A04_SOW_V2_Mainland_VC_Interior_Paint_(7-30-2026)_0001.pdf

PDF 3 MB Posted

Attached to
SERVICE, PAINT INTERIOR OF MAINLAND VISITOR CENTER
Solicitation number
140P5426Q0024
Issued by

About this file

This is a Statement of Work (SOW) for interior repainting services at Cumberland Island National Seashore's Mainland Visitor Center, issued by the National Park Service (NPS).

The contractor must repaint 1,900 square feet of interior surfaces between August 1-30, 2026, including interior walls, wood trim, interior doors, millwork, ground-level entry from breezeway, and stairwell leading to the visitor check-in counter. Required finishes include matte Sherwin Williams Emerald Interior Acrylic Latex Paint for drywall areas (color TBD), satin finish Sherwin Williams Emerald for millwork (color TBD), and extra white semi-gloss Sherwin Williams Emerald for all wood trim. All coatings must be applied by brush and roller only unless written justification and prior NPS approval is obtained for spray application. Two finish coats are required on all designated surfaces. Entry doors receive interior-face-only painting while interior doors are painted on all six sides. Surface preparation includes cleaning, light sanding, minor repairs, and primer application where needed. The contractor must protect adjacent surfaces, coordinate to minimize disruption to NPS operations, maintain safe facility access, and remove all debris and materials. Deliverables include product data submittals, color samples, two unopened gallons of each finish for touch-ups, and a comprehensive Job Specific Site Safety Plan covering general/administrative procedures, hazard communication, personal protective equipment, fall protection, and public/site safety protocols.

Three optional tasks are available: color change for millwork in the Eastern National Bookstore area using specified Sherwin-Williams colors; preparation and repainting of the steel elevator door and frame with rust-inhibitive primer and two coats of Sherwin-Williams Industrial Enamel Alkyd oil-based semi-gloss; and repainting of low-ceiling areas with Sherwin-Williams Emerald Flat White. Excluded from scope are exposed trusses and high ceilings in the visitor waiting/exhibit area.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUMBERLAND ISLAND NATIONAL SEASHORE

PMIS CUIS_349571

Repaint Interior of Mainland Visitor Center

National Park Service (NPS)

1.0 Background and Justification

The Mainland Visitor Center serves as the primary point of contact for visitors accessing Cumberland Island National Seashore. The visitor area facing area is 1900 Square Feet. Interior painted surfaces have experienced normal wear from high visitor traffic and daily operations. Repainting will improve durability, maintain a clean and professional appearance, and extend the service life of interior finishes in this visitor-facing facility.

2.0 Scope

The Contractor shall provide all labor, materials, tools, equipment, and transportation necessary to prepare and repaint interior surfaces within the Mainland Visitor Center, consisting of:

1. Interior wall surfaces

2. Wood trim

3. Interior doors

4. Millwork surfaces

5. Ground-level entry from the breezeway

6. Stairwell leading to the Visitor Check-In and Point of Sale counter

2.1 Period of Performance

CUIS is requesting that the Period of Performance be from August 1, 2026-August 30, 2026.

3.0 Tasks

3.1 Surface Preparation

The Contractor shall inspect and prepare all surfaces to receive paint. Preparation shall include cleaning, removal of dirt and contaminants, light sanding as required, and repair of minor surface imperfections. The Contractor shall apply primer where needed to cover stains, patched areas, or other irregularities that may affect finish appearance.

3.2 Protection of Adjacent Surfaces

The Contractor shall protect floors, fixtures, glazing, hardware, and adjacent finished surfaces from paint, dust, and damage during preparation and painting activities.

3.3 Application of Coatings

3.3.1: All coatings shall be applied by brush and roller. Spray application shall not be permitted unless the Contractor submits a written justification and receives prior written approval from the NPS.

3.3.2: The Contractor shall apply two (2) finish coats to all designated surfaces, including walls, trim, doors, and millwork. Coatings shall be applied in accordance with manufacturer recommendations to achieve a uniform, continuous finish free of runs, sags, or visible lap marks.

3.4 Doors and Trim

Entry doors shall be painted on the interior face only. Interior doors shall be painted on all six (6) sides. Trim and millwork shall receive a semi-gloss finish unless otherwise directed by NPS.

4.0 Requirements

1. The contractor shall use matte finish Sherwin Williams Emerald Interior Acrylic Latex Paint, or approved equivalent, to coat the drywall areas. Color TBD

2. The contractor shall use satin finish Sherwin Williams Emerald Interior Acrylic Latex Paint, or approved equivalent, to coat millwork. Color TBD

3. The contractor shall use extra white semi-gloss finish Sherwin Williams Emerald Interior Acrylic Latex Paint, or approved equivalent, to cover all wood trim.

4. All materials and application methods shall comply with manufacturer specifications.

5. Work shall be performed in a neat and professional manner.

6. The job site shall be policed and neat at the end of each workday.

7. The Contractor shall coordinate work to minimize disruption to NPS employee operations and maintain safe access through the facility at all times.

