This document contains answers to questions from potential offerors regarding a solicitation for the rehabilitation of a ranch house and terrace walls at a National Park Service site in the Midwest region. Key details include that the work involves restoration of crown molding, repair of interior lath and plaster, replacement of wallpaper which may damage plaster, and replacement of windows. The period of performance is 180 days but offerors may propose an alternate schedule with additional time. The contractor is responsible for shoring designs and temporary heating. All wood used must be FSC certified and windows pre-1940 are unlikely to contain hazardous materials. The pre-bid sign-in sheet will be published in an amendment. Lead paint can be removed, stabilized, or encapsulated.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTION ANSWER
1. What is the reasoning behind the 20% Bid Bond? Normally we provide a 5% Bid Bond. Is this standard practice for the National Park Service? Is it because of the type of project this is?
In accordance with FAR 28.101-2, the bid guarantee shall be at least 20% of the bid price.
The amount protects the Government from loss should the successful bidder fail to execute further contractual documents and bonds as required.
1. The Buy American provision-what percentage will be required and what items are affected?
Please see FAR 52.225-9. No percentage is specified.
2. Can the Project Superintendent also perform the duties of the Quality Control Supervisor?
Yes
3. Can the Project Superintendent also perform the duties of the Environmental Manger?
Yes
4. Is Submittal Exchange acceptable to use for the submittal process as an FTP site?
The National Park Service uses a Submittal Exchange document that the contractor will send via email to the Contract Specialist.
5. Project Plans Sheet P0.0 states Bid Option #2 is for all plumbing work that is not directly associated with the Mechanical Systems. Is this correct? As Plan Sheet G1.1 CLIN 003 & 004 are the bid option and cover Site Wall Rehabilitation 1 & 2.
CLIN definitions on sheet G1.1 take precedence.
6. After walking the site and reviewing the project plan, it is of our opinion that this project cannot be completed within the 180 period of performance with the submittal process, project execution and closeout.
Would the Government increase the period of performance to 365 days?
You are encouraged to prepare your proposal assuming the 180 calendar day period of performance; however, you are also able to provide a second proposal with additional days incorporated into the period of performance. It is highly recommended that you attach a justification to this increased period of performance.
7. Division 0100: Drawing C1.1 has a note that refers CLINs 1-4 to Specification 01-27-00 for complete definition of CLINS 1-4 Specification Section 01-27-00 Does not include specific Definition of Contract Line Items. Please revise specification section 01-27-00 to provide complete description of CLINS.
CLIN #01 thru CLIN #04 are defined on Sheet G1.1 and further identified on the plan view on sheet G1.1.
8. Division 9900: Please confirm finish required for front double doors.
Paint
9. Division 9900: Please confirm finish to ABA Decking and Ramp
Stain
10. Division 9900: Specs require Crown Molding to receive P1 Matte while, Item 3.0#4 states match existing which is semi-gloss.
Match existing semi-gloss.
11. Division 9900: Does NPS require Crown Molding to be fully stripped or just removal of peeling previous coating.
The existing finish may be removed. Fully stripping of existing finish is not required.
12. Division 9900: Does the Crown Molding have lead based paint?
No
13. Division 9900: Does any ceiling or walls have lead based paint?
No
14. Division 9900: Does the exterior trim require painting?
Yes
15. Division 9900: Does the Southwest Porch require repainting?
No
16. Is the NPS willing to modify the period of performance based on a schedule of construction that will include preconstruction submittals, action submittals and review and construction?
You are encouraged to prepare your proposal assuming the 180 calendar day period of performance; however, you are also able to provide a second proposal with additional days incorporated into the period of performance. It is highly recommended that you attach a justification to this increased period of performance.
17. The drawing requires shoring by the contractor of parts of the existing structure during structural remedial and new construction work. Will the Engineer of Record provide load calculations and design of the shoring, or will the contractor be required to provide shoring designs and calculations using a Structural Engineer certified in the State of Kansas?
