Attach_1_-_Project_Specifications.pdf

PDF 3 MB Posted

Attached to
Replace Alan Bible Visitor Center HVAC and Roof
Solicitation number
140P8124B0002
Issued by

About this file

This document appears to be a set of project specifications for the replacement of the HVAC system and roof at the Alan Bible Visitor Center located at Lake Mead National Recreation Area in Boulder City, Nevada. The project is being solicited by the Department of the Interior's National Park Service Pacific West Region. The specifications cover detailed requirements for various construction and installation activities including demolition, concrete repair, metal fabrication, roofing, piping, HVAC equipment, and electrical work. Key products and services required include HVAC equipment, insulation, ductwork, piping, and electrical components. The document provides extensive technical details and requirements for these products and services. This appears to be a complete set of project specifications, rather than a summary document or template.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAKE 228968 & 334958_Div 1 Specs FINAL_1-29-24

LAKE 228968 & 334958_Div 2-49 Specs FINAL_1-29-24
DIVISION, SECTION & PARAGRAPH NUMBERING
DIVISION 02
EXISTING CONDITIONS
PART 2 - PRODUCTS - NOT USED. PART 3 - EXECUTION
3.2 PREPARATION
3.3 REPAIR / RESTORATION - NOT USED.
1.2 LIMITATIONS
1.3 STANDARDS
1.4 QUALIFICATIONS
1.5 PRECONSTRUCTION CONFERENCE
1.6 SUBMITTALS
1.7 PROJECT CONDITIONS
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.2 UTILITIES
3.3 CONCRETE SOUNDING AND LAYOUT
3.4 CONCRETE REMOVAL
3.5 QUALITY CONTROL INSPECTIONS
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.2 SHORING DESIGN REQUIREMENTS
3.3 SHORING INSTALLATION CERTIFICATION
3.4 REMOVAL OF SHORING
1.2 SUBMITTALS
1.3 SITE CONDITIONS
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.2 PREPARATION
3.3 DEMOLITION/ABANDONMENT
3.4 HAZARDOUS MATERIALS
3.5 DISPOSAL
3.6 SALVAGE
DIVISION 03
CONCRETE
1.2 REFERENCES
1.3 SUBMITTALS
PART 2 - PRODUCTS
PART 3 - EXECUTION
1.2 REFERENCES
1. ACI 318
1.3 SUBMITTALS
1.4 DELIVERY, STORAGE, AND HANDLING
PART 2 - PRODUCTS
PART 3 - EXECUTION
1.2 REFERENCES
1. ACI 318
1.3 SUBMITTALS
1.4 DELIVERY, STORAGE, AND HANDLING
PART 2 - PRODUCTS
2.2 FABRICATION - NOT USED. PART 3 - EXECUTION
1.2 REFERENCES
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.2 DEMOLITION
3.3 PREPARATION
3.4 PLACEMENT AND CURING OF REPAIR PRODUCTS FOR REPAIR AREAS
3.5 FIELD QUALITY CONTROL
3.6 CLEANING
1.2 DESCRIPTION
1.3 UNIT PRICES
1.4 PREINSTALLATION MEETINGS
1.5 ACTION SUBMITTALS
1.6 INFORMATION SUBMITTALS
1.7 QUALITY ASSURANCE
1.8 DELIVERY, STORAGE, AND HANDLING
1.9 PROJECT CONDITIONS
1.10 WARRANTY
PART 2 – PRODUCTS
2.2 ELASTOMERIC JOINT SEALANTS
2.3 JOINT-SEALANT BACKING
2.4 MISCELLANEOUS MATERIALS
PART 3 – EXECUTION
3.2 PREPARATION FOR SEALANT INSTALLATION
3.3 INSTALLATION OF JOINT SEALANTS
3.4 FIELD QUALITY CONTROL
3.5 CLEANING
3.6 PROTECTION
DIVISION 05
METALS
1.2 ACTION SUBMITTALS
1.3 QUALITY ASSURANCE
PART 2 – PRODUCTS
2.2 MATERIALS AND COMPONENTS
2.3 FASTENERS
2.4 MISCELLANEOUS MATERIALS
2.5 FABRICATION, GENERAL
2.6 SHELF ANGLES
2.7 MISCELLANEOUS STEEL TRIM
2.8 DOWNSPOUT GUARDS
2.9 LOOSE BEARING AND LEVELING PLATES
2.10 LOOSE STEEL LINTELS
2.11 STEEL WELD PLATES AND ANGLES
2.12 MISCELLANEOUS METAL ITEMS
2.13 FINISHES, GENERAL
2.14 STEEL AND IRON FINISHES
PART 3 – EXECUTION
3.2 PREPARATION
3.3 INSTALLATION, GENERAL
3.4 INSTALLING BEARING AND LEVELING PLATES
3.5 ADJUSTING AND CLEANING
1.2 RELATED WORK
1.3 REFERENCE
1.4 FIELD MEASUREMENTS
1.5 SUBMITTALS
PART 2 - PRODUCTS
2.2 FRAMES, COVERS, ACCESS HATCHES
2.3 DRY PIT/SUMP PUMP GRATE FRAMES
2.4 MANHOLE LADDERS
2.5 LADDER “SAFETY POST”
PART 3 - EXECUTION
3.2 GENERAL
DIVISION 06
WOOD, PLASTICS, & COMPONENTS
1.2 SECTION INCLUDES
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
PART 2 - PRODUCTS
2.2 ACCESSORIES
2.6 FACTORY WOOD TREATMENT
PART 3 - EXECUTION
3.2 GENERAL
3.3 FRAMING INSTALLATION
3.4 WOOD NAILERS & INSUALTION STOPS FOR ROOFING
3.5 DRILLING, CUTTING AND NOTCHING
3.6 ROUGH HARDWARE AND ADHESIVES
1. ASTM F844.
2. ASTM F1667:
3.7 SITE APPLIED WOOD TREATMENT
3.8 WORKMANSHIP
3.9 TOLERANCES
DIVISION 07
THERMAL & MOISTURE PROTECTION
1.2 RELATED WORK
1.3 APPLICABLE PUBLICATIONS
1.4 PREINSTALLATION MEETINGS
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.7 FIELD CONDITIONS
1.8 WARRANTY
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.2 RE-ROOFING PREPARATION – GENERAL
