Questions_and_Answers_0001.pdf
PDF 119 KB Posted
- Attached to
- Lakeview Accessibility Federal contract opportunity
- Solicitation number
- 140P6423B0008
About this file
This document contains questions and answers regarding a federal solicitation for the Lakeview Accessibility Improvements project. The solicitation will require a prime contractor to provide all labor, materials, tools and equipment for accessibility upgrades to concrete structures, walks, lighting, and landscaping at Indiana Dunes National Park. Work includes installing accessible ramps, seating areas, walks, seven solar lights, sand fill, beach access matting, and landscaping. Two optional items are benches and additional matting. The firm-fixed price contract is set aside for total small businesses between $500,000 to $750,000. The solicitation will be issued requiring registration in SAM.gov and an UEI number to be awarded. The site visit and pre-bid details will be in the solicitation. The National Park Service Midwest Region is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Drawings_-_Bench_Locations_0001.pdf | ||
| Sol_140P6423B0008_Amd_0001.pdf | ||
| Specifications_-_Lakeview_Accessibility.pdf | ||
| Sol_140P6423B0008.pdf | ||
| Attachment_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Attachment_-_Addendum_to_Specifications.pdf | ||
| Notice_to_Contractors.pdf | ||
| Attachment_-_Submittal_List.pdf | ||
| Attachment_-_Structural_Tests_and_Inspections.pdf | ||
| Attachment_-_Drawings.pdf | ||
| Wage_Determination_-_Porter_Co.pdf | ||
| Construction_Contract_Administration.pdf | ||
| Bid_Schedule_-_Lakeview_Accessibility.xlsx | XLSX spreadsheet | |
| Bid_Schedule_-_Lakeview_Accessibility.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: 140P6423B0008 Amendment #: 0001
Lakeview Accessibility Improvements - INDU
Questions and Answers listed below:
QUESTIONS:
Question # Question Answer/Response 1.
Option 02 for this project is to furnish and install the park benches. Specification 129340-1.4-A states to install at locations according to plans. Please advise where these are located on the plans and shown on the drawings.
See Bench Locations on Drawings Page 9 LA1.0. See red marks on attached file.
2.
Our company manufactures and markets Solar parking and street lighting. We can remove and replace poles to Solar street lights and was wondering if the bid can be separated to be able to address the lighting?
The work will not be separated and is a firm fixed price contract to a prime contractor who will be required to perform all aspects of the work under a single contract.
The prime can hire subs as needed to perform different aspects of the work, but the prime has the full responsibility of ensuing all work is completed accordingly per the project specifications.
3.
The attached information was received regarding the Soltech lighting. According to a Soltech representative, there should be 7 lights on drawing C2.0. Only 6 have been counted. The Soltech representative has provided an attachment that he worked on for the architect. It appears that one of the lights may have been blocked out by a note on C2.0.
Yes, the project requires the installation of 7 lights, sheets C3.0 & C4.0 shows the location of the light that was blocked out by a note on sheet C2.0.