This federal solicitation advertises a design-build contract to rehabilitate a large on-site septic system at Olympic National Park in Washington. The contractor will be responsible for designing and constructing a new system to meet current and future peak wastewater flow conditions in accordance with state regulations. Key requirements include installing new septic and dosing tanks, a sand-lined drainfield, and pressurized dispersal system by summer 2020. The estimated value is between $1-2 million. This is a 100% small business set-aside available through SAM.gov, with proposals due by the date specified in the SF1442. The site visit will be held on January 30 dependent on weather. Funding is not guaranteed, and the government may cancel the solicitation before or after the closing date without obligation.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P8320R0003, Attachment 1
OLYMPIC NATIONAL PARK
PORT ANGELES, WA
REHABILITATE HURRICANE RIDGE VISITOR CENTER LARGE
ONSITE SEWAGE SYSTEM (LOSS)
OLYM PMIS No. 205653
DESIGN-BUILD (DB) PROJECT SCOPE
January 10, 2020
NATIONAL PARK SERVICE (NPS)
DEPARTMENT OF THE INTERIOR
OLYM 205653 | Page 2 of 31
Table of Contents
PROJECT INTRODUCTION
1.1 SCOPE
1.2 LOCATION
1.3 BACKGROUND
1.4 DESCRIPTION
1.5 SCHEDULE
DB DESIGN DEVELOPMENT (DD) DOCUMENTS:
100% DRAFT DB CONSTRUCTION DOCUMENTS (CD):
100% COMPLETE DB CONSTRUCTION DOCUMENTS (CD):
COMPLETE STAMPED AND SIGNED DB CONSTRUCTION DOCUMENTS (CD):
CONSTRUCTION:
AS-CONSTRUCTED DRAWINGS:
1.6 NPS CONTACTS & ADDRESS:
1.7 DATA AND MATERIALS PROVIDED BY NPS
PROJECT REQUIREMENTS
2.1 GENERAL REQUIREMENTS
2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS
2.1.2 DEFINITION OF CONTRACT LINE ITEMS
2.1.3 PROGRESS PAYMENTS
2.1.4 PROJECT MEETINGS
2.1.5 PROJECT SCHEDULE
2.2 DESIGN REQUIREMENTS
2.2.1 DB DESIGN DEVELOPMENT (DD) DOCUMENTS AND DB CONSTRUCTION
DOCUMENTS (CD)
2.3 CONSTRUCTION REQUIREMENTS
2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS
2.3.2 SCHEDULE OF VALUES (SOV)
2.3.3 CONSTRUCTION SUPPORT
2.3.4 SUBMITTALS DURING CONSTRUCTION
2.3.6 DIGITAL IMAGES
2.3.7 QUALITY CONTROL
2.3.8 WORKING HOUR RESTRICTIONS
2.3.9 TEMPORARY SERVICES
2.3.10 ACCESS
2.3.11 PRESERVATION OF ADJACENT FEATURES
2.3.12 EXISTING UTILITIES
2.3.13 HAULING RESTRICTIONS
2.3.14 ACCIDENT PREVENTION
2.3.15 TEMPORARY CONTROLS
2.3.16 FIELD ENGINEERING & SURVEY DATA
2.3.16 DEMOLITION
2.3.17 PROJECT CLOSE-OUT
2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTIONS
PERFORMANCE REQUIREMENTS
3.1 DESIGN IMPERATIVES
3.2 SUSTAINABILITY
OLYM 205653 | Page 3 of 31
3.3 INTEGRATED DESIGN PRINCIPLES
3.4 FACILITY PERFORMANCE
3.5 ELEMENTS AND PRODUCTS
OLYM 205653 | Page 4 of 31
PROJECT INTRODUCTION
Park Acronym and PMIS Number: OLYM 205653
Project Title: Rehabilitate Hurricane Ridge Visitor Center Large Onsite Sewage System (LOSS)
Project Drawing Number: OLYM 149/165,522
1.1 Scope
In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work for the National Park Service (NPS) as described below.
Architect/Engineer (A/E) Services required in this RFP shall be performed by licensed Architects and Engineers registered in Washington State.
1.2 Location
This project is located at the Hurricane Ridge Visitor Center at Olympic National Park. The Hurricane Ridge Visitor Center is located approximately 18 miles from Port Angeles, WA on Hurricane Ridge Road at approximately 5200 feet elevation.
1.3 Background
Hurricane Ridge is one of the most popular destinations at Olympic National Park, receiving more than 500,000 visitors annually. The area provides for a variety of visitor activities, including a Visitor Center that houses a concession-operated mercantile and deli restaurant, and a small ski facility that operates during the winter months. Facilities are served by a central water system, but the Hurricane Ridge Visitor Center has a dedicated onsite sewage system that was constructed in 1951. Approximately 1190 linear feet of 6” diameter concrete bell and spigot sewer pipe passes through eight manholes between the Visitor Center and a 24,000 gallon dual chamber concrete septic tank. Septic tank effluent gravity flows to a 12’ x 133’ filter bed constructed from three rows of 36” half round corrugated metal pipe backfilled with broken shale. A concrete distribution box splits flows between the three rows. The system was designed so that sludge could be drained from the sloped base of each septic tank chamber to a sludge drying bed. The sludge bed is no longer used, and the septic tank is pumped annually to prevent overloading of the filter bed.