8. The NPS shall grant access to the janitorial floor sink for washout. The contractor shall be responsible for cleaning the floor sink after all wash out is completed.

9. The Contractor shall remove all debris and materials associated with the work.

5.0 Deliverables

1. Product data submittals for all coatings prior to application.

2. Color samples or drawdowns.

3. Two (2) unopened gallons of each finish for touch ups.

4. Job Specific Site Safety Plan including:

General / Administrative

1. Project info (location, scope, duration)

2. Contractor safety officer + competent persons

3. Emergency contacts (EMS, park dispatch, nearest hospital)

4. Daily safety meetings / Job Hazard Analysis (JHA) requirement

5. Accident/incident reporting procedures

Hazard Communication (REQUIRED)

1. Written HazCom program

2. Safety Data Sheets (SDS) for all coatings, solvents, cleaners

3. Labeling system

4. Employee training documentation

Personal Protective Equipment (PPE)

1. Based on coatings and methods:

2. Gloves (chemical resistant)

3. Eye protection

4. Protective clothing (especially for LBP)

5. Respiratory protection (see below)

Fall Protection

1. Ladders (setup, tie-off, angle)

2. Scaffolding (erection, inspection)

3. Tie-off requirements (typically ≥6 ft)

Public & Site Safety

1. Work zone control (barriers, signage)

2. Protection of visitors and staff

3. Restricted access areas

4. Coordination with park operations

6.0 Compliance

1. Work shall be limited to interior spaces.

2. No ground disturbance is authorized.

3. The Contractor shall ensure that all materials, debris, and washout are contained and disposed of in accordance with local, state, and federal regulations.

4. Adjacent finishes and building components shall be protected from damage during all phases of work.

7.0 Options

7.1 Color change for the millwork work in the gift shop area

Contractor shall provide pricing to top perform a color change to the millwork in the Eastern National Bookstore area.

Colors for the bookstore millwork:

Cabinets and cabinet doors: SW 6192 Coastal Plain or approved equivalent Decorative shapes on cabinet doors: SW 3637 Oyster White or approved equivalent.

7.2 Elevator Door and Frame: The Contractor shall prepare and repaint the existing steel elevator door and frame located at the ground-level entrance of the Mainland Visitor Center.

7.2.1 Surface Preparation

1. The Contractor shall remove loose paint, oxidation, and surface corrosion from the elevator frame by hand scraping, sanding, or other non-destructive mechanical means.

2. Existing coatings that remain tightly adhered shall be feathered to provide a smooth transition between existing and repaired surfaces.

3. Surface scratches, gouges, and minor dents shall be repaired using a metal-compatible filler. Repaired surfaces shall be sanded smooth prior to application of primer.

7.2.2 Priming

1. Areas exhibiting exposed steel or active corrosion shall receive one coat of a rust-inhibitive metal primer recommended by the finish coat manufacturer.

2. Primer shall be applied only after all loose corrosion has been removed and the surface has been prepared in accordance with the manufacturer's recommendations.

7.2.3 Finish Coating

1. Following primer application and curing, the Contractor shall apply two (2) finish coats of Sherwin-Williams Industrial Ename Alykd, Oil-Based, Semi-Gloss Finish, or approved equivalent, to the elevator door and frame.

2. Finish coats shall provide complete hiding and produce a uniform color and sheen free from brush marks, runs, sags, holidays, or other coating defects.

7.2.4 Protection of Elevator Components

1. The Contractor shall protect elevator operating equipment, controls, call buttons, thresholds, weather seals, identification plates, and moving components from damage and paint contamination.

2. Paint shall not be applied to hardware, weather stripping, hinges, rollers, labels, or any surface not designated for painting.

7.3 Low ceiling areas

7.3.1 Surface Preparation

1. The Contractor shall prepare and repaint the low ceiling areas within the Mainland Visitor Center as identified by the National Park Service.

2. Surface preparation shall include cleaning and removal of dust, dirt, cobwebs, and other contaminants. Minor surface imperfections shall be repaired as necessary to provide a sound substrate for painting.

7.3.2 Priming and Finish Coating

1. The Contractor shall apply one (1) primer coat where required by the manufacturer and two (2) finish coats of Sherwin-Williams Emerald® Interior Acrylic Latex Paint, Flat White, or approved equivalent.

2. Finish coats shall provide a uniform appearance free of lap marks, holidays, runs, sags, roller marks, or visible flashing.

7.3.3 Fixture Protection

1. The Contractor shall protect adjacent walls, light fixtures, HVAC diffusers, sprinkler heads, smoke detectors, signage, and other building components from paint and damage during the work.

2. Upon completion, all protective coverings shall be removed, and the work area shall be left in a clean condition.

8.0 Exclusions

1. The Scope of Work does not include exposed trusses

2. The Scope of Work does not include high Ceilings in the Visitor waiting area/exhibit area.

File details come from the government source that posted it. Updated .