Attach5_Questions_and_Answers_29_Aug_2024_0003.pdf

PDF 176 KB Posted

Attached to
RODENT INFESTATION WASTE CLEANUP Federal contract opportunity
Solicitation number
140P8124B0010
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document contains Questions and Answers related to Solicitation No. 140P8124B0010 for a Rodent Infestation Cleanup project at the Lake Mead National Recreation Area. The key details are:

The contractor or subcontractor performing the hazardous material removal must have a Nevada Department of Agriculture Pest Control License and a hazardous materials handling certification from the Institute of Inspection and Cleaning and Restoration Certification or equivalent. The awarded contractor must have an active SAM.gov registration and be certified as a small business under the applicable NAICS code. Subcontractors may be used. No mechanical plans exist for the building, and the government will not be providing specific ceiling tile specifications, though they are outlined in the Statement of Work.

View the file

Other files for this federal contract opportunity

Other files attached to RODENT INFESTATION WASTE CLEANUP, newest first.
File Type Posted
Sol_140P8124B0010_Amd_0004.pdf PDF
Sol_140P8124B0010_Amd_0003.pdf PDF
Building_Drawings_0002.pdf PDF
Sol_140P8124B0010_Amd_0002.pdf PDF
Sol_140P8124B0010_Amd_0001.pdf PDF
Attach1_Statement_of_Work.pdf PDF
Sol_140P8124B0010.pdf PDF
Attach2_Wage_Determination.pdf PDF
Attach3_Construction_Contract_Administration_Notice.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers #1 Solicitation No. 140P8124B0010

Rodent Infestation Cleanup August 29, 2024

1. What are the licensing and/ or certification requirements?

Contractor or subcontractor managing the hazardous material removal must have a Nevada Department of Agriculture Pest Control License and a hazard materials handling certification from Institute of Inspection and Cleaning and Restoration Certification or equivalent.

2. Does the offeror have to be a general contractor? If we can piggyback off a general contractor if they are not approved through APEX?

The awarded contractor must have an active registration in SAM.gov at time of bid submission and certify as a small business under the applicable NAICS code for this acquisition. Subcontractors may be used for this project.

3. When it comes to the hazardous certification, we are certified by The Institute of Inspection

Cleaning and Restoration Certification (IICRC) to remove sewer, mold, etc. Would this certification work as a hazardous?

Yes. See above answer to #1.

4. Will the government be able to supply existing mechanical plans for this project?

No mechanical plans exist for the building.

5. In SOW states installation of new ceiling grid and ceiling tiles. Is the government going to spec a specific ceiling tile for this project?

No, but there is specification in the Statement of Work.