In 2019 an architecture/engineering (A/E) firm was hired to evaluate the onsite sewage system and prioritize deficiency corrections. Average daily flows were estimated from 2014-2019 metered water consumption data for the Visitor Center and averaged 8,338 gallons per day (GPD) in the peak months of July and August, with a maximum of 11,409 GPD recorded in July 2016. In October 2019, while investigating the drainfield soil profile to determine an acceptable hydraulic loading rate, the drainfield was found to be completely flooded and backing up into the distribution box and septic tank. The system was moved into the large onsite sewage system (LOSS) program
OLYM 205653 | Page 5 of 31 regulated by the Washington State Department of Health (DOH) due to the high flows, and DOH issued a letter of concern for public health and the environment regarding the failing drainfield.
DOH regulates LOSS under Washington Administrative Code (WAC) Chapter 246-272B Large On-site Sewage System Regulations and has identified deficiencies associated with the existing infrastructure that make rehabilitation of these components unlikely due to a combination of aging infrastructure, increased visitation and use, and increases in wastewater strength. DOH has worked with Olympic National Park to complete fieldwork needed to identify a replacement drainfield location and confirmed soil characterization. A schematic design and Predesign Report (Attachment
3) have been submitted to DOH for review based on this site information and a peak design flow of 10,000 GPD. The park intends to continue use of the Hurricane Ridge Visitor Center LOSS under a DOH-approved Contingency Plan for the summer of 2020 until replacement infrastructure can be constructed.
1.4 Description
The purpose of this Design-Build contract is to design and construct a new large onsite sewage system (LOSS) for the Hurricane Ridge Visitor Center to meet current and future peak flow conditions in accordance with Washington Administrative Code (WAC) Chapter 246-272B, Large On-site Sewage System Regulations. Modifications to CLM045 Hurricane Ridge Visitor Center LOSS will entail installing new septic and dosing tanks with duplex submersible pumps, sand-lined bed drainfield, pressurized multi-zone dispersal system with gravelless chambers, and new electrical pump controls. A portion of the collection system will be re-routed to direct wastewater to the new treatment infrastructure, and a new access road will be constructed for ongoing septic tank pumping and maintenance. Obsolete collection and treatment infrastructure will be decommissioned and abandoned in place. An engineering report, plans, and specifications along with a draft operations and maintenance (O&M) manual shall be prepared by a professional engineer licensed in Washington State and submitted to Washington State Department of Health (DOH) for review and approval to construct. Construction completion documentation including a final O&M manual and as-constructed record drawings shall be submitted to DOH and NPS as part of project closeout.
1.5 Schedule
Contractor shall complete work according to the schedule milestones described below. The following table depicts schedule milestones with the identified durations and target due date assuming contract award by March 1, 2020. Provide all required submittals to NPS Project Manager (PM). NPS will forward documents to DOH as required.
Milestone Duration Target Due Date DB Design Development Documents 30 3/31/2020
NPS Review of DD Docs 15 4/15/2020 100% Draft DB Construction Documents 30 4/30/2020
NPS Review of 100% Draft CDs 15 5/15/2020 100% Complete DB Construction Documents 20 5/20/2020
NPS & DOH Review of Complete CDs 30 6/19/2020 Complete Signed & Stamped CDs 15 7/4/2020
OLYM 205653 | Page 6 of 31
DOH Approval to Construct and NPS Notice to Proceed
2 7/6/2020
Construction 60 9/4/2020 As-Constructed Drawings 21 9/25/2020
DB Design Development (DD) Documents:
Submit DB Design Development Documents no later than 30 calendar days after award.
NPS will complete their review no later than 15 calendar days after receiving DB Design Development Documents.
100% Draft DB Construction Documents (CD):
Continue work on 100% Draft DB Construction Documents during DB Design Development Documents review. After receiving DB Design Development review comments, address and incorporate comments in 100% Draft DB Construction Documents.
Submit 100% Draft DB Construction Documents and responses to NPS Review form with responses to DB Design Development Documents no later than 30 calendar days after submitting DB Design Development Documents.
NPS will complete their review no later than 15 calendar days after receiving 100% Draft DB Construction Documents.
100% Complete DB Construction Documents (CD):
Submit 100% Complete (electronically stamped and signed) DB Construction Documents and NPS Review form with responses to 100% Draft DB Construction Documents review comments no later than 20 calendar days after submitting 100% Draft DB Construction Documents. NPS will forward to DOH for simultaneous review.
NPS will complete their review no later than 15 calendar days after receiving 100% Complete DB Construction Documents. DOH will complete their review no later than 30 calendar days after receiving 100% Complete DB Construction Documents.
Complete Stamped and Signed DB Construction Documents (CD):
Submit Complete Stamped and Signed DB Construction Documents and NPS Review form with responses to 100% Complete DB Construction Documents review comments no later than 15 calendar days after receiving DOH review comments.
Construction:
Construction may begin when Contracting Officer issues Notice to Proceed with Construction (see also Section 2.1.5).
OLYM 205653 | Page 7 of 31
Substantially complete construction no later than 200 calendar days after award of contract or by September 14, 2020 – whichever date is earlier.
As-Constructed Drawings:
Complete As-Constructed Drawings and DOH Construction Completion Report no later than 21 calendar days after Substantial Completion.
