Q: Does the contractor have to follow the statement of work word for word or can they provide suggestions where they believe improvements are needed?

A: In this instance, the contractor may submit a Request for Information to the Contracting Officer (Diana_Vanderzanden@nps.gov). The contractor must reference the Page Number and paragraph within the Scope of Work AND identify the clarification needed.

Q: Are there technical drawings available for the system?

A: As built drawings are available for companies that require information on the current system as configured. Access to printed files are available at the customer's facility.

Q: Can equipment racks be mounted to the back wall VS the ceiling?

A: Contractors may provide individual installation methodologies if they are appropriate and in compliance with industry standards.