This document is a Statement of Work (SOW) for a project to fabricate and install a metal gate at the entrance to the Government Wash Road in Lake Mead National Recreation Area, Nevada.
The key details are:
- The project requires the fabrication and installation of a metal gate with 6" diameter gate posts, 3" diameter gate arms, and 5" diameter attachment posts. The gate must span the two-lane road to restrict vehicle access during closures.
- The gate must include features such as a removable center bollard post, locking mechanisms to secure the gate in open and closed positions, and reflective highway tape.
- The contractor will be responsible for excavation, concrete footings, painting, cleanup, and traffic control during installation.
- The period of performance is 60 calendar days from award of the contract.
- Contractor must submit fabrication drawings for approval prior to fabrication.
- The related federal contract opportunity is Solicitation #140P8124Q0043, issued by the Department of the Interior National Park Service Pacific West Region.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lake Mead National Recreation Area
Boulder City, Nevada
SERVICES REQUEST: Fabricate and Install Gate at Government
Wash Road
REVISED DATE: July 1, 2024
Prepared By: Trent Martinez, Supervisory Facility Operations Specialist
NATIONAL PARK SERVICE
Lake Mead National Recreation Area
LAKE – Fabricate & Install Gate
A04 STATEMENT OF WORK: FABRICATE & INSTALL GATE
1. BACKGROUND
Lake Mead National Recreation Area (LAKE) is a U.S. national recreation area in Southeastern Nevada and Northwestern Arizona. Operated by the National Park Service, Lake Mead NRA follows the Colorado River corridor from the westernmost boundary of Grand Canyon National Park to just north of the cities of Laughlin, Nevada and Bullhead City, Arizona. LAKE offers many recreational opportunities including boating, hiking, fishing, and both tent and RV camping. Because of these attractions, dispersed camping of RV’s and campers in unauthorized areas has become a growing concern. Specifically, the Government Wash area of LAKE has become inundated with disperse camping that has resulted in resource damage, littering of trash, and lead to major health and safety concerns.
This project will fabricate and install a meta gate at the entrance to the Government Wash Road. The gate will be of metal pipe construction and will need to span the two-lane road to restrict access of vehicles during closures. The gate will have a removal center bollard to help support the gate arms when closed but will be removed from the road when opened. In addition to the gate, attachment poles will be installed to lock the gate arms in the open position. Gate drawings have been attached to this document as a guideline for fabrication and installation.
2. PROJECT LOCATION:
Project is located by the intersection of Northshore Road Hwy 167 and Government Wash Road. GPS coordinates 36.147076, -114.848500. See attached project drawings for more detailed location map and information.
3. PROJECT TASKS
The following tasks shall be completed by contractor as a part of this contract:
a) Fabricate gate, gate posts, and attachment posts based on drawings attached to document, tasks within this statement of work, and information requested by NPS COR and maintenance staff.
b) Gate arms will have a 6” diameter post sleave and 3” diameter arms. Gate post will be made of 5” diameter pipe and pipe hinge to allow gate arms to sleave over post and utilize pipe hinge. Attachment posts will be made of 5” diameter pipe.
c) Gate arms shall lock with pins to the bollard post when closed and shall lock to attachment posts by chain when kept open. NPS will provide padlocks for locking the gates and other components chains, pins, fasteners, and accessories shall be provided by the contractor.
d) Paint all metal finishes brown (NPS will provide exact color code) with high performance oil-based enamel paint.
LAKE – Fabricate & Install Gate
e) Excavate and set gate posts and attachment posts in a 3’ x 3’ x 3’ concrete footing just outside of edge of pavement of road. Contractor shall set exact location of posts to assure proper opening and closure of the gates and gate elements in the field.
f) Excavate and set gate attachment posts according to the drawings assuring gate arms open with the flow of traffic of each lane and are slightly past parallel to edge of pavement when secured open.
g) Saw cut road to install removable bollard post and elements set in concrete. Bollard post shall be removable and base components will allow for minimal disturbance to vehicle traffic when the bollard is not installed.
h) Install highway approved reflective tape along the top post of the gate arms and around the top of each gate arm, attachment post, and bollard.
i) Assure gate arms swing fluidly, lock and open without use of force, weight, or additional tools. Pins and locking mechanism are easy to remove and use without hammers or adjustments.
j) Finished gate will be visually plumb and level, paint will be free of chips and scratches, fasteners and pins will be secure, and concrete foundations will be smooth and level.
k) All equipment tracks showing on unpaved surfaces will be raked, debris removed from site, and road swept of debris caused by the construction.
4. CONTRACTOR USE OF PREMISES
a) Contractor will keep worksite organized and clean as work allows
b) Designated areas for staging and contractor access will be identified by NPS COR
c) Contractor will be responsible for disposal of all construction debris and waste
d) Contractor will provide temporary traffic control while working in the road and road shoulders in accordance to the Nevada Department of Transportation Guidelines
e) Any government property damaged during this project will be replaced at the contractor’s expense
f) COR has the right to revoke any of the above privileges at anytime if cleanliness or unprofessional behavior warrants it
5. PERIOD OF PERFORMANCE:
All tasks and deliverables for this contract must be completed within 60 of days after award NTP. Days listed herein refer to calendar days.
5. PROJECT SUBMITTALS
a) Fabricator drawings for gate construction. Contractor shall provide final shop drawings before fabrication to NPS COR for approval to assure gate concept meets project requirements. This may include details of fasteners, hinges, and components.
| A04 statement of work: Fabricate & Install GATE |
| 1. Background |
| 2. project Location: |
| 3. Project Tasks |
| 4. Contractor Use of Premises |
| 5. Period of Performance: |
| 5. ProJect Submittals |