1.6 NPS Contacts & Address:
Contractual:
Contracting Officer (CO): Sarah Welch, (360) 854-7220, sarah_welch@nps.gov North Cascades NPS Complex, 810 State Route 20, Sedro-Woolley WA 98284
Technical:
Project Manager (PM) & Contracting Officer’s Representative (COR): Kerri Cook, (360) 565-3161, kerri_cook@nps.gov Olympic National Park, 600 E. Park Ave., Port Angeles, WA 98362
1.7 Data and Materials Provided by NPS
NPS is providing the following data and materials.
• 100% Final Trip Report & Schematic Design Preferred Alternative – Hurricane Ridge Utilities (relevant excerpts); Attachment 2.
- Appendix H: Existing Conditions Plans (Sewer System)
- Appendix J: Soil Test Pits & DOH Soil Verification Letter
- Appendix K: Septic Tank Effluent Water Quality
- Appendix M: Sewer System Design Schematics
• Draft CLM045 Hurricane Ridge Predesign Report (submitted to DOH in January 2020);
Attachment 3.
- Appendix A: Sample Results
- Appendix B: Soil Logs & Site Map
- Appendix C: NEPA Documentation
• Washington State Department of Health CLM045 Documents; Attachment 4.
- DOH Public Health Environmental Concern Letter 2019.11.15
- CLM045 Hurricane Ridge Visitor Center LOSS Operating Permit
• 2001 Hurricane Ridge Visitor Center As-Built Drawings with Notations (for electrical purposes); Attachment 5.
• Site Survey Data (separate file to be provided upon contract award) mailto:sarah_welch@nps.gov mailto:kerri_cook@nps.gov
OLYM 205653 | Page 8 of 31
PROJECT REQUIREMENTS
2.1 General Requirements
2.1.1 Scope of Work and Project Summary/Requirements
The project will consist of the design and construction of a new large onsite sewage system (LOSS) for the Hurricane Ridge Visitor Center to meet current and future peak flow conditions in accordance with Washington Administrative Code (WAC) Chapter 246-272B Large On-site Sewage System Regulations.
The project will include, but not be limited to:
• Review Schematic Design preferred alternative and other attachments provided in the solicitation package.
• Upon award, determine and provide schedule for design work and Schedule of Values.
• Design large onsite sewage system (LOSS) in accordance with Schematic Design preferred alternative and DOH comments on Predesign Report.
• Submit DB Design Development and DB Construction Documents for NPS review and approval, as required.
• Prepare Engineering Report, Plans & Specifications in accordance with WAC 246-272B-
04000 and 246-272B-04400, and submit to NPS for DOH review and approval, as required.
• Provide schedule of construction work.
• Preserve and salvage existing meadow vegetation.
• Construct project.
• Demolish and abandon obsolete system components.
• Provide septic tank pumping during contract performance period, if NPS exercises option for this service.
• Prepare the LOSS construction completion report.
• Provide LOSS as-constructed record drawings.
• Create and provide operations and maintenance manual in accordance with WAC 246-
272B-04200.
This Section 2.0, Project Requirements, shall be in effect during the design and construction phases, serving as Division 1 of the Construction Specifications.
2.1.2 Definition of Contract Line Items
In general, explain what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include costs in a related line item.
CONTRACT LINE ITEM 1 – DESIGN LOSS & DEVELOP CONSTRUCTION DOCUMENTS
OLYM 205653 | Page 9 of 31
This item consists of preparing an engineering report, plans and specifications in accordance with WAC 246-272B for National Park Service (NPS) and Washington State Department of Health (DOH) review and approval. Peak design flow shall be for 10,000 GPD. Key design elements include new gravity sewage piping from manhole #6 to a single 30,000-gallon septic tank and 14,000-gallon pump chamber with duplex alternating pumps for timed dosing; wall-mounted electric pump controls; septic tank access road; gravelless chamber pressure distribution to 15,000 square feet of sand lined beds; and abandonment of existing manholes, gravity sewer line, septic tank and drainfield downstream of manhole #6. This item also includes development of a draft operations and maintenance (O&M) manual for DOH review.
CONTRACT LINE ITEM 2 – DEMOLITION/ABANDONMENT
This item consists of decommissioning and abandoning in place obsolete components of the existing onsite septic system in accordance with WAC 246-272B-07500 Abandonment once new components are fully functional, inspected, and approved. Specific items include removing partially treated sewage; removing or destroying septic tank and manhole lids, and penetrating bases to allow drainage; filling voids with soil or gravel; cutting, capping, and abandoning in place all gravity sewer line; and scarifying the existing drainfield and areas disturbed by abandonment in preparation for NPS revegetation.
CONTRACT LINE ITEM 3 – GRAVITY SEWER PIPING
This item consists of installing new 6” gravity sewer pipe from manhole #6 (located southeast of Visitor Center) to the new septic and pump tanks (located southwest of Visitor Center).
Estimated distance is approximately 200 lineal feet of excavation, pipe bedding, and trench backfill, including compaction.
CONTRACT LINE ITEM 4 – SEPTIC/PUMP TANKS & APPURTENANCES
This item consists of installing a single dual-chamber 30,000 gallon septic tank, a single 14,000 gallon pump chamber, and all necessary appurtenances including risers, access hatches, effluent filters, single phase duplex submersible pumps with rail systems and lifting components, and all necessary connections between tanks. Excavations deeper than approximately six feet are expected to penetrate weathered bedrock characterized by thin, laminated beds of sandstone, siltstone, slate, and shale.
