Attachment_2_-_Question_Answer_Document.docx

DOCX document 13 KB Posted

Attached to
Audio/Video System Modifications - Purchase and Installation - MWRO Federal contract opportunity
Solicitation number
140P6018R0033
Issued by
Department of the Interior National Park Service

About this file

Attachment 2 - Question Answer Document

View the file

Other files for this federal contract opportunity

Other files attached to Audio/Video System Modifications - Purchase and Installation - MWRO, newest first.
File Type Posted
Attachment_1_-_Site_Visit_Attendance.pdf PDF
Sol_140P6018R0033_Amd_0002.pdf PDF
Attachment_3_-_System_Drawings.pdf PDF
Sol_140P6018R0033_Amd_0001.pdf PDF
Sol_140P6018R0033.pdf PDF
140P6018R0033_SF_18.pdf PDF
Attachment_03_-_SCA_Wage_Determinations.pdf PDF
Attachment_01_-_Combined_Synopsis_Solicitation.pdf PDF
Attachment_02_-_Scope_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q: Does the contractor have to follow the statement of work word for word or can they provide suggestions where they believe improvements are needed?

A: In this instance, the contractor may submit a Request for Information to the Contracting Officer (Diana_Vanderzanden@nps.gov). The contractor must reference the Page Number and paragraph within the Scope of Work AND identify the clarification needed.

Q: Are there technical drawings available for the system?

A: As built drawings are available for companies that require information on the current system as configured. Access to printed files are available at the customer's facility.

Q: Can equipment racks be mounted to the back wall VS the ceiling?

A: Contractors may provide individual installation methodologies if they are appropriate and in compliance with industry standards.

File details come from the government source that posted it.