at least 100 feet from Kestner Creek. A payment bond is required, and a performance bond is required if the award exceeds $150,000. The National Park Service is providing a temporary 1,550-gallon water storage tank and pump system to maintain residential water service during construction. The contractor is responsible for flushing, testing, and disinfecting the new components before reconnecting to the residential service line.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Well System, Peck Residence, Olympic NP, newest first.
File Type Posted
Sol_140P8324Q0064_Amd_0001.pdf PDF
Attachment_D_Forms_to_Return_with_Quote.docx DOCX document
Attachment_C__DOL_Wage_Determination.pdf PDF
Attachment_B_Drawings.pdf PDF
Attachment_A_Specifications.pdf PDF
Sol_140P8324Q0064.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ #140P8324Q0064, Rehabilitate Peck Residence Well Olympic N.P.

Attachment E: Clarifications

Clarifications for Solicitation #140P8324Q0064

This document provides clarifications to Attachment A, Project Specifications, and Attachment B, Drawings, based on queries submitted during the solicitation phase and/or raised during the site visit. The responses are incorporated into the contract.

1. Sheet C1 Note 1 says to replace a 30 amp breaker with a 30 amp breaker to feed the new pump house. The sub panel in the pump house is 100 amps. Do we want to feed the new pump house with 30 amps or 100 amps?

The existing pump house uses a 100 amp panel fed by a 30 amp circuit from the main house to meet the existing well pump, treatment equipment, and building electrical needs.

This has been sufficient for the need, and we anticipate replacement in kind for the new pump house. However, contractor shall verify sizing based on final pump house components and notify the Contracting Officer if a 30 amp circuit is insufficient or unacceptable for other legitimate reasons.

2. Sheet E1 has pictures of the existing house panel and meter. Where are these located on the house?

The photos shown on sheet E1 are the meter on the exterior wall and the panel on the interior wall, both located in the center of the north wall of the residence, adjacent to the back door. See yellow cloud in the image below for approximate location of the exterior meter and interior panel.

3. Is there a log for the existing well?

Yes, a copy of the original 1979 well log is located at the end of Section 02 41 00 Demolition & Abandonment.

4. How far away is the new well’s proposed site?

We anticipate locating the new well approximately 35 feet north-northeast of the existing well, at least 100 feet from Kestner Creek. Exact location is flexible based on well driller’s preference for site access and setup.

5. What is the reason for decommissioning the existing well?

In 2022 and 2023, the existing 61-foot-deep well ran dry during the late summer months (approximately late July – September). In 2022, the park was able to lower the well pump to the bottom of the well and maintain some level of flow to the residence. In 2023, the water table dropped below the bottom of the well, and there was no access to water. The purpose of this project is to install a deeper well so that a good supply of water can be accessed on a year-round basis.

6. Does the well have to meet a certain production standard?

Per Section 33 21 00 Water Supply Wells, paragraph 1.3 A., the water supply well performance capacity target is 5 to 10 gallons per minute.

7. Are there any minimum construction standards?

The new residential well shall be constructed in accordance with Washington Administrative Code (WAC) Chapter 173-160 Minimum Standards for Construction and Maintenance of Wells. Section 33 21 00 Water Supply Wells contains additional minimum requirements for well construction.

8. What is the model number of the existing Iwaki Walchem metering pump?

The existing chemical metering pump is model EWB15F1-VC. However, the Walchem EWB15F1-VC pump is now obsolete and was replaced by the EWB16F1-VC pump, which has a new head and diaphragm design. Both the EWB15F1-VC and the EWB16F1-VC have the same specifications of 1.0 GPH, 105 PSI, digital input, PVC/CE/FKM, 3/8" OD, 115 VAC.

9. What bonds are required for this project?

Per item 13.b. on Standard Form 1442, an offer (a.k.a. bid) guarantee is not required. Per Section H.2 of the solicitation, the awardee shall furnish a payment bond within 10 days after contract award. A performance bond will also be required should award exceed $150,000.

10. Are we required to retain water service to the Peck Residence throughout construction, provide temporary water, or meet any sequencing requirements for the project?

The NPS is installing a temporary water system in the form of a 1550-gallon water storage tank and pump system plumbed directly to the house service line with valves, downstream of the existing pump house and treatment system. Therefore, no specific sequencing will be required for demolition or reconstruction of the existing well and pump house, as residential water service can be met through use of the temporary water system. Contractor shall be responsible for all flushing, testing, and disinfection of new components prior to making final re-connection to the residential service line. Coordinate with NPS on timing for disconnecting temporary water system upon completion.

File details come from the government source that posted it. Updated .