CONTRACT LINE ITEM 5 – DRAINFIELD
This item consists of excavating and salvaging subalpine meadow vegetation to construct multiple zones of sand lined beds 10 feet in width along topographic contours below the Visitor Center for a total drainfield infiltrative area of 15,000 square feet, in accordance with the final DOH- and NPS-approved design. Spacing between sand lined beds is expected to be 15 feet due to a site slope that averages approximately 25 percent. This item includes installation of gravelless infiltration chambers, pressure pipe, monitoring ports, zone rotation valves, and other miscellaneous piping and valves required by the final design. Include delivery and placement of 36” (minimum) of ASTM C-33 sand below constructed infiltration surface, as well as disposal of dense restrictive layer soils not reused in septic tank and manhole abandonment. Include salvage and stockpile of meadow vegetation in accordance with NPS guidance for NPS revegetation efforts. Include salvage and stockpile of loam topsoil (anticipated up to 22” below ground surface) for reuse and backfill around infiltration chambers.
OLYM 205653 | Page 10 of 31
CONTRACT LINE ITEM 6 – ACCESS ROAD
This item consists of excavating and salvaging subalpine meadow vegetation; installing and compacting a base course; and installing a compacted crushed gravel top course for providing septic pumper truck access from the existing parking lot to the septic and pump tanks. This item includes cut and repair of pedestrian sidewalk as well as installation of removable bollards to limit vehicular access. Access road length is anticipated to be less than 200 feet.
CONTRACT LINE ITEM 7 – ELECTRICAL CONTROLS
This item consists of installing a duplex pump control panel inside a NEMA 4X Type 316 stainless steel wall-mounted enclosure with padlockable latch located on the western exterior wall of the Visitor Center. Include main disconnect, separate breaker for each pump starter, and separate alarm circuit. This item includes running conduit and wire from existing electrical Panel A (located on lower level of Visitor Center) through up to 100 feet of both public and attic space to a new control panel located near the southwest corner of the building. This item also includes cut and repair of concrete slab terrace and stone retaining wall, and up to 100 feet of trenching with conduit to provide duplex submersible pump control, liquid level monitoring, and alarm activation. Upsize wire to accommodate voltage drop, and conceal conduit in public spaces.
CONTRACT LINE ITEM 8 – PROFESSIONAL SERVICES DURING CONSTRUCTION
This item consists of providing periodic inspections during construction such as reviewing variations in soil profile and sand bed construction to ensure penetration of restrictive layer into Type 1 soils; pre-testing effluent dispersal components to verify functionality prior to DOH final inspection to allow phased construction of drainfield; and participating in DOH and NPS final inspection. This item includes development of post-construction documentation including construction completion report, as-built record drawings, and final O&M manual. This item also includes NPS employee training on standard and emergency system operations; preventive or reoccurring maintenance needs; and other relevant items as part of system start-up and commissioning.
OPTION A – SEPTIC PUMPING:
This item consists of providing septic tank pumping services during the contract performance period if the existing drainfield fails and untreated sewage or effluent threatens to discharge on the ground. Potential pumping requirements could reach a maximum of 10,000 GPD during peak visitation but is expected to range from 3,000 to 6,000 GPD during July and August. Provide unit pricing per 3,000 gallons pumped.
OPTION B – ADDITIONAL ASTM C-33 SAND:
This item consists of providing additional sand media meeting ASTM C-33 specifications if more than 36 inches of ASTM C-33 sand is required below the infiltration surface to penetrate the restrictive layer into Type 1 soil. Total additional sand media is expected to range from 100 to 300 tons. Provide unit pricing per additional ton of ASTM C-33 sand delivered and placed in the drainfield.
2.1.3 Progress Payments
OLYM 205653 | Page 11 of 31
Design Phase - Progress payments will be based on submission, review, and acceptance of design deliverables by both NPS and DOH.
Construction Phase - Progress payments will be based on percentage of work completed on items listed in approved schedule of values and as verified by the Contracting Officer’s Representative.
DB Contractor shall furnish to Contracting Officer originals of field notes and other records relating to basis for payment upon request. DB Contractor shall retain copies of material furnished to Contracting Officer.
2.1.4 Project Meetings
Design Meeting
After award of contract and acceptance of Performance and Payment bonds, Contracting Officer will arrange a design meeting with DB Contractor. Meeting agenda will include the following as a minimum:
• Design criteria
• Areas available for use by DB Contractor
• Access requirements of the Park
• Commissioning (review requirements in ASHRAE 0-2005 paragraphs 6 and 7)
• Design schedule
• Environmental and sustainability requirements
• Natural and Cultural Resource Protection
• Payments to DB Contractor
• Review and emphasize Park needs and design objectives
• Modifications during design
• Schedule of Values
• Submittals during design
Preconstruction Meeting
Submit following deliverables by June 1, 2020.
• Accident Prevention Program (APP)
• DB Contractor’s Commissioning Plan (CCxP)
• Evidence of liability insurance coverage and worker’s compensation for DB Contractor and Subcontractors
• Letter designating your Project Superintendent
• List of Subcontractors for project (must match list in proposal)
• Project Schedule with construction portion fully developed
• Quality Control Plan
• Schedule of Values
OLYM 205653 | Page 12 of 31
• Under-an-Acre Pollution Prevention Plan (UPPP) – template available here
• Written statements from Subcontractors certifying compliance with applicable labor standard clauses, using Standard Form (SF) 1413.