3.3 COMPLETE ROOFING SYSTEM REMOVAL
3.4 DECK PREPARATION
3.5 TEMPORARY ROOFING
3.6 BASE FLASHING REMOVAL
3.7 FIELD QUALITY CONTROL
3.8 DISPOSAL
1.2 SECTION INCLUDES
1.3 SUBMITTALS
1.4 SYSTEM DESCRIPTION
1.5 DELIVERY, STORAGE AND HANDLING
1.6 PROJECT CONDITIONS
PART 2 - PRODUCTS
PART 3 – EXECUTION
3.3 INSTALLATION
1.2 SUMMARY
1.3 DEFINITIONS
1.4 REFERENCES
C. AMERICAN STANDARD OF TESTING METHODS (ASTM):
D. AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI):
E. FACTORY MUTUAL (FM):
F. INTERNATIONAL CODES COUNCIL (ICC):
G. NATIONAL ROOFING CONTRACTOR’S ASSOCIATION (NRCA).
1.5 PREINSTALLATION MEETINGS
1.6 ACTION SUBMITTALS
1.7 INFORMATIONAL SUBMITTALS
1.8 CLOSEOUT SUBMITTALS
1.9 QUALITY ASSURANCE
1.9 DELIVERY, STORAGE, AND HANDLING
1.10 FIELD CONDITIONS
1.11 WARRANTIES
PART 2 – PRODUCTS
2.2 ROOFING SYSTEM BASIS OF DESIGN
2.3 PERFORMANCE REQUIREMENTS
2.4 FIELD SHEET MATERIALS
2.5 FLASHING SHEET MATERIALS
2.6 AUXILIARY ROOFING MATERIALS
2.7 ROOF INSULATION
2.8 INSULATION ACCESSORIES
2.9 WALKWAYS
PART 3 – EXECUTION
3.2 PREPARATION
3.3 INSTALLATION, GENERAL
3.4 THERMAL BOARD INSTALLATION
3.5 ROOFING INSTALLATION, GENERAL
3.6 INSULATION INSTALLATION
3.7 BASE SHEET INSTALLATION
3.8 FIELD INSTALLATION
3.9 FLASHING INSTALLATION
3.10 LIQUID-APPLIED FLASHING
3.11 WALKWAY INSTALLATION
3.12 FIELD QUALITY CONTROL
3.13 PROTECTING AND CLEANING
1.2 SECTION INCLUDES
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 WARRANTY / GUARANTEE
PART 2 - PRODUCTS
2.2 ACCESSORIES
2.3 FABRICATION
PART 3 - EXECUTION
3.2 PREPARATION
3.3 INSTALLATION - GENERAL
3.4 INSTALLATION – FLASHINGS
3.5 INSTALLATION – SEALANT
1.2 SECTION INCLUDES
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 ENVIRONMENTAL REQUIREMENTS
1.7 COORDINATION
1.8 GUARANTEE
PART 2 – PRODUCTS
2.2 PRIMER
2.3 ACCESSORIES
PART 3 – EXECUTION
3.2 EXAMINATION
3.3 PREPARATION
3.4 INSTALLATION – SEALANTS, GENERAL
3.5 CLEANING
3.6 PROTECTION OF FINISHED WORK
3.7 FIELD QUALITY CONTROL
DIVISION 08
OPENINGS
1.2 SUMMARY
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.7 PROJECT CONDITIONS
PART 2 - PRODUCTS
2.2 FABRICATION, GENERAL
2.3 FIXED, EXTRUDED-ALUMINUM LOUVERS