The shoring design is the responsibility of contractor and requires the seal of a Kansas Professional Engineer.
18. Specification 01-81-13-13b, Item 1.2 Chain of Custody: Please confirm that all wood procured and used for any and all installations (even if used to repair or replace existing wood construction installed in 1890) must be FSC accredited certification.
Confirmed.
19. Specification 08-08-08, Glass in Existing Windows: Please advise us of the anticipated age of the existing glass in the windows that require replacement. (Note: existing glass manufactured prior to 1930-40 may contain chemicals that react with solar film, thereby making the application of solar film a possible warranty problem)
Records indicate the all windows below the third floor have been replaced within the last 20 years.
Based on records, no pre 1940 glass should remain.
20. Is it possible to extend the proposal due date to February 17, 2020?
Please see the proposal due date in the amendment.
21. Windows: The specifications & the "Window Schedule" are conflicted. The Window Schedule shows minimal work and very little
The specifications define the types of work. The Window Schedule identifies the extent of the work.
sash removal. Yet, the Specifications indicate total restoration. Please clarify.
22. Are the exterior transom windows to be restored?
As defined in the Window Schedule or as required to complete other tasks defined in the Window Schedule.
23. Please confirm that “Attachment 6 – Blank Proposal Template” is the document referred to in Section B as the Bid Schedule.
Confirmed.
24. Please confirm that the Excel File (Attachment 6) is to be submitted as is, with no modifications or calculation changes.
Confirmed.
25. Please confirm that the Blank Proposal Template (Attachment 6) must include content in all cells currently blank.
Confirmed.
26. Sheet G1.1 Contract Line Items Plan directs us to “Reference Specification Section 01 27 00 for the Full CLIN Descriptions” however on page 14 of Attachment 1 – Div. Section 01 27 00 there is no description of the CLINs. Please identify where we can find the Full Description of the CLINS as referenced on G1.1.
See response to question 7.
27. Per Incorporated Clause 52.236.14 “Availability and Use of Utility Services” – please confirm that all temporary heating solutions as necessary would be the responsibility of the contractor to obtain the fuel source; as Natural Gas nor propane service is provided by the National Park Service per the above clause.
Confirmed. The contractor shall provide their own fuel source.
28. Please confirm if an additional Formal Site Visit or Pre-bid is to be scheduled.
No, no other site visits are scheduled.
29. Please confirm that the Pre-Bid attendees sign-in sheet will be published through Amendment.
Confirmed.
30. Per H1.0 Abatement Summary of Hazardous Materials & General Notes states in Note 5 “Remove Lead Based Paints from Wood & Trim Components throughout the Interior as appropriate based on the overall scope.”
Please confirm if the term remove indicates complete abatement to raw material, or if encapsulation is acceptable.
Per the note at the end of the Lead Based Paints Summary Table (located in the upper left corner of sheet H1.0); Paints on Wood Trim/Components, which may be affected by interior renovation scope of work may be either removed, stabilized and/or encapsulated.
31. Provide a scope of work for each room for repairs to crown molding and repair to interior lath and plaster.
Reference Interior Elevation (sheets A7.0, A7.1, A7.2, A7.3, A7.4, A7.5), the Finish Schedule on Sheet A10.1 and specification section 09 01 20 91, Plaster Restoration.
32. Please provide a defined scope of work for replacing wall-paper. We are concerned that removal of wall-paper installed in 1985 will damage the lath and plaster and will require repairs that are difficult to estimate, can we insert an allowance or maximum square foot of repaired plaster.
Reference Interior Elevation (sheets A7.0, A7.1, A7.2, A7.3, A7.4, A7.5), the Finish Schedule on Sheet A10.1 and specification section 09 72 23, Wallpapering.
Damage to lath and plaster caused by removal of wall paper will be the contractor’s responsibility.
An allowance will not be permitted.