In mid-June, 2020, Contracting Officer will arrange on-site Preconstruction meeting with DB Contractor. Meeting agenda will include the following:
• Accident reporting
• Construction schedule
• Correspondence procedures
• Jobsite safety
• Labor standards
• Lines of Authority
• Modifications
• Park Rules and Regulations
• Payroll reports
• Progress Payments
• Roles and responsibilities
• Submittal process
• Entry station, access road and site constraints
• Medical emergency procedures and contacts
• Visitation and public relations
• Archeological Resources Protection Requirements (NPS cultural resource staff will attend)
• Revegetation Requirements (NPS vegetation management staff will attend)
• Saturdays, Sundays, holidays and night work
• Traffic control
Progress Meetings
DB Contractor shall facilitate and document minutes from telephone conference calls with Contracting Officer and other project team members. Meetings will be convened as needed during the design phase and weekly during construction. Meetings will include updates to the following meeting agenda items:
• Approval of minutes of previous meetings
• Modifications
• Review of off-site fabrication and delivery
• Requests for Information (RFI) and issues
• Schedule update
• Status of Project Record Drawings and O&M (Operation & Maintenance) Manuals
• Submittal status
• Work in progress and projected
• Other business relating to work https://www.nps.gov/dscw/upload/UnderAnAcre-UPPP_Template_3-30-16.docx
OLYM 205653 | Page 13 of 31
2.1.5 Project Schedule
Execution of this project is expected to be limited by seasonal weather conditions impacting site access. The Hurricane Ridge Visitor Center is located at 5200 feet elevation. While the proposed septic tank and drainfield site is south-facing, snow accumulation from winter precipitation may linger into May or June. Snowfall may resume as early as late September or October. Therefore, the target construction window for this project is July/August 2020, although construction may start earlier if design is complete and weather and site conditions allow access.
LOSS design for this project requires an engineering report, plans, and specs that must be reviewed and approved by the Washington State Department of Health (DOH) in addition to the NPS. DOH is allowed 30 days to review and comment on submitted construction documents.
NPS will not issue Notice to Proceed (NTP) with construction until DOH issues approval to construct. Section 1.5 Schedule (above) identifies timeframes for development of deliverables selected to meet the target construction window of July/August 2020.
The Contracting Officer may authorize access to the site after the pre-construction meeting but prior to receipt of DOH approval to construct, allowing the DB Contractor to mobilize, stage equipment and materials, etc. Authorization will be granted only after approval of liability insurance, accident prevention plan, and other deliverables noted above. The DB Contractor shall not commence demolition or construction until the Contracting Officer issues the Notice to Proceed. Mobilization prior to receiving the NTP is at the discretion of the Contractor.
General: DB Contractor shall prepare a detailed schedule of the design phase with design deliverable submission dates, review periods, and summary construction schedule with important milestones included for both phases. Provide an electronic copy of schedule to NPS before design meeting.
Contractor shall fully develop construction portion of project schedule and submit to Contracting Officer before June 1, 2020.
Construction work cannot begin until Washington State Department of Health (DOH) and Government (NPS) approval is obtained for the entire set of Complete Signed and Stamped DB Construction Documents.
Purpose: Project schedule ensures adequate planning, coordinating, scheduling, and reporting of DB Contractor’s design and construction activities. Project schedule will assist DB Contractor and Contracting Officer to monitor work progress, evaluate proposed changes, and process DB Contractor's monthly progress payment requests.
Schedule Development: Project schedule shall cover entire contract period. Target date for substantial completion is 200 calendar days after award of contract or by September 14, 2020 – whichever date is earlier. Failure to meet milestones during the design phase of schedule will not automatically extend schedule milestones set for the construction phase.
DB Contractor shall use Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. DB Contractor's project schedule shall consist of procurement
OLYM 205653 | Page 14 of 31 activities (including mobilization, submittal, and fabrication and delivery of key and long-lead procurement items) and construction activities. Note that product submittal review by the NPS may occur simultaneously with DOH review of 100% Complete DB Construction Documents or earlier to expedite ordering of long-lead procurement items like tanks.
DB Contractor's project schedule shall consist of, but not be limited to, the following for each activity:
• Identify activities and numbers numerically (maximum 5-digit).
• Concisely describe work represented by activity. Avoid using non-standard abbreviations. Limit work related to each activity to one work trade.
• Activity duration shall be in whole working days with maximum duration 15 work days each, unless otherwise approved by Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.
DB Contractor shall ensure project schedule includes own work and Subcontractor work.
Project schedule shall show sequence and interdependence of activities required for complete performance of work and shall be cost and resource loaded. DB Contractor shall ensure work sequences are logical and project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be DB Contractor's best estimate of time required to complete activity, considering scope and resources planned. Include permit requirements and constraints.
Consider and include seasonal weather conditions in planning and scheduling of work influenced by high or low ambient temperatures and wind and/or precipitation, to ensure completion of work within authorized period of performance.
Project Schedule monthly updates: Monthly updates of project schedule shall be an integral part and basic element of estimate upon which progress payments shall be made under this contract. If, in judgment of Contracting Officer, DB Contractor fails or refuses to provide schedule of values and complete schedule update or revision as specified hereinafter, DB Contractor shall be deemed to have not provided required information upon which progress payment may be made and shall be subject to retainage of a portion of the payment.
As work progresses, indicate Actual Completion percentage for each activity. If schedule update shows late finish date after performance period end date, at a minimum, include the following in narrative with submission:
• Known delays.