2.4 LOUVER SCREENS
2.5 WALL VENTS (BRICK VENTS)
2.6 FINISHES, GENERAL
2.7 ALUMINUM FINISHES
PART 3 - EXECUTION
3.2 PREPARATION
3.3 INSTALLATION
3.4 ADJUSTING AND CLEANING
DIVISION 09
FINISHES
1.2 SECTION INCLUDES
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 REGULATORY REQUIREMENTS
1.7 DELIVERY, STORAGE & HANDLING
1.8 PROJECT CONDITIONS
PART 2 - PRODUCTS
2.3 ACCESSORIES
PART 3 - EXECUTION
3.2 EXAMINATION
3.3 PROTECTION
3.4 GYPSUM BOARD INSTALLATION
3.5 INSTALLATION OF TRIM & ACCESSORIES
3.6 JOINT TREATMENT
3.7 TOLERANCES
3.8 CLEAN UP
1.2 SECTION INCLUDES
1.3 REFERENCES
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 REGULATORY REQUIREMENTS
1.7 DELIVERY, STORAGE, AND PROTECTION
1.8 ENVIRONMENTAL REQUIREMENTS
1.9 EXTRA MATERIALS
PART 2 - PRODUCTS
2.2 PAINTS AND COATINGS - GENERAL
2.3 ACCESSORY MATERIALS
PART 3 - EXECUTION
3.2 GWB FINISH INSPECTION WITH SECTION 09 29 00 & PROJECT SUPERINTENDENT
3.3 EXAMINATION
3.4 SURFACE PREPARATION
3.5 PROTECTION
3.6 APPLICATION
3.7 FINISHING MECHANICAL AND ELECTRICAL EQUIPMENT
3.8 CLEANING
3.9 BACK-PRIMING
3.10 SURFACES THAT DO NOT REQUIRE PAINT FINISH
3.11 SURFACES THAT REQUIRE PAINT FINISH
3.12 SCHEDULE - PAINT SYSTEMS (ALL WORK IS MPI PREMIUM GRADE)
DIVISION 22
PLUMBING
1.2 SUMMARY
1.3 ACTION SUBMITTALS
PART 2 - PRODUCTS
2.2 METAL PIPE HANGERS AND SUPPORTS
2.3 FIBERGLASS PIPE HANGERS
2.4 FIBERGLASS STRUT SYSTEMS
2.5 FASTENER SYSTEMS
2.6 PIPE STANDS
2.7 PIPE-POSITIONING SYSTEMS
2.8 MATERIALS
PART 3 - EXECUTION
3.2 HANGER AND SUPPORT INSTALLATION
3.3 EQUIPMENT SUPPORTS
3.4 METAL FABRICATIONS
3.5 ADJUSTING
3.6 PAINTING
3.7 HANGER AND SUPPORT SCHEDULE
1.2 ACTION SUBMITTALS
PART 2 - PRODUCTS
2.2 STENCILS
PART 3 - EXECUTION
3.2 INSTALLATION, GENERAL REQUIREMENTS
3.3 INSTALLATION OF EQUIPMENT LABELS, WARNING SIGNS, AND LABELS
1.2 ACTION SUBMITTALS
1.3 INFORMATIONAL SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 DELIVERY, STORAGE, AND HANDLING
1.6 COORDINATION
1.7 SCHEDULING
PART 2 - PRODUCTS
2.2 INSULATING CEMENTS
2.3 ADHESIVES
2.4 MASTICS AND COATINGS
2.5 LAGGING ADHESIVES
2.6 SEALANTS
2.7 FACTORY-APPLIED JACKETS
2.8 FIELD-APPLIED JACKETS
a. 3M.
