The amendment provides responses to contractor questions regarding the vehicle upfit scope and timelines. Key details include:
- Vehicles must be accepted and work begun immediately after award, with each vehicle required to be completed within 30 days. At least one vehicle should be completed by the end of May, with the remaining vehicles in June and July. All work must be finished within 120 days of award.
- Government-furnished equipment (GFE) includes some used items that have not been tested, so the contractor can request new equipment if there are concerns about the condition of the old items. The new GFE items have been confirmed compatible with the vehicles.
- The contractor can choose to upfit the two F-150 vehicles simultaneously.
The solicitation quotes are due by April 3, 2024 at 2:00 PM PDT. All other terms and conditions remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_-_Atch_2_-_Wage_Determination__CA_2015-5629.pdf | ||
| B08_-_Atch_1_-_SOW.pdf | ||
| Sol_140P8124Q0016.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8124Q0016 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPL
Boulder City NV 89005-2426 601 Nevada Way
DOI, NPS, PWR - LAKE MABO
PPL
Boulder City NV 89005-2426 601 Nevada Way
NPS, PWR - LAKE MABO
03/20/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
03/20/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
See Continuation Page
Period of Performance: 04/10/2024 to 08/08/2024
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Caroline Bachelier
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
140P8124Q0016 Amendment 0001
The purpose of this amendment is to answer contractor questions.
1) Questions and Answers:
a) Question: The solicitation references potential time frames regarding GSA vehicle returns. What are the actual date ranges that the 3 vehicles need to be started and completed by?
Answer: Upon awarding, ideally vehicles are accepted and work begins immediately, after coordination of drop off of the vehicles/equipment. Upon receipt of the vehicles, the contractor needs to complete each vehicle within 30 days. If each vehicle is done individually each vehicle has its own 30 days. If multiple vehicles are taken at the same time a different timeline can be discussed. We are in need of a completed vehicle in a shorter time frame and are hoping for atleast 1 built out by end of May (depending on awarding timeframe) with a follow up in June and July. All vehicles need to be done before September. The entire contract must be completed within 120 of being awarded.
b) Question: The solicitation references GFE that is to be used from previous service.
Is the contractor required to remove any of this equipment from older vehicles?
Answer: No. All equipment has already been removed from previous vehicles or is new in box.
c) Question: What items of the GFE are new versus old (previous service)?
Answer: Of items listed as GFE: the lightbar, radars, radio, siren control, gun rack, and a few select lights are old from previous builds. Everything else is new in box.
d) Question: Of GFE old items, have these items all been checked for correct operation and contain all accessory wiring and parts related to the specific item?
Answer: Since being removed from previous vehicles they have not been checked. If questions of age or quality of old GFE exists new equipment can be purchased (excluding radio) by contractor after conversation with POC/COR.
e) Question: Of the GFE, has it all been confirmed to be compatible with the vehicles it is to be installed in?
Answer: Of the new GFE, all items were specifically bought for the specific vehicles make/model where applicable.
f) Question: Can the 2 F150'S be up fitted simultaneously?
Answer: If the contractor decides they want to do the f150s simultaneously, that is acceptable. More time can be allocated after contract is awarded and discussion with POC for outfitting.
140P8124Q0016 Amendment 0001
2) All other terms and conditions remain the same. Quotes are due April 3, 2024, at 1400