• Actions taken to get back on schedule.
• Pending modifications.
• Impediments or constraints affecting progress.
Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or DB Contractor revises project schedule, DB Contractor shall submit to
OLYM 205653 | Page 15 of 31
Contracting Officer a written time impact analysis illustrating influence of each modification, change, delay, or DB Contractor’s request on the contract time.
• Time Extensions: Activity delays shall not automatically mean an extension of contract time is warranted or due to DB Contractor. It is possible that modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of available total float that may exist within an activity chain of the project schedule, thereby not effecting the contract time. Time extensions will be granted according with terms of contract.
• Float: Float is not for exclusive use or benefit for NPS or DB Contractor. Extension of contract time is granted only to extent the equitable time adjustments to activity or activities affected by modification, change, or delay exceeds total (positive or zero) float available on a particular activity.
2.2 Design Requirements
2.2.1 DB Design Development (DD) Documents and DB Construction Documents (CD)
Prepare DB Design Development Documents and DB Construction Documents using English System of Weights and Measurements and according to DSC Design Standards and DSC Design Deliverables - Content and Format Requirements for DB Design Development Documents and DB Construction Documents.
List salient characteristics for products and materials specified. Refer to Guide for Specifiers.
Deliverables
The following deliverables are required (refer to Section 1.5 for schedule) for NPS Review:
• DB Design Development (DD) Documents o Submit electronic copies of the following DB Design Development Documents for review:
Draft DB Design Development Drawings Divisions 2 through 49 Outline Specifications Product File (including preferred/selected material literature) Draft Engineering Report
• 100% Draft DB Construction Documents (CD) o Submit electronic copies of the following 100% Draft DB Construction Documents for review:
100% Draft DB Construction Drawings Divisions 2 through 49 Construction Specifications (Construction
Specifications Institute (CSI) MasterFormat) Product File Engineering Report Draft operations and maintenance (O&M) manual https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designdevelopdb.htm https://www.nps.gov/dscw/del_constructiondb.htm https://www.nps.gov/dscw/loader.cfm?csModule=security/getfile&pageid=242817
OLYM 205653 | Page 16 of 31
NPS Review form with responses to DB Design Development Documents review comments
• 100% Complete DB Construction Documents (CD) o Submit electronic copies of the following 100% Complete DB Construction
Documents (electronically signed and stamped) for NPS and DOH review and final approval:
100% Complete DB Construction Drawings Divisions 2 through 49 Construction Specifications Product File Engineering Report Draft O&M Manual NPS Review form with responses to 100% Draft DB Construction
Documents review comments
• Complete Stamped and Signed DB Construction Documents (CD) o Upon final NPS and DOH approval of 100% Complete DB Construction Documents, submit Complete Stamped and Signed DB Construction Documents per following table for construction, NPS archiving, and general use. For format and media submission requirements, see Design Deliverables - Content and Format Requirements DB Hard Copy and Electronic Submittal Requirements.
COMPLETE STAMPED AND SIGNED
DB CONSTRUCTION DOCUMENTS (CD)
ELECTRONIC
FORMATS *
HARD COPY
FORMATS
DB Construction Drawings ** AutoCAD & PDF Full-Size Paper
(ANSI D)
Divisions 2 through 49 Construction Specifications PDF & MS (Microsoft)-Word
N/A (Not Applicable)
Product File PDF N/A Engineering Report PDF N/A NPS/DOH Review form with responses to 100% Complete DB CD review comments PDF & MS-Excel N/A
* The recipient of the electronic files is TIC (Technical Information Center).
** DB Construction Drawings shall be printed from the native software (e.g. AutoCAD .dwg).
DB Construction Drawings printed from secondary software (e.g. Adobe .pdf) are not acceptable as they often result in off-scale product.
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. General requirements:
• Site Disturbance: Minimize construction limits of project to reduce impact on site.
Locate staging and access areas where they will minimize new disturbance of area soils and vegetation. NPS may furnish metal landing mats to minimize vehicular and equipment impacts on sensitive meadow vegetation, if requested.
https://www.nps.gov/dscw/del_submitformatdb.htm
OLYM 205653 | Page 17 of 31
• Toxic Chemicals: Avoid materials that can leach toxic chemicals into ground water. Use spill-prevention measures to prevent inadvertent spills of fuel, oil, hydraulic fluid, antifreeze, and other toxic chemicals that could affect wildlife. Inspect all machinery for leaks prior to starting work each day and make all necessary repairs before commencement of work.
• Soil Erosion: Protect against erosion and topsoil depletion according to NPS-approved Under-An-Acre Pollution Prevention Plan (UPPP).
• Habitats: Protect natural habitats and ecological systems on facility site. A marmot survey will be conducted by the NPS within the vicinity of the proposed drainfield prior to the start of construction. No threatened and endangered species have been identified in the vicinity of this project.
• Noise: Minimize noise during construction.
Minimize Construction Impacts
Implement the following mitigation measures to minimize impacts of construction activities:
Soil Erosion: Protect against erosion and topsoil depletion. Preparation of and compliance with UPPP are required.
Exotic Vegetation and Noxious Weeds: Prevent introduction and minimize spread of exotic vegetation and noxious weeds. Incorporate the following procedures:
• Obtain all fill, rock, and topsoil from the project area, if possible. If not possible, then obtain weed-free fill, rock, or additional topsoil from a source approved by the NPS vegetation staff or Clallam County.