2.9 FIELD-APPLIED FABRIC-REINFORCING MESH
2.10 FIELD-APPLIED CLOTHS
2.11 TAPES
2.12 SECUREMENTS
2.13 PROTECTIVE SHIELDING GUARDS
PART 3 - EXECUTION
3.2 PREPARATION
3.3 GENERAL INSTALLATION REQUIREMENTS
3.4 PENETRATIONS
3.5 GENERAL PIPE INSULATION INSTALLATION
3.6 INSTALLATION OF FLEXIBLE ELASTOMERIC INSULATION
3.7 INSTALLATION OF GLASS-FIBER INSULATION
3.8 INSTALLATION OF PHENOLIC INSULATION
3.9 INSTALLATION OF POLYOLEFIN INSULATION
3.10 INSTALLATION OF FIELD-APPLIED JACKETS
3.11 FINISHES
3.12 FIELD QUALITY CONTROL
3.13 PIPING INSULATION SCHEDULE, GENERAL
3.14 INDOOR PIPING INSULATION SCHEDULE
3.15 OUTDOOR, ABOVEGROUND PIPING INSULATION SCHEDULE
3.16 INDOOR, FIELD-APPLIED JACKET SCHEDULE
1.2 ACTION SUBMITTALS
1.3 INFORMATIONAL SUBMITTALS
1.4 FIELD CONDITIONS
1.5 WARRANTY
PART 2 - PRODUCTS
2.2 PIPING MATERIALS
2.3 GALVANIZED-STEEL PIPE AND FITTINGS
2.4 DUCTILE-IRON PIPE AND FITTINGS
2.5 COPPER TUBE AND FITTINGS
2.6 ABS PIPE AND FITTINGS
2.7 SPECIALTY PIPE FITTINGS
PART 3 - EXECUTION
3.2 JOINT CONSTRUCTION
3.3 INSTALLATION OF SPECIALTY PIPE FITTINGS
3.4 INSTALLATION OF HANGERS AND SUPPORTS
3.5 CONNECTIONS
3.6 IDENTIFICATION
3.7 FIELD QUALITY CONTROL
3.8 CLEANING AND PROTECTION
3.9 PIPING SCHEDULE
1.2 SUMMARY
1.3 DEFINITIONS
1.4 ACTION SUBMITTALS
1.5 INFORMATIONAL SUBMITTALS
1.6 CLOSEOUT SUBMITTALS
PART 2 - PRODUCTS
2.2 MISCELLANEOUS SANITARY DRAINAGE PIPING SPECIALTIES
PART 3 - EXECUTION
3.2 PIPING CONNECTIONS
3.3 LABELING AND IDENTIFYING
3.4 PROTECTION
DIVISION 23
HEATING, VENTILATING, & AIR CONDITIONING (HVAC)
1.2 SUMMARY
1.3 DEFINITIONS
1.4 ACTION SUBMITTALS
1.5 INFORMATIONAL SUBMITTALS
1.6 CLOSEOUT SUBMITTALS
1.7 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 ANTIMICROBIAL SURFACE TREATMENT
PART 3 - EXECUTION
3.2 CLEANING
3.3 CLEANLINESS VERIFICATION
3.4 RESTORATION
3.5 PROJECT CLOSEOUT
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
1.7 COORDINATION
PART 2 - PRODUCTS
2.2 PIPE, TUBE, AND FITTINGS
2.3 JOINING MATERIALS
2.4 TRANSITION FITTINGS
a. NIBCO INC.
