B08_-_Atch_1_-_Statement_of_Work_Install_and_Fabricate_Gate_at_Government_Wash.pdf

PDF 150 KB Posted

Attached to
LAKE24-0128-INSTALL GATE @ GOV WASH RD
Solicitation number
140P8124Q0043
Issued by

About this file

This document is a Statement of Work (SOW) for the fabrication and installation of a metal gate at the entrance to the Government Wash Road in the Lake Mead National Recreation Area. The key details are:

The project requires the contractor to fabricate a metal gate with 6-inch diameter post sleeves, 3-inch diameter arms, and 5-inch diameter gate posts and attachment posts. The gate arms must lock to a removable bollard post and attachment posts when opened and closed. All metal components must be painted brown. The contractor will excavate and set the gate and attachment posts in concrete footings, saw-cut the road to install the removable bollard, and install reflective tape on the gate elements. The work must be completed within 30 calendar days after award of the contract. The contractor is required to keep the worksite organized and clean, follow traffic control guidelines, and repair any government property damage at their own expense.

The related federal contract opportunity is Solicitation Number 140P8124Q0043, titled "LAKE24-0128-INSTALL GATE @ GOV WASH RD", issued by the Department of the Interior National Park Service Pacific West Region. The contract is for the fabrication and installation of the gate described in the SOW.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lake Mead National Recreation Area

Boulder City, Nevada

SERVICES REQUEST: Fabricate and Install Gate at Government

Wash Road

DATED: April 29th, 2024

Prepared By: Trent Martinez, Supervisory Facility Operations Specialist

NATIONAL PARK SERVICE

Lake Mead National Recreation Area

MOJA – Install Flooring at OX Ranch House

A04 STATEMENT OF WORK: INSTALL FLOORING AT OX RANCH HOUSE

1. BACKGROUND

Lake Mead National Recreation Area (LAKE) is a U.S. national recreation area in Southeastern Nevada and Northwestern Arizona. Operated by the National Park Service, Lake Mead NRA follows the Colorado River corridor from the westernmost boundary of Grand Canyon National Park to just north of the cities of Laughlin, Nevada and Bullhead City, Arizona. LAKE offers many recreational opportunities including boating, hiking, fishing, and both tent and RV camping. Because of these attractions, dispersed camping of RV’s and campers in unauthorized areas has become a growing concern. Specifically, the Government Wash area of LAKE has become inundated with disperse camping that has resulted in resource damage, littering of trash, and lead to major health and safety concerns.

This project will fabricate and install a meta gate at the entrance to the Government Wash Road. The gate will be of metal pipe construction and will need to span the two-lane road to restrict access of vehicles during closures. The gate will have a removal center bollard to help support the gate arms when closed but will be removed from the road when opened. In addition to the gate, attachment poles will be installed to lock the gate arms in the open position. Gate drawings have been attached to this document as a guideline for fabrication and installation.

2. PROJECT LOCATION:

Project is located by the intersection of Northshore Road Hwy 167 and Government Wash Road. GPS coordinates 36.147076, -114.848500. See attached project drawings for more detailed location map and information.

3. PROJECT TASKS

The following tasks shall be completed by contractor as a part of this contract:

a) Fabricate gate, gate posts, and attachment posts based on drawings attached to document, tasks within this statement of work, and information requested by NPS COR and maintenance staff.

b) Gate arms will have a 6” diameter post sleave and 3” diameter arms. Gate post will be made of 5” diameter pipe and pipe hinge to allow gate arms to sleave over post and utilize pipe hinge. Attachment posts will be made of 5” diameter pipe.

c) Gate arms shall lock with pins to the bollard post when closed and shall lock to attachment posts by chain when kept open. NPS will provide padlocks for locking the gates and other components chains, pins, fasteners, and accessories shall be provided by the contractor.

d) Paint all metal finishes brown (NPS will provide exact color code) with high performance oil-based enamel paint.

MOJA – Install Flooring at OX Ranch House

e) Excavate and set gate posts and attachment posts in a 3’ x 3’ x 3’ concrete footing just outside of edge of pavement of road. Contractor shall set exact location of posts to assure proper opening and closure of the gates and gate elements in the field.

f) Excavate and set gate attachment posts according to the drawings assuring gate arms open with the flow of traffic of each lane and are slightly past parallel to edge of pavement when secured open.

g) Saw cut road to install removable bollard post and elements set in concrete. Bollard post shall be removable and base components will allow for minimal disturbance to vehicle traffic when the bollard is not installed.

h) Install highway approved reflective tape along the top post of the gate arms and around the top of each gate arm, attachment post, and bollard.

i) Assure gate arms swing fluidly, lock and open without use of force, weight, or additional tools. Pins and locking mechanism are easy to remove and use without hammers or adjustments.

j) Finished gate will be visually plumb and level, paint will be free of chips and scratches, fasteners and pins will be secure, and concrete foundations will be smooth and level.

k) All equipment tracks showing on unpaved surfaces will be raked, debris removed from site, and road swept of debris caused by the construction.

4. CONTRACTOR USE OF PREMISES

a) Contractor will keep worksite organized and clean as work allows

b) Designated areas for staging and contractor access will be identified by NPS COR

c) Contractor will be responsible for disposal of all construction debris and waste

d) Contractor will provide temporary traffic control while working in the road and road shoulders in accordance to the Nevada Department of Transportation Guidelines

e) Any government property damaged during this project will be replaced at the contractor’s expense

f) COR has the right to revoke any of the above privileges at anytime if cleanliness or unprofessional behavior warrants it

5. PERIOD OF PERFORMANCE:

All tasks and deliverables for this contract must be completed within 30 of days after award NTP. Days listed herein refer to calendar days.

5. PROJECT SUBMITTALS

a) Fabricator drawings for gate construction. Contractor shall provide final shop drawings before fabrication to NPS COR for approval to assure gate concept meets project requirements. This may include details of fasteners, hinges, and components.

File details come from the government source that posted it. Updated .