• Vehicles and equipment used at the site must be pressure cleaned and free of weeds, seed, debris, and mud to prevent the introduction and/or spread of exotic, invasive plants.
Arrange with Contracting Officer or COR for NPS inspection of equipment prior to offloading.
• Ensure that tools and clothing are free of seeds or other parts of exotic plans before being used at the construction site.
• If any portion of the project area is mulched, only weed-free material, approved by the NPS, shall be used.
• Cover any stockpiled fill material with a tarp to prevent accumulation of exotic plant seeds.
• Use approved native seed and/or plants and coordinate with NPS staff to revegetate areas disturbed by construction.
Vegetation Salvage and Revegetation Plan: Required for this project. Coordinate subalpine meadow vegetation salvage efforts with NPS staff for all vegetation-disturbing activities including trenching, temporary and permanent access routes, and excavation for construction.
Remove sod in strips of uniform thickness for stockpiling. Sod removed for more than 8 days prior to replacement shall be stockpiled in the Visitor Center parking area west of the building for NPS irrigation management until areas disturbed by construction are ready for revegetation.
Native topsoil shall be stockpiled and reused for drainfield construction and revegetation to
OLYM 205653 | Page 18 of 31 ensure a smooth, non-hummocky final vegetation surface matching the original topographic contours. Sand may be used in addition to native topsoil to create a final level surface.
Accommodate NPS-provided and operated temporary irrigation system for areas revegetated prior to completion of construction.
Air and Water Pollution Control: Air quality impacts are expected to be temporary and localized. To minimize these impacts, take following actions:
• To reduce tailpipe emissions, do not leave construction equipment idling longer than necessary for safety and mechanical reasons.
• Take necessary reasonable measures to reduce air and water pollution with material or equipment used during construction.
Cultural Resources: Archaeological monitoring is required for this project. The NPS will provide an Archeological Monitor to be present at the work site for all ground-disturbing work associated with new construction. Identify all ground-disturbing work and coordinate with NPS cultural resource staff at least two weeks in advance. If archeological resources are discovered at project site while Archeological Monitor is absent, immediately stop work in vicinity of discovery and report discovery to Contracting Officer and COR. If human remains are discovered during construction, all work on the project must stop and the park archaeologist contacted immediately. All provisions in the Native American Graves Protection and Repatriation Act (1990) will be followed.
2.3.2 Schedule of Values (SOV)
After contract award and before Design Meeting, submit schedule of dollar value based on Contract Price Schedule. Break down lump-sum contract line items into component parts for which progress payments may be requested. Total costs for component parts of work shall equal contract line item amount for that lump-sum item. Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead, and profit in total dollar value of unit price item and in component parts of work for each lump-sum item, as described below. Do not include mobilization, general condition costs, overhead, or profit as separate items.
For option items A and B, list unit price only in the SOV. Option items will not be exercised at award, but added by contract modification if necessary, after which the DB Contractor shall update the SOV accordingly. Total cost of Items 1 thru 8 shall equal contract sum. Before first progress payment is processed, DB Contractor and Contracting Officer shall agree on an acceptable Schedule of Values.
2.3.3 Construction Support
Staging Areas
OLYM 205653 | Page 19 of 31
Limit construction sites to smallest feasible area. Carefully control ground disturbance and site management to prevent undue damage to vegetation, soils, and archeological resources, and to minimize air, water, soil, and noise pollution.
Staging is limited in or near construction area for a construction office or trailer. Locate construction equipment and material storage in previously disturbed areas near construction site.
Obtain Contracting Officer’s approval for staging area location for construction equipment. Once construction is complete, return staging areas to pre-construction conditions. Develop standards and methods for determining pre-construction conditions after consultation with NPS.
The paved visitor parking area immediately west of the Hurricane Ridge Visitor Center (approximately 20’ x 320’) will be available as a dedicating staging and construction site access area. An additional paved visitor parking area of equivalent size due north of this staging area can also be made available if needed; DB Contractor shall be responsible for ensuring safe visitor vehicular and pedestrian access between staging areas to Hurricane Hill Road and facilities located west of the Visitor Center.
Structures: Trailers, Storage, Field Offices, Staging Area and Sheds: Contracting Officer (CO) to approve location. Do not place until CO issues Notice to Proceed with Construction. All structures shall be structurally sound construction and weather tight.
Construction Camp: Establishment of a construction camp will not be permitted.
Construction Zones: Before construction activity, use construction barrier, plastic, or portable fencing, approved by Contracting Officer, to define construction zone, minimum area required for construction. Clearly state protection measures in construction specifications and instruct workers to avoid conducting activities beyond construction zone.
Protection of Public: Use fence, barricade, or other means to block immediate work area and prevent unauthorized entry. Erect and maintain fencing, barricades, lights, signals, and warning signs according to current version of Manual on Uniform Traffic Control Devices (MUTCD).
Parking of Construction Vehicles: Limit to existing roads in legally designated areas and within approved staging area(s).
Park Access: A park Entrance Station is located approximately 5 miles up Hurricane Ridge Road at Heart O’ the Hills and all vehicles must drive through it to access the project site. DB Contractor and subcontractors will be authorized to pass without fee or payment. This entrance station does not have an established bypass lane, so Contractor’s vehicles must wait in line with park visitors to pass the station; wait times may be long during high-visitation periods (e.g.
summer afternoons, weekends, and holidays).