2.5 DIELECTRIC FITTINGS
2.6 MECHANICAL SLEEVE SEALS
2.7 SLEEVES
2.8 ESCUTCHEONS
2.9 GROUT
PART 3 - EXECUTION
3.2 PIPING JOINT CONSTRUCTION
3.3 PIPING CONNECTIONS
3.4 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS
3.5 PAINTING
3.6 CONCRETE BASES
3.7 ERECTION OF METAL SUPPORTS AND ANCHORAGES
3.8 ERECTION OF WOOD SUPPORTS AND ANCHORAGES
3.9 GROUTING
1.2 SUMMARY
1.3 COORDINATION
PART 2 - PRODUCTS
2.2 MOTOR CHARACTERISTICS
2.3 POLYPHASE MOTORS
2.4 ADDITIONAL REQUIREMENTS FOR POLYPHASE MOTORS
2.5 SINGLE-PHASE MOTORS
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 METAL PIPE HANGERS AND SUPPORTS
2.3 TRAPEZE PIPE HANGERS
2.4 FIBERGLASS PIPE HANGERS
2.5 PLASTIC PIPE HANGERS
2.6 METAL FRAMING SYSTEMS
2.7 FIBERGLASS STRUT SYSTEMS
2.8 THERMAL-HANGER SHIELD INSERTS
2.9 FASTENER SYSTEMS
2.10 PIPE STANDS
2.11 EQUIPMENT SUPPORTS
2.12 OUTDOOR EQUIPMENT STANDS
2.13 MATERIALS
PART 3 - EXECUTION
3.2 HANGER AND SUPPORT INSTALLATION
3.3 EQUIPMENT SUPPORTS
3.4 METAL FABRICATIONS
3.5 ADJUSTING
3.6 PAINTING
3.7 HANGER AND SUPPORT SCHEDULE
1.2 SUMMARY
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 ACTION SUBMITTALS
1.5 ACTION SUBMITTALS
1.6 INFORMATIONAL SUBMITTALS
1.7 CLOSEOUT SUBMITTALS
1.8 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 FLEXIBLE DUCT CONNECTORS
2.4 VIBRATION ISOLATION EQUIPMENT BASES
2.5 SEISMIC-RESTRAINT DEVICES
2.6 THRUST RESTRAINT MATERIALS
2.7 FACTORY FINISHES
PART 3 - EXECUTION
3.2 APPLICATIONS
3.3 VIBRATION-CONTROL AND SEISMIC-RESTRAINT DEVICE INSTALLATION
3.4 ACCOMMODATION OF DIFFERENTIAL SEISMIC MOTION
3.5 FIELD QUALITY CONTROL
3.6 ADJUSTING
3.7 HVAC VIBRATION-CONTROL AND SEISMIC-RESTRAINT DEVICE SCHEDULE
B. HVAC EQUIPMENT VIBRATION ISOLATION SCHEDULE
1.2 ACTION SUBMITTALS
PART 2 - PRODUCTS
2.2 EQUIPMENT LABELS
2.3 WARNING SIGNS AND LABELS
2.4 WARNING TAPE
2.5 PIPE LABELS
2.6 DUCT LABELS
2.7 STENCILS
2.8 VALVE TAGS
2.9 WARNING TAGS
PART 3 – EXECUTION
3.2 INSTALLATION OF DUCT LABELS
3.3 INSTALLATION OF VALVE TAGS
3.4 INSTALLATION OF WARNING TAGS
1.2 SUMMARY
1.3 DEFINITIONS
1.4 PREINSTALLATION MEETINGS
1.5 INFORMATIONAL SUBMITTALS
1.7 QUALITY ASSURANCE
1.8 FIELD CONDITIONS
3.1 EXAMINATION
3.2 PREPARATION
3.3 GENERAL PROCEDURES FOR TESTING AND BALANCING
3.4 TESTING, ADJUSTING, AND BALANCING OF HVAC EQUIPMENT
3.5 GENERAL PROCEDURES FOR BALANCING AIR SYSTEMS
3.6 PROCEDURES FOR CONSTANT-VOLUME AIR SYSTEMS
3.7 PROCEDURES FOR MOTORS
3.8 PROCEDURES FOR COILS
3.9 DUCT LEAKAGE TESTS
3.10 HVAC CONTROLS VERIFICATION
3.11 PROCEDURES FOR TESTING, ADJUSTING, AND BALANCING EXISTING SYSTEMS
3.12 TOLERANCES
3.13 PROGRESS REPORTING
3.14 FINAL REPORT
3.15 VERIFICATION OF TAB REPORT
3.16 ADDITIONAL TESTS
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
1.7 COORDINATION
1.8 SCHEDULING
PART 2 - PRODUCTS
2.2 INSULATING CEMENTS
2.3 FIRE-RATED INSULATION SYSTEMS
2.4 ADHESIVES
2.5 MASTICS AND COATINGS
2.6 LAGGING ADHESIVES
2.7 SEALANTS
2.8 FACTORY-APPLIED JACKETS
2.9 FIELD-APPLIED FABRIC-REINFORCING MESH
2.10 FIELD-APPLIED CLOTHS
2.11 FIELD-APPLIED JACKETS
2. .12 TAPES
2.13 SECUREMENTS
2) GEMCO; CD.
