Amd_0001_Atch_1_Questions-Answers_0001.pdf
PDF 126 KB Posted
- Attached to
- CHAM Theater Seating Federal contract opportunity
- Solicitation number
- 140P6324Q0043
About this file
This document is a set of Questions and Answers related to Solicitation # 140P6324Q0043 for the reupholstering of theater seats at the Chamizal National Memorial.
The key details are:
The solicitation allows for the work to be done either on-site or off-site, with the contractor responsible for removing, transporting, and reinstalling the seats if working off-site. The government will provide space on-site for the contractor to perform the work. The existing foam and fabric can be removed while the seat standards remain in place, as the seats have varying attachment methods. The government provided the dimensions of the theater seat tops (21"x21"x1" foam) and bottoms (24"x24"x4" foam). The solicitation is being issued by the Department of the Interior National Park Service Midwest Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6324Q0043_Amd_0002.pdf | ||
| B09_Amd_0002_Atch_1_Questions-Answers_8_6_23_0002.pdf | ||
| Sol_140P6324Q0043_Amd_0001.pdf | ||
| B08_Atch_4_DOL_Wage_Determination_2015-5229.pdf | ||
| B08_Atch_1_SOW.pdf | ||
| Sol_140P6324Q0043.pdf | ||
| B08_Atch_3_Experience_Questionnaire.xls | XLS spreadsheet | |
| B08_Atch_2_Price_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Chamizal National Memorial-Reupholster Theater Seats Solicitation # 140P6324Q0043
Question 1: Would the Government allow replacing the foam and reupholstery on site? Would the Government allow replacing and reupholstery off site such as removing/disassembling 100 seats and transporting them back and forth?
Reference: 4.1 Detailed Project Description in SOW
Government Response:
Per the specifications, work can be accomplished on site, the National Park Service will provide a space for the contractor to conduct the service. The space must be returned to its original state and the floor must be protected by ram board.
Per the specifications, If the Contractor chooses to work offsite. The Contractor is responsible for taking seats out and shipping them to the work site. The park service will not be responsible for removing seats and shipping the seats to the work site. Work can be done on park grounds. AC power is available to the contractor. If the seats do need to be removed and shipped off site, the contractor is responsible for the logistics and removal. The space must be returned to its original state.
Reference: 4.1 Detailed Project Description in SOW
Question 2: Can the Government confirm that if the seats standards are left in place and anchored into the floor can the existing foam and fabric pieces be removed to reupholster/replace the fabric and foam?
Government Response:
The Government will allow the removal of the existing foam and fabric pieces to be removed to reupholster/replace the fabric and foam. Please note that the seat will have to be unattached. The top and arm rest are together. Some of the seats are attached together. There is no uniform anchoring it depends on seat.
Reference: 4.1 Detailed Project Description in SOW
Question 3: Can the Government provide theater seat dimensions?
Government Response:
The top part of the seat:
length 21 inches width 21 inches foam depth is 1 inch thick.
The bottom part of the seat length 24 inches width 24 inches foam depth is 4 inches thick.
File details come from the government source that posted it. Updated .