2.3.4 Submittals During Construction
OLYM 205653 | Page 20 of 31
Construction Submittals: Identify during the design phase proposed materials and equipment with long lead times; list material submittals on Critical Path schedule; and submit for Government review and approval along with 100% Complete DB Construction Documents.
Construction Submittal Types
Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.
• Product Data: Collect information in single submittal for each element of construction and type of product or equipment.
• Shop Drawings: Prepare project-specific information, drawn accurately to scale.
• Samples: Submit Samples of kind, color, pattern, and texture for reviewing characteristics with other elements and comparing between submittal and actual component as delivered and installed.
• Construction Materials: DB Contractor is encouraged to submit, for approval, products made of recycled or environmentally responsible material. NPS will make every effort to approve these materials.
Informational Submittals: Written information not requiring Government’s responsive action.
Submittals may be rejected for not complying with requirements.
• Prepare and submit Informational Submittals required by individual Specification Sections.
• Informational submittals include, but are not limited to, Test reports, Manufacturer’s instructions, Division 01 Management Plans, etc.
Contractors Review
Review each submittal for coordination with other work of contract and compliance Contract Documents. Note corrections and field dimensions.
General Submittal Procedures
Prepare and submit submittals electronically using transmittal form CM-16.
Contracting Officer reserves the right to require submittals in addition to those identified in individual sections.
Coordination: Coordinate submittal preparation and processing with construction activity performance. Review for legibility, accuracy, completeness, and compliance with Contract Documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities requiring sequential activity.
2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.
https://www.nps.gov/dscw/upload/TransmittalForm-CM16_10-8-19_v508-1016.xlsx
OLYM 205653 | Page 21 of 31
Processing Time: Allow enough time for submittal review and re-submittals. Start review when Contracting Officer, or designee, receives email transmitting submittal. After Contracting Officer completes review, an email is sent to the DB Contractor indicating submittal has been processed.
Contract time extensions will not be authorized if submittals are not transmitted with enough time to permit processing, including re-submittals.
1. Action Submittals: Allow 15 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
2. Informational Submittals: Allow 10 days for review of each submittal.
Contracting Officer's (CO) Review
Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate appropriate action on transmittal form in one of three ways:
1. Approved: Acceptable with no corrections required.
2. Approved with Notations: Minor corrections or clarifications required. Comments are clear and no further review required. DB Contractor shall address review comments when proceeding with work.
3. Disapproved - Resubmit: Rejected for not according with contract or requiring major corrections or clarifications. Contracting Officer will identify reasons for disapproval. DB Contractor shall revise and resubmit with changes clearly identified.
Informational Submittals: Contracting Officer will review submittals and accept or reject.
Use for Construction
Use only final submittals marked with Approved or Approved with notations. Ensure notations are incorporated and, at a minimum, keep one copy of final approved submittal on site during construction.
2.3.6 Digital Images
Take six (6) to ten (10) color, digital images each week when site work occurs documenting construction progress, problems, and elements that may not be visible at a later date (e.g.
underground piping). Select vantage points to show status of construction and progress since last images were taken. Email digital images of each work activity with date, location, title, description, and other information pertinent to subject captured in photos to the Contracting Officer and COR.
2.3.7 Quality Control
General
OLYM 205653 | Page 22 of 31
DB Contractor is responsible for quality of work. Inspect and test work as needed to ensure quality of materials, workmanship, construction, and finish, and to ensure functional performance is in compliance with applicable specifications and drawings.
DB Contractor accepts ultimate responsibility, liability and duty to control quality of services provided to the Government as stipulated in FAR Part 36.609-2. DB Contractor shall be responsible for professional quality, technical accuracy, and coordination of designs, drawings, specifications, and other services furnished by DB Contractor, their Employees, Agents, Assignees, and Subcontractors under the contract. DB Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its designs, drawings, specifications, and other services.
DB Contractor shall demonstrate existence of a Quality Control (QC) system used for work submitted to NPS. DB Contractor and Subcontractors shall use this QC system and, at a minimum, include:
• Coordination of drawings and specifications within each discipline and between disciplines.
• Verification that documents to be submitted are accurate and correct.
Contracting Officer may designate test locations.
Quality Control Staff
QC Supervisor, designated by DB Construction Contractor, shall be on project site whenever contract work is in progress. QC Supervisor may also perform duties of Project Superintendent.
DB Construction Contractor's job supervisory staff may assist QC Supervisor and supplement, as necessary, by adding certified testing technicians.
Testing Laboratory and Equipment:
• Employ certified independent laboratories to perform sampling and testing. Testing laboratory organization shall be certified for type of testing work.
• Calibrate measuring devices, laboratory equipment, and instruments at established intervals against certified standards according to National Bureau of Standards (NBS) requirements. Upon request, Government will make available measuring and testing devices for verification tests.
Submittals
Quality Control Plan: Prior to June 1, 2020, submit written QC plan for approval. If plan requires revisions or corrections, DB Construction Contractor shall resubmit plan within 10 days.
Government reserves right to require changes to the plan during contract period as necessary to obtain quality specified. No change in the approved plan may be made without written concurrence by Contracting Officer. The plan shall include:
OLYM 205653 | Page 23 of 31
• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
• A copy of a letter of direction to QC Supervisor outlining assigned duties.
• Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
• Methods of performing, documenting, and enforcing quality control of work.
• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
Daily Reports: During…