2. 14 CORNER ANGLES
PART 3 - EXECUTION
3.2 PREPARATION
3.3 GENERAL INSTALLATION REQUIREMENTS
3.4 PENETRATIONS
F. INSTALLATION OF CALCIUM SILICATE INSULATION
G. CELLULAR-GLASS INSULATION INSTALLATION
H. FLEXIBLE ELASTOMERIC INSULATION INSTALLATION
I. INSTALLATION OF MINERAL-FIBER INSULATION
3.5 FIELD-APPLIED JACKET INSTALLATION
3.6 FIRE-RATED INSULATION SYSTEM INSTALLATION
3.7 FINISHES
3.8 FIELD QUALITY CONTROL
3.9 DUCT INSULATION SCHEDULE, GENERAL
3.10 INDOOR DUCT AND PLENUM INSULATION SCHEDULE
3.11 ABOVEGROUND, OUTDOOR DUCT AND PLENUM INSULATION SCHEDULE
B. PIPING INSULATION SCHEDULE, GENERAL
F. INDOOR PIPING INSULATION SCHEDULE
G. OUTDOOR, ABOVEGROUND PIPING INSULATION SCHEDULE
H. INDOOR, FIELD-APPLIED JACKET SCHEDULE
I. OUTDOOR, FIELD-APPLIED JACKET SCHEDULE
1.2 ACTION SUBMITTALS
1.3 INFORMATIONAL SUBMITTALS
1.4 CLOSEOUT SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 DELIVERY, STORAGE, AND HANDLING
PART 2 - PRODUCTS
2.2 COPPER TUBE AND FITTINGS
2.3 STEEL PIPE AND FITTINGS
2.4 VALVES AND SPECIALTIES
2.5 REFRIGERANTS
PART 3 - EXECUTION
3.2 VALVE AND SPECIALTY APPLICATIONS
3.3 INSTALLATION OF PIPING, GENERAL
3.4 PIPE JOINT CONSTRUCTION
3.5 INSTALLATION OF HANGERS AND SUPPORTS
3.6 FIELD QUALITY CONTROL
3.7 SYSTEM CHARGING
3.8 ADJUSTING
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 SINGLE-WALL RECTANGULAR DUCTS AND FITTINGS
2.3 DOUBLE-WALL RECTANGULAR DUCTS AND FITTINGS
2.4 SINGLE-WALL ROUND AND FLAT-OVAL DUCTS AND FITTINGS
2.5 DOUBLE-WALL ROUND AND FLAT-OVAL DUCTS AND FITTINGS
2.6 SHEET METAL MATERIALS
2.7 FLEXIBLE DUCTS:
2.8 DUCT LINER
2.9 SEALANT AND GASKETS
2.10 HANGERS AND SUPPORTS
2.11 SEISMIC-RESTRAINT DEVICES
PART 3 - EXECUTION
3.2 INSTALLATION OF EXPOSED DUCTWORK
3.3 DUCTWORK EXPOSED TO WEATHER
3.4 DUCT SEALING
3.5 HANGER AND SUPPORT INSTALLATION
3.6 CONNECTIONS
3.7 PAINTING
3.8 FIELD QUALITY CONTROL
3.9 DUCT CLEANING
3.10 STARTUP
3.11 DUCT SCHEDULE
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 CLOSEOUT SUBMITTALS
1.6 MAINTENANCE MATERIAL SUBMITTALS
PART 2 - PRODUCTS
2.2 MANUAL VOLUME DAMPERS
2.3 DUCT-MOUNTED ACCESS DOORS
2.4 FLEXIBLE CONNECTORS
2.5 DUCT ACCESSORY HARDWARE
2.6 MATERIALS
PART 3 - EXECUTION
3.2 FIELD QUALITY CONTROL
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 CLOSEOUT SUBMITTALS
1.6 MAINTENANCE MATERIAL SUBMITTALS
PART 2 - PRODUCTS
2.2 SQUARE IN-LINE CENTRIFUGAL FANS
2.3 UTILITY SET FANS
2.4 MOTORS
2.5 SOURCE QUALITY CONTROL
PART 3 - EXECUTION
3.2 DUCTWORK AND PIPING CONNECTIONS
3.3 ELECTRICAL CONNECTIONS
3.4 CONTROL CONNECTIONS
3.5 .STARTUP SERVICE:
3.6 ADJUSTING
3.7 CLEANING
3.8 FIELD QUALITY CONTROL
3.9 DEMONSTRATION
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
2.1 PERFORATED DIFFUSERS
PART 3 - EXECUTION
3.2 INSTALLATION
3.3 ADJUSTING
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
PART 2 - PRODUCTS
2.2 SOURCE QUALITY CONTROL
PART 3 - EXECUTION
3.2 INSTALLATION
3.3 ADJUSTING
1.2 SUMMARY
1.3 DEFINITIONS
1.4 ACTION SUBMITTALS
1.5 INFORMATIONAL SUBMITTALS
1.6 FIELD CONDITIONS
1.7 CLOSEOUT SUBMITTALS
1.8 MAINTENANCE MATERIAL SUBMITTALS
1.9 WARRANTY
PART 2 - PRODUCTS
2.2 MANUFACTURERS
2.3 UNIT CASINGS
2.4 FANS, DRIVES, AND MOTORS
2.5 COILS
2.6 REFRIGERANT CIRCUIT COMPONENTS
2.7 AIR FILTRATION
2.8 DAMPERS
2.9 ELECTRICAL POWER CONNECTIONS
2.10 CONTROLS
2.11 ROOF CURBS
2.12 ACCESSORIES
2.13 MATERIALS
2.14 SOURCE QUALITY CONTROL
PART 3 - EXECUTION
3.2 INSTALLATION
3.3 PIPING CONNECTIONS
3.4 DUCT CONNECTIONS
3.5 ELECTRICAL CONNECTIONS
3.6 CONTROL CONNECTIONS
3.7 FIELD QUALITY CONTROL
3.8 STARTUP SERVICE
3.9 ADJUSTING
3.10 CLEANING
3.11 FIELD QUALITY CONTROL
3.12 DEMONSTRATION
1.2 SUMMARY
1.3 ACTION SUBMITTALS
1.4 INFORMATIONAL SUBMITTALS
1.5 CLOSEOUT SUBMITTALS
1.6 MAINTENANCE MATERIAL SUBMITTALS
1.7 QUALITY ASSURANCE
1.8 COORDINATION
1.9 WARRANTY
PART 2 - PRODUCTS
2.4 ACCESSORIES
PART 3 - EXECUTION
3.2 CONNECTIONS
3.3 FIELD QUALITY CONTROL
3.4 STARTUP SERVICE
3.5 DEMONSTRATION
DIVISION 26
ELECTRICAL
1.2 MINIMUM REQUIREMENTS
1.3 TEST STANDARDS
1.4 QUALIFICATIONS (PRODUCTS AND SERVICES)
1.5 APPLICABLE PUBLICATIONS
1.6 MANUFACTURED PRODUCTS
1.7 EQUIPMENT REQUIREMENTS
1.8 EQUIPMENT PROTECTION
1.9 WORK PERFORMANCE
1.10 EQUIPMENT INSTALLATION AND REQUIREMENTS
1.11 EQUIPMENT IDENTIFICATION
1.12 SUBMITTALS
1.13 SINGULAR NUMBER
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 EXISTING CONDITIONS
1.6 COORDINATION
1.7 MAINTENANCE
1.8 WARRANTY
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.2 EQUIPMENT IDENTIFICATION
3.3 NOISE AND VIBRATION
3.4 GENERAL INSTALLATION METHODS
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 COORDINATION
PART 2 - PRODUCTS
2.2 CONNECTORS AND SPLICES
2.3 SLEEVES FOR CABLES
2.4 SLEEVE SEALS
PART 3 - EXECUTION
3.2 CONDUCTOR INSULATION AND MULTI-CONDUCTOR CABLE APPLICATIONS AND WIRING METHODS
3.3 INSTALLATION OF CONDUCTORS AND CABLES
3.4 CONNECTIONS
3.5 SLEEVE INSTALLATION FOR ELECTRICAL PENETRATIONS
3.6 SLEEVE-SEAL INSTALLATION
3.7 INSPECTION AND TESTS
1.2 SUMMARY
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 CONNECTORS
2.3 GROUNDING SYSTEM DEVICES
PART 3 - EXECUTION
3.2 EQUIPMENT GROUNDING
3.3 INSTALLATION
3.3 TESTING
1.2 SUMMARY
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 SUBMITTALS
PART 2 - PRODUCTS
2.2 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES
PART 3 - EXECUTION
3.2 SUPPORT INSTALLATION
3.3 INSTALLATION OF FABRICATED METAL SUPPORTS
3.4 PAINTING
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
PART 2 - PRODUCTS
D. IMC: ANSI C80.6.
2.2 NONMETALLIC CONDUIT AND TUBING
C. LFNC: UL 1660.
2.3 METAL WIREWAYS
2.4 BOXES, ENCLOSURES, AND CABINETS
PART 3 - EXECUTION
3.2 INSTALLATION
3.3 PROTECTION
1.2 RELATED DOCUMENTS
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
PART 2 – PRODUCTS
PART 3 – EXECUTION
3.2 APPLICATIONS
3.3 SEISMIC-RESTRAINT DEVICE INSTALLATION
3.4 ACCOMMODATION OF DIFFERENTIAL SEISMIC MOTION
3.5 FIELD QUALITY CONTROL
1.2 SUMMARY
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 COORDINATION
PART 2 – PRODUCTS
2.2 EQUIPMENT IDENTIFICATION LABELS
2.3 MISCELLANEOUS IDENTIFICATION PRODUCTS
PART 3 - EXECUTION
3.2 IDENTIFICATION SCHEDULE
1.2 SUMMARY
1.3 DEFINITIONS
1.4 PERFORMANCE REQUIREMENTS
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.7 DELIVERY, STORAGE, AND HANDLING
1.8 PROJECT CONDITIONS
1.9 COORDINATION
1.10 WARRANTY
1.11 EXTRA MATERIALS
PART 2 – PRODUCTS
2.2 DISTRIBUTION PANELBOARDS
2.3 LIGHTING AND APPLIANCE BRANCH-CIRCUIT PANELBOARDS
2.4 DISCONNECTING AND OVERCURRENT PROTECTIVE DEVICES
2.5 PANELBOARD SUPPRESSORS
2.6 ACCESSORY COMPONENTS AND FEATURES
PART 3 – EXECUTION
3.2 INSTALLATION
3.3 IDENTIFICATION
3.4 FIELD QUALITY CONTROL
3.5 ADJUSTING
3.6 PROTECTION
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
PART 2 - PRODUCTS
2.2 STRAIGHT BLADE RECEPTACLES
2.3 GFCI RECEPTACLES
2.4 TWIST-LOCKING RECEPTACLES
2.5 WALL PLATES
2.6 FINISHES
PART 3 - EXECUTION
3.2 IDENTIFICATION
3.3 FIELD QUALITY CONTROL
1.2 SUMMARY
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 PROJECT CONDITIONS
1.6 COORDINATION
1.7 EXTRA MATERIALS
PART 2 – PRODUCTS
2.2 CARTRIDGE FUSES
2.3 PLUG FUSES
2.4 PLUG-FUSE ADAPTERS
PART 3 – EXECUTION
3.2 INSTALLATION
3.3 IDENTIFICATION
1.2 SUMMARY
1.3 DEFINITIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.6 PROJECT CONDITIONS
1.7 COORDINATION
1.8 EXTRA MATERIALS
PART 2 - PRODUCTS
2.2 NONFUSIBLE AND MANUAL SWITCHES
2.3 ENCLOSURES
PART 3 - EXECUTION
3.2 INSTALLATION
3.3 IDENTIFICATION
3.4 ADJUSTING

File details come from the government source that posted it. Updated .